High-Level & Tank Waste
Coverage of DOE-EM’s efforts to retrieve, treat, and immobilize high-level radioactive tank waste at Hanford, Savannah River, and other sites — including the Waste Treatment Plant and Defense Waste Processing Facility.
-
High-Level & Tank Waste
Correction
An article in the May 8 edition of Weapons Complex Monitor should have said Savannah River Remediation’s tenure as liquid waste manager for the Department of Energy’s Savannah River Site would be extended at least through Sept. 30, 2021, with three additional four-month option periods that could keep the contractor on the job through September 2022.
-
High-Level & Tank Waste
GAO Examines Cost, Oversight of Hanford Waste Pretreatment Facility
The Government Accountability Office said Tuesday the Energy Department should use best practices when seeking alternatives to the Pretreatment Facility for the Waste Treatment Plant being built at the Hanford Site in Washington state. The Pretreatment Facility is intended to separate radioactive waste into high-level and low-level streams before processing at the Waste Treatment Plant, […]
-
Transuranic Waste
Busy Procurement Season Ahead Despite Virus, DOE Says
The Energy Department expects to issue a final request for proposals this month for the Idaho Cleanup Contract, according to a procurement update made public last week. The potential 15-year, $6.4 billion agreement will replace Fluor Idaho’s nearly $2 billion, five-year deal that runs through May 2021. It would also replace Spectra Tech’s roughly five-year, […]
-
High-Level & Tank Waste
GAO Examines Cost, Oversight of Hanford Waste Pretreatment Facility
The Government Accountability Office said Tuesday the Energy Department should use best practices when seeking alternatives to the Pretreatment Facility for the Waste Treatment Plant being built at the Hanford Site in Washington state. The Pretreatment Facility is intended to separate radioactive waste into high-level and low-level streams before processing at the Waste Treatment Plant, […]
-
Transuranic Waste
Energy Dept. to Release Idaho Cleanup Procurement Notice This Month
The Energy Department expects to issue a final request for proposals this month for the Idaho Cleanup Contract, according to a procurement update made public Thursday. The potential 15-year, $6.4 billion agreement will replace Fluor Idaho’s nearly $2 billion, five-year deal that runs through May 2021. It would also replace Spectra Tech’s roughly five-year, $45 […]
-
High-Level & Tank Waste
Jacobs Earns More Revenue, Wrestles With Virus During Quarter
Engineering giant Jacobs said Wednesday it took in $3.4 billion in revenue during its fiscal 2020 second quarter, up from the $3.1 billion generated during the same period of 2019, despite moving most of its worldwide workforce to telework. Thanks to rapid action since the beginning of the crisis, Jacobs expedited the shift of its […]
-
High-Level & Tank Waste
Current Savannah River Liquid Waste Vendor Receives Extension
The liquid waste vendor for the Savannah River Site in South Carolina will remain in place for up to two years while the Energy Department prepares to solicit a long-term contract that could be worth $21 billion. Amentum-led Savannah River Remediation (SRR) has held the $6 billion business since July 2009; its current extension is […]
-
High-Level & Tank Waste
Reduced Staffing Level Stays in Place for Waste Treatment Plant at Hanford
A partial stop work order from the Energy Department at the Waste Treatment Plant being built at the Hanford Site in Washington state is scheduled to stay in effect through May 23, a manager for construction contractor Bechtel said last week. The order for the plant that will convert Hanford tank waste into a stable […]
-
Transuranic Waste
AECOM Quarterly Earnings Drop Slightly
AECOM, the former owner of what is now Department of Energy contractor Amentum, generated $3.2 billion in revenue during its second quarter of fiscal 2020, down from $3.4 billion for the same period a year earlier. Net income for the Los Angeles-based engineering and infrastructure multinational landed at $49 million, or $0.31 per share, for […]
-
Vitrification & Grout
DOE Idaho, Savannah River Waste Projects Largely Frozen by COVID-19
The COVID-19 pandemic has temporarily halted most physical work on major waste projects scheduled to come online this year at the Energy Department’s Idaho National Laboratory and Savannah River Savannah River Site in South Carolina. Reductions in on-site staffing triggered by DOE efforts to slow the spread of the coronavirus have suspended virtually all physical […]
-
Vitrification & Grout
Work on Savannah River Waste Unit Temporarily Suspended Due to Pandemic
Reduced staffing caused by the COVID-19 pandemic forced the Department of Energy to suspend construction of the Saltstone Disposal Unit 7 (SDU 7) at the Savannah River Site in South Carolina, the Defense Nuclear Facilities Safety Board (DNFSB) said in a recent report. The April 3 staff report filed with DNFSB Technical Director Christopher Roscetti […]
-
High-Level & Tank Waste
Wrap Up: No Word Yet on Oak Ridge Extension
The Energy Department has yet to execute an extension of up to two years for the Amentum-led joint venture responsible for remediation at the Oak Ridge Site in Tennessee. The agency in February announced its intention to award a sole-source deal to URS/CH2M Oak Ridge (UCOR) in the form of a one-year extension, plus options […]
-
High-Level & Tank Waste
Savannah River Confirms Sixth Case of COVID-19
The Energy Department’s Savannah River Site in South Carolina on Wednesday confirmed its sixth case of COVID-19, but noted that three previously infected employees have recovered and returned to work. The three others “are being monitored for a return to work within a week,” according to the press release from DOE’s office at Savannah River. […]
-
High-Level & Tank Waste
Energy Dept. Issues Draft Procurement Notice for Savannah River National Lab Contract
The Energy Department on Thursday issued its draft request for proposals for a potential 10-year, $3.8 billion stand-alone contract for management of the Savannah River National Laboratory in South Carolina. The facility is currently run through the $14.8 billion contract held by Fluor-led Savannah River Nuclear Solutions (SRNS) for management of DOE’s entire Savannah River […]
-
High-Level & Tank Waste
Correction
The Waste Treatment Plant at the Hanford Site in Washington state is under court order to demonstrate it can convert low-activity tank waste into glass by the end of 2023, and effectively do the same thing for high-level waste by the end of 2033. An article in the Wednesday Weapons Complex Morning Briefing misstated the […]
-
Interim Storage & Waste Disposal
NRC Spends $97 From Nuclear Waste Fund
Nuclear Regulatory Commission spending from its Nuclear Waste Fund balance slipped below $100 in February, according to the agency’s monthly report to Congress. The outlay of $97 for unspecified program planning and support left the agency with a balance of $430,881 from the fund intended to pay for federal disposal of high-level radioactive waste from […]
-
High-Level & Tank Waste
Correction
An article in the March 26 Weapons Complex Morning Briefing should have said that Centrus Energy sells natural uranium to short-term traders and utilities, and that it returns uranium feed components to the Russian refining company TENEX.
-
High-Level & Tank Waste
Construction of Hanford Tank-Side Cesium Removal System Could Start in Weeks
The Department of Energy hopes in April to start construction of the Tank-Side Cesium Removal (TSCR) system at the Hanford Site in Washington state, a vendor said Wednesday. Tank waste management contractor Washington River Protection Solutions and DOE’s Office of River Protection are requesting temporary authorizations from the Washington state Department of Ecology to start […]
-
Interim Storage & Waste Disposal
Energy Dept. Preparing Report on Nuclear Waste Disposition Approaches
The Department of Energy is still preparing a report to Congress on “innovative options” for meeting its legal requirement to dispose of tens of thousands of tons of U.S. nuclear waste. “The Department is currently working on the report, and we’ll follow up once it’s public,” a spokesperson said by email Monday. The spokesperson did […]
-
Interim Storage & Waste Disposal
Stakeholders Debate Trump’s Commitment Against Yucca Mountain
PHOENIX – Two Nevada officials with distinctly different opinions on the Yucca Mountain nuclear waste repository last week offered distinctly different views on what the Trump administration’s latest budget might mean for the future of the always-embattled project. In February, the White House issued a fiscal 2021 spending plan that included nothing to resume licensing […]
-
High-Level & Tank Waste
Construction of Hanford Tank-Side Cesium Removal System Could Start in Weeks
The Department of Energy hopes in April to start construction of the Tank-Side Cesium Removal (TSCR) system at the Hanford Site in Washington state, a vendor said Wednesday. Tank waste management contractor Washington River Protection Solutions and DOE’s Office of River Protection are requesting temporary authorizations from the Washington state Department of Ecology to start […]
-
Interim Storage & Waste Disposal
Energy Dept. Preparing Report on Nuclear Waste Disposition Approaches
The Department of Energy is still preparing a report to Congress on “innovative options” for meeting its legal requirement to dispose of tens of thousands of tons of U.S. nuclear waste. “The Department is currently working on the report, and we’ll follow up once it’s public,” a spokesperson said by email Monday. The spokesperson did […]
-
Interim Storage & Waste Disposal
Deep Isolation Eyes DOE Procurement for Interim Storage Design
PHOENIX – Another company indicated Monday it would be ready to bid on an anticipated procurement from the Department of Energy to design a facility for interim storage of nuclear waste. “We are interested in interim storage,” Rod Baltzer, chief operating officer for Deep Isolation, told RadWaste Monitor. “With our design, we do think you […]
-
High-Level & Tank Waste
Correction
An article in the Wednesday edition of Weapons Complex Morning Briefing should have said the Energy Department expects within weeks to issue a draft request for proposals for management of the Savannah River National Laboratory.
-
Interim Storage & Waste Disposal
Deep Isolation Eyes DOE Procurement for Interim Storage Design
PHOENIX – Another company indicated Monday it would be prepared to bid on an anticipated procurement from the Department of Energy to design a facility for interim storage of nuclear waste. “We are interested in interim storage,” Rod Baltzer, chief operating officer for Deep Isolation, told Weapons Complex Morning Briefing. “With our design, we do […]
-
High-Level & Tank Waste
2020 Called Pivotal Year for DOE Tank Waste, Cleanup
PHOENIX — By the end of 2020, the Energy Department’s Office of Environmental Management expects to start operation of facilities in Idaho and South Carolina that will convert radioactive tank waste into stable forms for eventual disposal, agency officials said here Monday. The Salt Waste Processing Facility (SWPF) at the Savannah River Site in South […]
-
High-Level & Tank Waste
Savannah River Waste Processing Plant to Begin Operations This Month
The $470 million Salt Waste Processing Facility (SWPF) at the Department of Energy’s Savannah River Site in South Carolina is on track to begin operations this month, following completion in February of a readiness assessment, according to builder Parsons. Both the Energy Department and Parsons said via email this week that the agency’s readiness assessment […]
-
Interim Storage & Waste Disposal
Nevada Senator Suggests Rollback of Requirement to Build Yucca
WASHINGTON —Secretary of Energy Dan Brouillette on Tuesday would not commit to supporting a congressional rewrite of the 1982 Nuclear Waste Policy Act to exclude mandatory construction of a permanent nuclear waste repository at Yucca Mountain in Nevada. “If we were to consider a repeal of the 1987 amendment that designated Yucca Mountain as the […]
-
Interim Storage & Waste Disposal
Energy Dept. Plans Procurement for Rad Waste Interim Storage Design
The Department of Energy plans to take bids on the design of a facility for interim storage of used reactor fuel from nuclear power plants, a senior official said Tuesday. Assistant Secretary for Nuclear Energy Rita Baranwal discussed the upcoming procurement in a hearing on the Energy Department’s latest budget proposal before the House Appropriations […]
-
High-Level & Tank Waste
Savannah River Waste Processing Plant Set to Begin Operations This Month
The $470 million Salt Waste Processing Facility (SWPF) at the Department of Energy’s Savannah River Site in South Carolina is on track to begin operations this month, following completion in February of a readiness assessment, according to builder Parsons. Both the Energy Department and Parsons said via email this week that the agency’s readiness assessment […]