Coverage of DOE-EM’s multi-billion-dollar effort to address Cold War and Manhattan Project nuclear legacy waste, including tank waste treatment, site remediation, and decommissioning at Hanford, Savannah River, Oak Ridge, and other major sites.

  • Cleanup Complex at DOE Has More than 430 Ongoing Cases of COVID-19

    The nuclear cleanup properties overseen by the Department of Energy’s Office of Environmental Management had 431 active cases of COVID-19 as of the close of business Wednesday. The figure, shared in a Thursday email by an Environmental Management (EM) spokesperson, is a jump from the 366 active cases reported by the office one week before […]

  • Los Alamos Prepped for Tritium-bearing Container Venting; Waiting on New Mexico Approval

    The Los Alamos National Laboratory has finished technical preparations to vent the headspace of some tritium-bearing waste drums that cannot be disposed of until they’re depressurized, but the operation is on hold until after the winter, pending the approval of the state of New Mexico. The National Nuclear Security Administration (NNSA) and lab contractor Triad […]

  • DOE Pulls Plug on $13B Hanford Tank Closure Contract Award

    Just before Christmas, and months after two losing teams protested the award, the Department of Energy canned a $13-billion liquid-waste cleanup contract awarded in May to a BWX Technologies-led team. In a Dec. 23 memo to Hanford employees, DOE said it scrapped the Tank Closure Contract because it wants to combine that work — emptying […]

  • Atkins-led Team Fails to Win Attorney Fees in GAO Case

    The Government Accountability Office says Hanford Tank Closure Co., made up of Atkins, Amentum and Westinghouse Government Services, is not entitled reimbursement of its legal costs for protesting a $13-billion tank closure contract issued in May by the Department of Energy. In a November decision published this month, the Government Accountability Office (GAO) said the […]

  • DOE Clears Transition to New Hanford 222-S Laboratory Contractor

    Navarro-led Hanford Laboratory Management and Integration on Monday received notice from the Department of Energy to begin taking over the 222-S Laboratory at the Hanford Site in Washington state. Located in the 200-West Area of the former plutonium complex, the primary purpose of the 70,000 square foot lab is to provide analytical support for the […]

  • Centerra-SRS Racks Up About 98% of Potential Fee for Paramilitary Work

    The Department of Energy said Monday that Centerra, the paramilitary security contractor at the Savannah River Site in South Carolina, is taking home roughly 98% of its potential $6.73 million in fee for the 12 months ended Oct. 7. Centerra-Savannah River Site will pocket $6.58 million for providing an armed and uniformed security force for […]

  • Oak Ridge RFP Questions Due Tonight

    The Department of Energy reiterated in Dec. 23 online comments that questions on the long-term contract, potentially worth up to $8.3-billion, at the Oak Ridge Site in Tennessee, are due at 11:59 p.m. Eastern Time today, Monday Dec. 28. In answer to a question submitted by a potential bidder, the DOE stressed any questions should […]

  • With Cleanup Complete, DOE Transfers SPRU Property to Naval Reactors Office

    The Department of Energy’s Office of Environmental Management said Dec. 21 that it has transferred the Separations Process Research Unit in New York from the nuclear cleanup office to the DOE Office of Naval Reactors as of Dec. 16. The DOE announced the transfer of the Separations Process Research Unit (SPRU) areas from the Office […]

  • UCOR Pockets 98% of Potential Fee for Oak Ridge Cleanup Work in Latter Fiscal 2020

    UCOR, the Amentum-Jacobs team in charge of remediation at the Department of Energy’s Oak Ridge Site in Tennessee, earned 98% of its potential fee, almost $28 million, for its work for the final six months of fiscal 2020. The joint venture earned 100% of its $20.8 million in objective fee for meeting deadlines and accomplishing […]

  • COVID-19 Keeps Spreading During Christmas Holiday

    The COVID-19 pandemic did not take a holiday during Christmas week, with new infections reported at Department of Energy nuclear cleanup operations such as the Hanford Site in Washington state and the Waste Isolation Pilot Plant in New Mexico. Supervisors at the Waste Isolation Pilot Plant (WIPP) were notified of nine positive COVID-19 cases between […]

  • Nuke Cleanup Sites Could Become Home for New Reactors

    Cold War and Manhattan Project locations being cleaned up by the Department of Energy could be viable candidates for new nuclear power plants, a federal official said during an online presentation Wednesday. About a dozen of the 16 nuclear cleanup properties run by the DOE Office of Environmental Management (EM) boast “unique characteristics” potentially attractive […]

  • Nuke Cleanup Sites Could Become Home for New Reactors

    Cold War and Manhattan Project locations being cleaned up by the Department of Energy could be viable candidates for new nuclear power plants, a federal official said during an online presentation Wednesday. About a dozen of the 16 nuclear cleanup properties run by the DOE Office of Environmental Management (EM) boast “unique characteristics” potentially attractive […]

  • Navarro-led Group Expected to Start 222-S Transition Right After New Year’s

    A group led by Navarro Research and Engineering is expected to start its transition Jan. 4 as the new contractor at the Department of Energy’s Hanford Site in Washington state, a source said this week. Hanford’s DOE site manager, Brian Vance, said last week during an appearance before the Hanford Advisory Board to expect the […]

  • Top Hanford Fed Expects 3 Crumbling Structures to be Stabilized in January

    The Department of Energy’s manager for the Hanford Site in Washington state expects the stabilization of three crumbling underground waste structures near the Plutonium Finishing Plant to be shored up by the end of January. “We expect to complete that project by the end of January,” Hanford’s site manager Brian Vance told a meeting of […]

  • New Mexico Frustrated With DOE’s Slow Progress on Cleanup of Los Alamos Road Site

    The New Mexico Environment Department is still waiting on the Department of Energy to provide more details on the planned remediation of contamination discovered earlier this year on a public road outside the Los Alamos National Laboratory. The preliminary screening plan that will determine if the hazardous constituents at the 28-acre DP Road site are […]

  • Megabuck Oak Ridge Remediation RFP Hits the Street

    The Department of Energy’s Office of Environmental Management on Friday issued its final request for proposals for the Oak Ridge Reservation Cleanup Contract in Tennessee. The potential $8.3 billion indefinite-delivery/indefinite-quantity contract has an ordering period of 10 years and the completion of the task orders are expected within 15 year, DOE said in a Friday […]

  • PUBLICATION NOTICE

    Weapons Complex Monitor will not publish next week in observance of the Christmas holiday, nor the week after, in observance of New Year’s Day. Look for the next issue in your inbox on Friday, Jan. 8. Happy 2021!

  • Nuke Cleanup Sites Could Become Home for New Reactors

    Cold War and Manhattan Project locations being cleaned up by the Department of Energy could be viable candidates for new nuclear power plants, a federal official said during an online presentation Wednesday. About a dozen of the 16 nuclear cleanup properties run by the DOE Office of Environmental Management (EM) boast “unique characteristics” potentially attractive […]

  • PUBLICATION NOTICE

    Weapons Complex Morning Briefing will not publish next week in observance of the Christmas holiday. Look for the next issue in your inbox on Monday, Dec. 28.

  • Public Hearing Planned on Modifying Hanford Effluent Facilities

    The Washington state Department of Ecology will hold an online public hearing Jan. 21 on proposed modifications to certain facilities at the Department of Energy’s Hanford Site. The DOE and contractor Washington River Protection Solutions seek a class 2 modification to allow expansion of loading areas at the Liquid Effluent Retention Facility and the 200 […]

  • SRS Area Congressman Tests Positive for COVID-19

    Rep. Joe Wilson (R-S.C.), whose district includes the Savannah River Site, has tested positive for COVID-19, the congressman’s office said in a statement late Wednesday. “Earlier this evening I learned that I have tested positive for COVID-19,” Wilson said in the written statement posted to his website. “I will be taking all necessary precautions, as […]

  • Navarro-led Group Expected to Start 222-S Transition Right After New Year’s

    A group led by Navarro Research and Engineering is expected to start its transition Jan. 4 as the new contractor at the Department of Energy’s Hanford Site in Washington state, a source said Tuesday. Hanford’s DOE site manager, Brian Vance, said last week during an appearance before the Hanford Advisory Board to expect the new […]

  • Draft Decision on Oak Ridge Landfill Now Anticipated in Mid-2021

    The draft Record of Decision on a proposed 2.2-million-cubic yard landfill for the Department of Energy’s Oak Ridge Site in Tennessee is being delayed once again, with the new publication target being next July. The document was previously scheduled for publication this week by the DOE Office of Environmental Management at Oak Ridge. But spokespeople […]

  • CORRECTIONS:

    An article in Weapons Complex Morning Briefing [“Meeting on LANL Stormwater Scheduled for This Week,” Dec. 15, 2020] should have identified Huntington Ingalls Industries as the lead partner in Newport News Nuclear BWXT Los Alamos (N3B). An article in Weapons Complex Morning Briefing [“Law Pausing Ohio Nuclear Plant Subsidies To Be Heard Tuesday,” Dec. 14, […]

  • Top Hanford Fed Expects 3 Crumbling Structures to be Stabilized in January

    The Department of Energy’s manager for the Hanford Site in Washington state expects the stabilization of three crumbling underground waste structures near the Plutonium Finishing Plant to be shored up by the end of January. “We expect to complete that project by the end of January,” Hanford’s site manager Brian Vance told a meeting of […]

  • Meeting on LANL Stormwater Scheduled for This Week

    The Department of Energy and its legacy cleanup contractor for the Los Alamos National Laboratory will discuss 2021 plans for improved stormwater runoff around the lab during a public meeting Wednesday evening. It is the second of two required semiannual meetings by DOE’s Office of Environmental Management at the federal complex and remediation contractor, Newport […]

  • 14 Cases of COVID-19 Reported at Hanford Over Weekend

    Fourteen new cases of the coronavirus were confirmed at the Department of Energy’s Hanford Site in Washington state over the weekend, putting the site’s cumulative case count at more than 500 since the pandemic hit the U.S. in January. Eight workers at the former plutonium production facility informed management Friday they had tested positive for […]

  • New Mexico Frustrated With DOE’s Slow Progress on Cleanup of Los Alamos Road Site

    The New Mexico Environment Department is still waiting on the Department of Energy to provide more details on the planned remediation of contamination discovered earlier this year on a public road outside the Los Alamos National Laboratory. The preliminary screening plan that will determine if the hazardous constituents at the 28-acre DP Road site are […]

  • 74 Workers Sign Up for Early Buyout at Fluor-BWXT

    Seventy-four employees have agreed to take a voluntary buyout from the decommissioning and demolition contractor at the Department of Energy’s Portsmouth Site in Ohio. Fluor-BWXT Portsmouth announced the results of its Self-Select Voluntary Separation Program in a Wednesday email statement. The voluntary buyout package includes a severance based on years of service and the applicable […]

  • Fluor Idaho Pays $580K Penalty Over 2018 Drum Breach

    After reviewing its options, cleanup contractor Fluor Idaho has decided to pay the $580,700 civil penalty issued by the Department of Energy over an April 2018 explosion at the Idaho National Laboratory where four 55-gallon drums overheated and blew off their lids spewing radioactive sludge. “Fluor Idaho chose not to contest the findings” in the […]