Home to the Kansas City National Security Campus, an NNSA facility operated by Honeywell that manufactures non-nuclear components for the nuclear weapons stockpile.

  • Livermore, Kansas City execs discuss nuclear modernization

    The United States nuclear weapons enterprise must be flexible, scalable and collaborative in coming years in a world where Russia and China are rapidly modernizing their nuclear triad, officials said during a Tuesday webinar held by the Advanced Nuclear Weapons Alliance (ANWA) Deterrence Center. Kim Budil, director of the Lawrence Livermore National Laboratory, and Eric […]

  • NNSA completes KC NeXT Phase 1

    The Department of Energy’s National Nuclear Security Administration (NNSA) said it completed the first phase of its Kansas City Non-Nuclear Expansion Transformation (KC NeXT) at its Kansas City National Security Campus. “In a rapidly changing national security environment, modernizing the enterprise to be more adaptive, agile, responsive, and resilient is more critical than ever before,” […]

  • NNSA completes KC NeXT Phase 1

    The Department of Energy’s National Nuclear Security Administration (NNSA) said it completed the first phase of its Kansas City Non-Nuclear Expansion Transformation (KC NeXT) at its Kansas City National Security Campus. “In a rapidly changing national security environment, modernizing the enterprise to be more adaptive, agile, responsive, and resilient is more critical than ever before,” […]

  • Phase 1 of Kansas City expansion expected in June, acting NNSA site boss says

    ARLINGTON, VA. – Kansas City National Security Campus (KCNSC) will complete the first phase of a real estate acquisition project that will add 2 million square feet of office and manufacturing space this June, the site’s acting manager said last week. Shekita Robinson spoke at a panel of the National Nuclear Security Administration’s (NNSA) field […]

  • Phase 1 of Kansas City expansion expected in June, acting NNSA site boss says

    ARLINGTON, VA. – Kansas City National Security Campus (KCNSC) will complete the first phase of a real estate acquisition project that will add 2 million square feet of office and manufacturing space this June, the site’s acting manager said last week. Shekita Robinson spoke at a panel of the National Nuclear Security Administration’s (NNSA) field […]

  • DOE eyes weapons complex for building data centers

    The Department of Energy is seeking feedback on how 16 installations, mostly in the weapons complex, stack up as potential spots to develop artificial intelligence data centers. Energy Secretary Chris Wright said Thursday April 3 that DOE is issuing a request for information on how the 16 federal properties might work for permitting and construction […]

  • Exchange Monitor 2024 U.S. election digest

    Editor’s note: the election digest tracks lawmakers whose constituencies include Department of Energy nuclear sites. Most lawmakers with big nuclear constituencies look, as usual, safe to win reelection this November. However, a few are retiring and some are in tight races. The Exchange Monitor’s election digest is tracking them all. Among the expected Senate retirees […]

  • Mo. Senate passes KCNSC tax bill after nixing proposal to add waste-cleanup aid

    Missouri state senators this week passed a bill to provide tax breaks for the expansion of the National Nuclear Security Administration’s factory for non-nuclear nuclear-weapon parts. The bill now heads to the state legislature’s House of Representatives, where it had not been scheduled for a vote at deadline Friday for Nuclear Security & Deterrence Monitor. […]

  • Replacement ICBM fuse closes in on milestone that precedes mass production

    The Kansas City National Security Campus in March produced a proof-of-concept replacement fuse for an Air Force nuclear weapon, the Sandia National Laboratory said last week. The Missouri site cranked out the first production unit for the Mark 21 Replacement Fuze, Sandia said in a press release. After this unit clears several more reviews, the […]

  • Replacement ICBM fuse closes in on milestone that precedes mass production

    The Kansas City National Security Campus in March produced a proof-of-concept replacement fuse for an Air Force nuclear weapon, the Sandia National Laboratory said last week.  The Missouri site cranked out the first production unit for the Mark 21 Replacement Fuze, Sandia said in a press release. After this unit clears several more reviews, the […]

  • Rogers asks for briefing about planned factory with alleged Chinese ties near KCNSC

    A U.S. Senator asked Tuesday if a planned manufacturing plant in Kansas poses a threat to the National Nuclear Security Administration’s nearby factory in Missouri for non-nuclear nuclear-weapon components. The conservative publication Daily Caller in December reported that Cnano Technology USA Inc., a company the publication said has ties to Chinese businesses, planned to build […]

  • Mo. legislature plans tax breaks for KCNSC extension

    The Missouri House of Representatives this week passed bills that would give tax breaks for the planned expansion of the Kansas City Nuclear Security Campus in Missouri. The state’s 163-member House of Representatives passed the bills Thursday, sending them on to the Senate, which had not scheduled a vote as of deadline for Nuclear Security […]

  • Mo. legislature plans tax breaks for KCNSC extension

    The Missouri House of Representatives was set to vote as soon as this week on bills that would give tax breaks for the planned expansion of the Kansas City Nuclear Security Campus in Missouri.  On Monday, the legislation was on the informal third reading calendar of the state’s 163-member House of Representatives, meaning the measure […]

  • Rogers asks for briefing about planned factory with alleged Chinese ties near KCNSC

    A U.S. Senator asked Tuesday if a planned manufacturing plant in Kansas poses a threat to the National Nuclear Security Administration’s nearby factory in Missouri for non-nuclear nuclear-weapon components. The conservative publication Daily Caller in December reported that Cnano Technology USA Inc., a company the publication said has ties to Chinese businesses, planned to build […]

  • Kansas City campus marks 75 years since taking over nuke component manufacturing mission

    The Kansas City National Security Campus in Missouri, which manufactures most of the non-nuclear components of U.S. nuclear weapons celebrates its diamond anniversary next month. Initially dedicated by then-Senator Harry Truman in 1942, what began as a Pratt & Whitney plant building Double Wasp radial engines for a variety of World War II aircraft, the […]

  • GAO: Kansas City Site struggling to meet staffing, supply chain needs 

    Staffing at the Kansas City National Security Campus can’t match its current workload and may not meet the demands of the next series of nuclear weapons life extensions, according to a recent report.  The National Nuclear Security Administration’s (NNSA) Kansas City site, managed for the agency by Honeywell Federal Manufacturing and Technologies, makes the non-nuclear […]

  • GAO: Kansas City Site struggling to meet staffing, supply chain needs 

    Staffing at the Kansas City National Security Campus can’t match its current workload and may not meet the demands of the next series of nuclear weapons life extensions, according to a recent report.  The National Nuclear Security Administration’s (NNSA) Kansas City site, managed for the agency by Honeywell Federal Manufacturing and Technologies, makes the non-nuclear […]

  • Wrap Up: Fluor unit lands UK contract, indictment alleges nuclear parts kickbacks, study out on culling wild pigs around SRS

    Fluor subsidiary Stork UK has landed a three-year contract to provide inspection and quality assurance services to Sellafield Limited’s nuclear site in the United Kingdom, Fluor said in a Thursday press release. The new contract is scheduled to start in November and has two single-year follow-on option periods, Fluor said in the release. The announcement […]

  • Honeywell dinged for conducting firearms training at too-hot Kansas City firing range

    The Department of Energy is wagging its enforcement finger at Honeywell, which manages five of its nuclear security sites, for conducting firearms training for security personnel in sweltering heat at the Kansas City National Security Campus. On May 11, 2022, when it was 85 degrees outside, Honeywell conducted outdoor firearms training and qualification activities at […]

  • Honeywell dinged for conducting firearms training at too-hot Kansas City firing range

    The Department of Energy is wagging its enforcement finger at Honeywell, which manages five of its nuclear security sites, for conducting firearms training for security personnel in sweltering heat at the Kansas City National Security Campus.  On May 11, 2022, when it was 85 degrees outside, Honeywell conducted outdoor firearms training and qualification activities at […]

  • Honeywell reports rising earnings in Q1, though commercial aviation takes the honors

    Earnings rose for Honeywell in the 1st quarter of 2023, which the aerospace and defense contractor, leading trans at five Department of Energy nuclear sites attributed mostly to a growth in commercial aviation. The company generated $1.4 billion in net income in the first quarter, about $300 million better than the first quarter of 2022, […]

  • With KCNSC in ‘dire need’ of more space, NNSA cuts sole-source contract to real estate broker

    The National Nuclear Security Administration sole-sourced a real-estate development contract to Tucson, Ariz.-based Tierra Right of Way to procure a parcel of land for the Kansas City National Security Campus in Missouri, which is “in dire need of new facilities.” The Kansas City National Security Campus, operated by Honeywell Federal Manufacturing and Technologies, is the […]

  • With KCNSC in ‘dire need’ of more space, NNSA cuts sole-source contract to real estate broker

    The National Nuclear Security Administration sole-sourced a real-estate development contract to Tucson, Ariz.-based Tierra Right of Way to procure a parcel of land for the Kansas City National Security Campus in Missouri, which is “in dire need of new facilities.” The Kansas City National Security Campus, operated by Honeywell Federal Manufacturing and Technologies, is the […]

  • Enterprise Assessments Checking Out Summer Head Injury at Kansas City

    The Department of Energy’s Enterprise Assessments office, one of the agency’s internal watchdogs, will check out an incident last summer at the Kansas City National Security Campus that resulted in one employee getting what the site called a mild concussion. Among the things the watchdog will look at — in the wake of the employee […]

  • Enterprise Assessments Checking Out Summer Head Injury at Kansas City

    The Department of Energy’s Enterprise Assessments office, one of the agency’s internal watchdogs, will check out an incident last summer at the Kansas City National Security Campus that resulted in one employee getting what the site called a mild concussion. Among the things the watchdog will look at — in the wake of the employee […]

  • About 100 Heads at Kansas City East Already, FM&T Says

    About 100 people are already working at a new Kansas City National Security Campus satellite facility that opened in October just down the road from the National Nuclear Security Administration’s main factory for non-nuclear nuclear weapon parts, a spokesperson said Tuesday. For the moment, however, Building 23 — also called Kansas City East — is […]

  • KCNSC ‘Christening’ New Manufacturing Space in Fall

    An auxiliary manufacturing space, known as Kansas City East and Building 23, should be christened in the fall, the president of the National Nuclear Security Administration’s main non-nuclear parts maker said this week. The headcount at the Kansas City National Security Campus (KCNSC) is “currently around 5,500 with plans growing to 6,000 here before the […]

  • KCNSC ‘Christening’ New Manufacturing Space in Fall

    An auxiliary manufacturing space, known as Kansas City East and Building 23, should be christened in the fall, the president of the National Nuclear Security Administration’s main non-nuclear parts maker said Tuesday. The headcount at the Kansas City National Security Campus (KCNSC) is “currently around 5,500 with plans growing to 6,000 here before the end […]

  • Subcontractor, Poor Communication Blamed in IG Report About Wonky Component Manufactures at KCNSC

    Lack of communications between the Sandia National Laboratories and the Kansas City National Security Campus resulted in some improperly manufactured flex cables, and separately in the Missouri manufacturing facility accepting other flex cables that failed  post-manufacturing tests, the Department of Energy’s inspector general reported recently. Someone who tipped off the IG in 2019 about the […]

  • Subcontractor, Poor Communication Blamed in IG Report About Wonky Component Manufactures at KCNSC

    Lack of communications between the Sandia National Laboratories and the Kansas City National Security Campus resulted in some improperly manufactured flex cables, and separately in the Missouri manufacturing facility accepting other flex cables that failed  post-manufacturing tests, the Department of Energy’s inspector general reported recently. Someone who tipped off the IG in 2019 about the […]