DOE Delays Draft Solicitation of Hanford Central Plateau Cleanup Contract
The Department of Energy delayed the release of a draft request for proposals for further cleanup of the Hanford Site’s central plateau until some time between now and Sept. 30, the agency announced Tuesday. “The Central Plateau Cleanup Contract (CPCC) Draft Request For Proposal is now anticipated to be released by the end of the […]
-
National Laboratories
NukeWatch Suit Can Go Forward, But Judge Won’t Nix 2016 Order
Nuclear Watch New Mexico (NukeWatch) can continue to pursue its lawsuit against the Energy Department and its former Los Alamos National Laboratory (LANL) contractor for failing to do certain tasks spelled out in a 2005 consent order, but a federal judge won’t throw out a revised 2016 settlement between DOE and the state of New […]
-
Cleanup & Remediation
Energy Department Seeks Vendor Information on F-Yard Cleanup at SPRU
The Energy Department is seeking feedback from small business contractors who might be interested in cleaning up the F-Building Storage Yard (F-Yard) at the Separations Process Research Unit (SPRU) facility near Schenectady, N.Y. The department’s Office of Environmental Management said Tuesday it is issuing a request for information (RFI)/sources sought, in order to connect with […]
-
Cleanup & Remediation
AECOM Executive McQuinn to Retire by September
Bob McQuinn, an AECOM senior executive who, among other things, led the prime contractor team for the Energy Department’s Waste Isolation Pilot Plant (WIPP), for about a year following a 2014 accident, has announced he will retire at the end of August. McQuinn is vice president of the company’s performance assurance and high-level waste sector. […]
-
Cleanup & Remediation
DOE Wants to Start Filling Second PUREX Tunnel in August; Washington State Wants to Wait
To prevent it from collapsing, the Department of Energy wants to start filling a second PUREX plant waste storage tunnel at the Hanford site with concrete-like grout in August — before the end of a scheduled public comment period about the effort. The Washington State Department of Ecology, lead state regulator at Hanford, plans a 45-day […]
-
Cleanup & Remediation
EPA to Release Public Comments on West Lake Cleanup Plan
The Environmental Protection Agency is scheduled today to release the public comments it received in recent months regarding its preferred plan for cleanup of the radioactively contaminated West Lake Landfill in Missouri. The agency in February announced its “partial excavation” approach, in which it would remove soil contaminated at 52.9 picocuries per gram or more to 16 […]
-
Cleanup & Remediation
Washington Ecology Plans Public Hearings on PUREX Aug. 27 and 29
The Washington state Department of Ecology will kick off a 45-day public comment period in mid-August to take input on proposed changes by the Energy Department and CH2M Hill Plateau Remediation to the PUREX Storage Tunnels at the Hanford Site. There are two public hearings slated, one Aug. 27 at 5:30 p.m., at the Richland, […]
-
Cleanup & Remediation
Hanford Firefighter Officers Sue for Overtime Back Pay
A dozen current and former fire captains or platoon sergeants at the Hanford site in Washington state are seeking overtime back pay and damages in a federal lawsuit filed against site-wide services contractor Mission Support Alliance (MSA). The plaintiffs say MSA owes them overtime pay, equal to one-and-a-half times their normal hourly wage, for time […]
-
Cleanup & Remediation
Prep Work Continues for On Site Disposal Cell at Portsmouth, DOE Says
The Energy Department and contractor Fluor-BWXT Portsmouth expect soil excavation and installation of necessary infrastructure for a planned on-site radioactive waste disposal cell at the Portsmouth Site in Ohio should be completed in fiscal 2019. Recent progress includes setting up trailers for work crews, installing security fencing along the perimeter of the site, including sedimentation […]
-
National Laboratories
Savannah River Lab Missions Resume After Two-Month Safety Pause
All Savannah River National Laboratory (SRNL) operations resumed at the end of June, following a two-month pause on all missions considered not essential to maintaining safety. Lab management initiated the pause due to growing concerns over the facility’s safety culture. The Department of Energy lab in South Carolina has been in management-controlled operations since June […]
-
Vitrification & Grout
Washington State Issues First Operations Permit for WTP
The Washington state Department of Ecology has issued an operations permit for the analytical laboratory for the Waste Treatment and Immobilization Plant (WTP) at the Department of Energy’s Hanford Site. This permit, issued in the spring, is the state agency’s first operations approval for the plant being built by Bechtel to turn Hanford’s radioactive tank […]
-
Cleanup & Remediation
Wrap Up: DOE Queries Potential Vendors for Brookhaven Stack Demo
The Energy Department’s Office of Environmental Management on Tuesday released a request for information and sources sought inquiry for stack dismantlement at the Brookhaven National Laboratory on Long Island, N.Y. The Environmental Management office is planning an upcoming solicitation for a contractor to decommission, tear down, and conduct site clearance for the High Flux Beam […]
-
Interim Storage & Waste Disposal
DOE Plans to Move Small Amount of Spent Fuel to Idaho National Lab
The Energy Department is seeking Nuclear Regulatory Commission approval for a one-time shipment of 2.5 kilograms of spent nuclear fuel material from the Oak Ridge National Laboratory in Tennessee to the Idaho National Laboratory for research purposes. The nuclear regulator said June 26 it had received DOE’s application for approval of a shipment route and […]
-
Cleanup & Remediation
Hanford Waste Burial Ground Cleanup Verified Complete
The parties to the Tri-Party Agreement on environmental remediation of the Hanford Site in Washington state have verified that the challenging cleanup of the 618-10 Burial Ground has been completed. That meets the deadline under the agreement for completion of the project by the end of this fiscal year, according to the Department of Energy. […]
-
Cleanup & Remediation
After Losing Suit, Former Savannah River Employee Must Pay Printing Costs
After Losing Suit, Former Savannah River Employee Must Pay Printing Costs In what should be the final chapter of a federal discrimination lawsuit, a former employee of the Savannah River Site’s management and operations contractor has been ordered to pay the company $908.45 for the cost of documents printed documents over the course of the […]
-
Contracts & Procurement
Fluor-BWXT’s Portsmouth Cleanup Contract Option to Expire in September
The current 30-month option period for Fluor-BWXT Portsmouth’s $3.4 billion decontamination and decommissioning contract for the Energy Department’s Portsmouth Site in Piketon, Ohio, is scheduled to expire Sept. 30. While a DOE spokesperson confirmed Tuesday the contract has not been extended beyond Sept. 30, other details were sparse. The Energy Department has not said if […]
-
Contracts & Procurement
RSI EnTech Chief Proud of Scorecard; Looks for More DOE Complex Biz
Although RSI EnTech did not win a recently announced successor contract for technical support services at the Energy Department’s Portsmouth Site in Ohio, company President Paul Clay thinks the 97 percent rating on a new performance scorecard demonstrates the firm’s caliber of work. RSI EnTech’s current $51 million, five-year contract at Portsmouth expires at the […]
-
National Laboratories
Savannah River Lab Missions Resume After Two-Month Safety Pause
All Savannah River National Laboratory (SRNL) operations resumed at the end of June, following a two-month pause on all missions considered not essential to maintaining safety. Lab management initiated the pause due to growing concerns over the facility’s safety culture. The Department of Energy lab in South Carolina has been in management-controlled operations since June […]
-
Cleanup & Remediation
After Losing Lawsuit, Former Savannah River Employee Must Pay Printing Costs
In what should be the final chapter of a federal discrimination lawsuit, a former employee of the Savannah River Site’s management and operations contractor has been ordered to pay the company $908.45 for the cost of printed documents over the course of the two-year case. U.S. District Judge J. Michelle Childs issued her decision on […]
-
Cleanup & Remediation
Pruitt Exit Won’t Change West Lake Cleanup Plan, EPA Says
The resignation of controversy-plagued Environmental Protection Agency Administrator Scott Pruitt will not change the federal approach for cleanup of the radioactively contaminated West Lake Landfill in Missouri, according to the agency. On July 5, Pruitt submitted his resignation to President Donald Trump following a 17-month term in office in which he was battered by a […]
-
Interim Storage & Waste Disposal
DOE Plans to Move Small Amount of Spent Fuel to Idaho National Lab
The Energy Department is seeking Nuclear Regulatory Commission approval for a one-time shipment of 2.5 kilograms of spent nuclear fuel material from the Oak Ridge National Laboratory in Tennessee to the Idaho National Laboratory for research purposes. The nuclear regulator said June 26 it had received DOE’s application for approval of a shipment route and […]
-
Cleanup & Remediation
Savannah River Lab Missions Resume After Two-Month Safety Pause
All Savannah River National Laboratory (SRNL) operations resumed at the end of June, following a two-month pause on all missions considered not essential to maintaining safety. Lab management initiated the pause due to growing concerns over the facility’s safety culture. The Department of Energy lab in South Carolina has been in management-controlled operations since June […]
-
Contracts & Procurement
Fluor-BWXT’s Portsmouth First Cleanup Contract Option to Expire in September
The current 30-month option period for Fluor-BWXT Portsmouth’s $3.4 billion decontamination and decommissioning contract for the Energy Department’s Portsmouth Site in Piketon, Ohio, is scheduled to expire Sept. 30. While a DOE spokesperson confirmed Tuesday the contract has not been extended beyond Sept. 30, other details were sparse. The Energy Department has not said if […]
-
Cleanup & Remediation
Energy Department Queries Potential Contractors for Brookhaven Stack Demo
The Energy Department’s Office of Environmental Management on Tuesday released a request for information and sources sought inquiry for stack dismantlement at the Brookhaven National Laboratory on Long Island, N.Y. The Environmental Management office is planning an upcoming solicitation for a contractor to decommission, tear down, and conduct site clearance for the High Flux Beam […]
-
Cleanup & Remediation
After Losing Lawsuit, Former Savannah River Employee Must Pay Printing Costs
In what should be the final chapter of a federal discrimination lawsuit, a former employee of the Savannah River Site’s management and operations contractor has been ordered to pay the company $908.45 for the cost of documents printed documents over the course of the two-year case. U.S. District Judge J. Michelle Childs issued her decision […]
-
Vitrification & Grout
Washington State Issues First Operational Permit for WTP
The Washington state Department of Ecology has issued an operating permit for the analytical laboratory at the Waste Treatment and Immobilization Plant (WTP) at the Department of Energy’s Hanford Site. This permit, issued in the spring, is the state agency’s first operating approval for the plant, being built by Bechtel to turn Hanford’s radioactive tank […]
-
Contracts & Procurement
Deadline Extended for DOE Cleanup Office Tech Support Contract Bids
The Energy Department’s Office of Environmental Management has extended the deadline from July 20 to Aug. 3 for prospective vendors to submit bids on a consolidated technical support services contract. After issuing the request for proposals on June 7, DOE last week announced an amendment to the document that extends the deadline. The indefinite-delivery, indefinite-quantity […]
-
Cleanup & Remediation
Pruitt Exit Won’t Change West Lake Cleanup Plan, EPA Says
The Environmental Protection Agency said Friday the resignation of controversy-plagued Administrator Scott Pruitt would not change its approach for cleanup of the radioactively contaminated West Lake Landfill in Missouri. Pruitt submitted his resignation Thursday to President Donald Trump following a 17-month term in office in which he was battered by a series of reports about […]
-
Cleanup & Remediation
DOE Ponders Sole-Source Contract for Rutgers Study on Hanford Waste
The Energy Department’s Office of River Protection could issue a sole-source contract for Rutgers University in New Jersey to study factors connected with vitrifying tank wastes at the Hanford Site in Washington state. Although DOE is not aware of other sources capable of doing the work, interested small businesses meeting certain size standards can submit […]
-
High-Level & Tank Waste
Three More Hanford Double-Shell Waste Tanks at Risk for Corrosion
Three more double-shell tanks at the Department of Energy’s Hanford Site contain waste with chemistry that puts them them at heightened risk of corrosion, according to a new report from tank farm contractor Washington River Protection Solutions. The report evaluated the waste chemistry of Hanford’s oldest double-shell tank, AY-102, which developed a leak from its […]