Archive

Cleanup & Remediation

Coverage of DOE-EM’s multi-billion-dollar effort to address Cold War and Manhattan Project nuclear legacy waste, including tank waste treatment, site remediation, and decommissioning at Hanford, Savannah River, Oak Ridge, and other major sites.

  • Mercury Treatment Plant Construction at Oak Ridge Stands at 35%

    Construction of a plant to treat mercury-laden water stemming from building demolition at the Department of Energy’s Oak Ridge Site in Tennessee is more than a third complete, an agency spokesperson said Tuesday. Construction of the Outfall 200 Mercury Treatment Facility by a joint venture of Louisiana-based APTIM and Idaho-based North Wind is about 35% […]

  • DOE Stands Behind Nuclear Safety Management Rule in Response to DNFSB

    The Department of Energy last week defended a 2020 update to a key nuclear safety management regulation but said the agency will work with a federal nuclear watchdog over its “technical concerns” with the final rule — including as it relates to aging nuclear facilities. The DOE “continues to conclude that its current regulatory framework, […]

  • Updated Draft ROD on Oak Ridge Landfill Now Expected in October

    A second draft of the Department of Energy’s Record of Decision to build a new on-site landfill for low-level radioactive waste at the Oak Ridge Site in Tennessee is now expected in mid-October, the agency said late last week. Originally slated to appear this week, publication of the updated draft has been pushed back until […]

  • Early Figures Show 65% Vax Rate for Savannah River Remediation

    Preliminary figures show the liquid waste cleanup contractor at the Department of Energy’s Savannah River Site in South Carolina has roughly two-thirds of its workforce vaccinated against COVID-19, a spokesman said Friday. The numbers are not final because DOE certification of vaccination forms were not due until Friday, a spokesman for Amentum-led Savannah River Remediation […]

  • Biden Promises Federal-Contractor Vaccine Mandate

    Six weeks after telling unvaccinated feds and contractors to wear masks and be tested regularly for COVID-19, President Joe Biden Thursday took things a step further and said such workers must either take the vaccine or find another job.   “If you want to work with the federal government, do business with us, get vaccinated,” Biden […]

  • Former Communications Director Becomes New EM Chief of Staff

    Mike Nartker, a former communications director at the Department of Energy’s Office of Environmental Management is now chief of staff, according to a new organizational chart posted online last Wednesday. In the post, Nartker reports to DOE’s acting assistant secretary for environmental management (EM) William (Ike) White.  In addition to supporting White and principal deputy […]

  • About 74% of Tailings Removed From Moab Pile

    The Department of Energy’s cleanup contractor at a uranium mill tailings pile near Moab, Utah has moved about 74% of the radioactive material to a disposal site 30 miles away, according to an update posted online this week. In August, North Wind Portage shipped 73,923 tons of tailings and debris from the former Atlas Minerals […]

  • Stopgap Budget Should Protect Uranium Cleanup Fund, White House says

    Given the shrinking chances of Congress agreeing on fiscal year 2022 appropriations by the end of the month, the Joe Biden administration on Tuesday requested that any continuing resolution Congress passes to extend 2021 budgets protect the short-term operations of the Department of Energy’s uranium enrichment cleanups. As Weapons Complex Monitor has reported, the government […]

  • Wrap Up: Mediation Extended in SRNS Disability Suit

    A federal court mediation deadline of Sept. 16 has been set for a long time worker at the Department of Energy’s Savannah River Site in South Carolina who sued operations contractor Savannah River Nuclear Solutions last year under the Americans With Disabilities Act. Attorneys for Richard Lusby, who initially filed his case in a South […]

  • About 74% of Tailings Removed From Moab Pile

    The Department of Energy’s cleanup contractor at a uranium mill tailings pile near Moab, Utah has moved about 74% of the radioactive material to a disposal site 30 miles away, according to an update posted online this week. In August, North Wind Portage shipped 73,923 tons of tailings and debris from the former Atlas Minerals […]

  • Stopgap Budget Should Protect Uranium Cleanup Fund, White House says

    Given the shrinking chances of Congress agreeing on fiscal year 2022 appropriations by the end of the month, the Joe Biden administration on Tuesday requested that any continuing resolution Congress passes to extend 2021 budgets protect the short-term operations of the Department of Energy’s uranium enrichment cleanups. As Weapons Complex Morning Briefing has reported, the […]

  • UCOR Gives its Workforce Until November to be Vaccinated

    The Amentum-Jacobs joint venture in charge of remediating the Department of Energy’s Oak Ridge Site in Tennessee said Tuesday it will make vaccination against COVID-19 a condition of employment for its 2,000 workers. That makes the team the third DOE nuclear-site contract to mandate the vaccine, after contractors at the Savannah River Site in South […]

  • Vaccine Mandates Could Spread, Sources Say

    With two major Department of Energy nuclear site contractors having already announced plans to mandate worker vaccination against COVID-19, don’t be surprised to see others follow in coming days, sources told Weapons Complex Morning Briefing. One industry source said Friday there is a good chance at least one more major limited liability corporation at a […]

  • Former Communications Director Becomes New EM Chief of Staff

    Mike Nartker, a former communications director at the Department of Energy’s Office’s Office of Environmental Management is now chief of staff, according to a new organizational chart posted online last Wednesday. In the post, Nartker reports to DOE’s acting assistant secretary for environmental management (EM) William (Ike) White.  In addition to supporting White and principal […]

  • Radwaste Summit Rescheduled for November

    The Exchange Monitor’s RadWaste Summit has been rescheduled to Nov. 3-5 at the J.W. Marriott Las Vegas Resort and Spa in Summerlin, Nev. For more information, please contact Beth Wagner, associate brand director for the RadWaste Summit.

  • House Committee’s 2022 NDAA Authorizes Big Outlay for Defense Cleanup

    The House Armed Services Committee’s version of the National Defense Authorization Act for fiscal 2022 would authorize the full $6.84 billion sought by the Joe Biden administration for Defense Environmental Cleanup at Department of Energy nuclear sites, according to the chairman’s mark. The House Armed Services Committee early Thursday approved its version of the 2022 […]

  • Portsmouth Cleanup Contractor Pockets 85% of Potential Fee

    Overall, Fluor-BWXT Portsmouth claimed $30 million, or 85% of a potential $35.3 million in total available fee, for its work at the Department of Energy’s Portsmouth Site for an 18-month period ending March 31. The Fluor-led contractor earned $7.4 million or 70% out a potential $10.6 million in subjective fee, according to the scorecard from […]

  • Momentum Builds for Employee Vax Orders Across Weapons Complex

    There have been 29 deaths from COVID-19 across the Department of Energy’s nuclear cleanup enterprise, 6,141 confirmed cases since the pandemic began and at least two prime contractors at major federal sites that say they will order employees to get vaccinated. Those are a few of the pre-Labor Day developments confirmed by Weapons Complex Monitor […]

  • Veolia Wins 89% of Fee in Final 7 Months at 222-S Lab

    Veolia earned about 89% of its potential fee from the Department of Energy during its last seven months of analytic work at the Department of Energy’s 222 S Laboratory at the Hanford Site in Washington state. That is according to a fee scorecard published by DOE earlier this month. A Veolia unit took home $148,707 […]

  • Wrap Up: Odors Prompt Temporary Hanford Take-Cover Order; WIPP Plans Panels

    The Department of Energy’s Hanford Site in Washington state lifted a take cover order about four hours after workers detected strange odors Wednesday morning in the 200 West Area of the cleanup complex. Crews investigating reports of odors near the Reduction Oxidation (REDOX) plant found no evidence of radiation or a chemical release near the […]

  • Judge Says SBA Erred in Finding Swift & Staley Too Big for Set-Aside

    An appeals panel within the Small Business Administration erred in May when it found Swift & Staley was too big to qualify for a $160-million Department of Energy set-aside contract for services at the Paducah Site in Kentucky, a U.S. Court of Federal Claims Judge ruled. The ruling turned on whether a Swift & Staley […]

  • UCOR Reaps 98% of Potential Fee in 1H 2021

    For the second review period in a row UCOR, the Amentum-Jacobs cleanup team at the Oak Ridge Site in Tennessee, is pocketing 98% of its potential fee from the Department of Energy. The contractor earned 100% of its almost $7.9 million potential fee for the first half of fiscal 2021, from Oct. 1, 2020 through […]

  • West Valley Contractor Eyes Demo of Main Plant Building Early Next Year

    The Department of Energy’s Jacobs-led contractor for remediation of the West Valley Demonstration Project in western New York could begin taking down the Main Plant Process Building this year, a manager said at a public meeting Wednesday. Deactivation of the contaminated facility should be finished later this fall, although the schedule could always slip due […]

  • Centerra Bid Protest on SRS Security Contract Dismissed for Now

    The Government Accountability Office has formally dismissed a bid protest brought last month by incumbent Centerra over the Department of Energy’s $1-billion security contract award to a rival at the Savannah River Site in South Carolina — but that might not be the end of the dispute. In a notice dated Aug. 9, the Government […]

  • State, DOE to Discuss Plans for New Waste Panels at WIPP

    A public meeting is set for 5 p.m. Mountain Time today as the New Mexico Environment Department reviews plans by the Department of Energy and its prime contractor for two new underground disposal panels at the Waste Isolation Pilot Plant near Carlsbad. The Amentum-led Nuclear Waste Partnership, which includes BXW Technologies, will present information on […]

  • Take Cover Order Lifted Hours After Hanford Workers Smell Odors

    The Department of Energy’s Hanford Site in Washington state lifted a take cover order about four hours after workers detected strange odors Wednesday morning in the 200 West Area of the cleanup complex. Crews investigating reports of odors near the Reduction Oxidation (REDOX) plant found no evidence of radiation or a chemical release near the […]

  • UCOR Reaps 98% of Potential Fee in 1H 2021

    For the second review period in a row UCOR, the Amentum-Jacobs cleanup team at the Oak Ridge Site in Tennessee, is pocketing 98% of its potential fee from the Department of Energy. The contractor earned 100% of its almost $7.9 million potential fee for the first half of fiscal 2021, from Oct. 1, 2020 through […]

  • Portsmouth Cleanup Contractor Pockets 85% of Potential Fee

    Overall, Fluor-BWXT Portsmouth claimed $30 million, or 85% of a potential $35.3 million in total available fee, for its work at the Department of Energy’s Portsmouth Site for an 18-month period ending March 31. The Fluor-led contractor earned $7.4 million or 70% out a potential $10.6 million in subjective fee, according to the scorecard from […]

  • Judge Says SBA Miscounted Size of Swift & Staley JV in Ruling Out Company for Small Biz Award

    An appeals panel within the Small Business Administration erred in May when it found Swift & Staley was too big to qualify for a $160-million Department of Energy set-aside contract for services at the Paducah Site in Kentucky, a U.S. Court of Federal Claims Judge ruled. The ruling turned on whether a Swift & Staley […]

  • West Valley Contractor Eyes Demo of Main Plant Building Early Next Year

    The Department of Energy’s Jacobs-led contractor for remediation of the West Valley Demonstration Project in western New York could begin taking down the Main Plant Process Building this year, a manager said at a public meeting Wednesday. Deactivation of the contaminated facility should be finished later this fall, although the schedule could always slip due […]