Uranium Enrichment & Fuel Cycle
News on domestic uranium enrichment capacity — including HALEU supply and policy — fuel fabrication, and the broader nuclear fuel supply chain serving both existing and advanced reactors.
-
Uranium Enrichment & Fuel Cycle
Centrus, Oklo to create joint venture to pursue nuclear fuel services
Centrus Energy and Oklo agreed on Monday to seek a joint venture focused on deconversion services for high-assay low-enriched uranium (HALEU) and advancing fuel-cycle technologies in Ohio. The nuclear fuel companies announced in a press release that the activities for this joint venture will take place at Centrus’ Piketon uranium enrichment facility site in Pike […]
-
Interim Storage & Waste Disposal
Lifecycle hub RFI highlights importance of back-end of the fuel cycle, panelists say
The Department of Energy’s recent solicitation for nuclear lifecycle hubs creates opportunities to better address the back-end of the fuel cycle, several nuclear officials said during a Thursday webinar. The solicitation, published Jan. 28 meant to gauge states’ interest in hosting what DOE calls a “nuclear lifecycle campus” that could include fuel fabrication, uranium enrichment […]
-
Uranium Enrichment & Fuel Cycle
Orano files environmental report for uranium enrichment plant
Orano USA submitted its environmental report for Project IKE, a planned uranium enrichment plant in Oak Ridge, Tenn., with the Nuclear Regulatory Commission (NRC) Monday. “We are pleased to reach this early review stage with the NRC and to submit a detailed and comprehensive Environmental Report addressing the required analyses, including land use, air quality, […]
-
Uranium Enrichment & Fuel Cycle
Deep Fission, Urenco USA ink nuclear fuel deal
Deep Fission signed an agreement with Urenco USA this week to receive low-enriched uranium (LEU) for fuel for its underground small modular reactor (SMR). The Berkeley, Calif.-based SMR developer said the fuel will be used to support its pilot Gravity reactor, under the Department of Energy’s (DOE) pilot reactor program, and initial commercial deployments, according […]
-
Contracts & Procurement
Wrap Up: Orano file enviro report; Amentum plans new HQ; BWXT appoints board member
Orano USA submitted its environmental report for Project IKE, a planned uranium enrichment plant in Oak Ridge, Tenn., with the Nuclear Regulatory Commission (NRC) Monday. With the environmental report filed, Orano USA, the U.S. subsidiary of France-based Orano, said the complete facility license submission should occur later this year. “We are pleased to reach this […]
-
Uranium Enrichment & Fuel Cycle
Orano files environmental report for uranium enrichment plant
Orano USA submitted its environmental report for Project IKE, a planned uranium enrichment plant in Oak Ridge, Tenn., with the Nuclear Regulatory Commission (NRC) Monday. “We are pleased to reach this early review stage with the NRC and to submit a detailed and comprehensive Environmental Report addressing the required analyses, including land use, air quality, […]
-
Uranium Enrichment & Fuel Cycle
NRC approves TRISO-X fuel facility license
The Nuclear Regulatory Commission (NRC) issued TRISO-X a special nuclear material license, allowing the company to use high-assay low-enriched uranium (HALEU) at its fuel fabrication facility in Oak Ridge, Tenn. TX-1 and TX-2, X-Energy’s commercial fuel facilities, are the first such facilities licensed by the NRC in 50 years, the company said last week. TX-1 […]
-
Uranium Enrichment & Fuel Cycle
NRC approves TRISO-X fuel facility license
The Nuclear Regulatory Commission (NRC) issued TRISO-X a special nuclear material license, allowing the company to use high-assay low-enriched uranium (HALEU) at its fuel fabrication facility in Oak Ridge, Tenn. The two facilities were issued an initial 40-year license by NRC. TX-1 will be operated by X-Energy’s subsidiary company TRISO-X. When TX-1 is completed, then […]
-
Uranium Enrichment & Fuel Cycle
Centrus, Fluor team up for Piketon uranium enrichment plant expansion
Centrus Energy has agreed to a strategic partnership with Fluor, which will serve as engineering, procurement and construction contractor for the planned expansion of an Ohio uranium enrichment plant. The Bethesda, Md.-based Centrus will collaborate with Fluor through subsidiary American Centrifuge Operating, according to its Wednesday press release. The subsidiary operates the American Centrifuge Plant […]
-
Uranium Enrichment & Fuel Cycle
BWXT cites progress on TRISO fuel production for Antares
BWX Technologies said it has made “significant progress” in the production of tri-structural isotropic (TRISO) for Antares Nuclear and is on track to have it completed by the July 4 deadline. Antares is one of 10 companies that were selected for DOE’s advanced reactor pilot program. The program seeks to have at least three reactors […]
-
Uranium Enrichment & Fuel Cycle
Startup company seeks to recycle spent nuclear fuel
A new nuclear technology company, Project Omega, said this week it will focus on developing nuclear fuel recycling technology. The Rhode Island-based private company said it will develop and deploy “cutting edge technologies and processes to recycle spent nuclear fuel into long-duration, high-density power sources, and critical materials for the nuclear industry,” according to the […]
-
Uranium Enrichment & Fuel Cycle
Centrus, Fluor team up for Piketon uranium enrichment plant expansion
Centrus Energy has agreed to a strategic partnership with Fluor, which will serve as engineering, procurement and construction contractor for the planned expansion of an Ohio uranium enrichment plant. The Bethesda, Md.-based Centrus will collaborate with Fluor through subsidiary American Centrifuge Operating, according to its Wednesday press release. The subsidiary operates the American Centrifuge Plant […]
-
Uranium Enrichment & Fuel Cycle
Five companies tapped for DOE nuclear fuel recycling awards
The Department of Energy has awarded over $19 million to five nuclear companies to research and develop fuel recycling technology for spent nuclear fuel. According to DOE’s Feb. 5 press release, the five selected companies were: Chicago-based Alpha Nur will research and validate a process that recovers highly enriched uranium from used fuel by domestic […]
-
Contracts & Procurement
Centrus earnings dip in fourth quarter
Earnings fell at Centrus Energy, Bethesda, Md., in the fourth quarter, which the uranium broker attributed to the decreased revenue from its uranium sector. Net earnings for the fourth quarter ended Dec. 31 were $17.8 million, or $0.79 a share, down from $53.7 million, or $3.20 a share, in the year-ago quarter. Quarterly revenue was […]
-
Uranium Enrichment & Fuel Cycle
BWXT cites progress on TRISO fuel production for Antares
BWX Technologies said it has made “significant progress” in the production of tri-structural isotropic (TRISO) for Antares Nuclear and is on track to have it completed by the July 4 deadline. Antares is one of 10 companies that were selected for DOE’s advanced reactor pilot program. The program seeks to have at least three reactors […]
-
Uranium Enrichment & Fuel Cycle
Centrus, Fluor team up for Piketon uranium enrichment plant expansion
Centrus Energy has agreed to a strategic partnership with Fluor, which will serve as engineering, procurement and construction contractor for the planned expansion of an Ohio uranium enrichment plant. The Bethesda, Md.-based Centrus will collaborate with Fluor through subsidiary American Centrifuge Operating, according to its Wednesday press release. The subsidiary operates the American Centrifuge Plant […]
-
Uranium Enrichment & Fuel Cycle
497 massive converters extracted from Paducah C-333 building
Work crews at the Department of Energy’s Paducah Site in Kentucky have removed and cut up nearly 500 large components, known as converters, from the C-333 Process Building, DOE’s Office of Environmental Management said this week. Work crews recently completed the “segmentation” of all 497 converters from the C-333 facility, DOE’s nuclear cleanup office said […]
-
Uranium Enrichment & Fuel Cycle
497 massive converters extracted from Paducah C-333 building
Work crews at the Department of Energy’s Paducah Site in Kentucky have removed and cut up nearly 500 large components, known as converters, from the C-333 Process Building, DOE’s Office of Environmental Management said this week. Work crews recently completed the “segmentation” of all 497 converters from the C-333 facility, DOE’s nuclear cleanup office said […]
-
Contracts & Procurement
Centrus earnings dip in fourth quarter
Earnings fell at Centrus Energy, Bethesda, Md., in the fourth quarter, which the uranium broker attributed to the decreased revenue from its uranium sector. Net earnings for the fourth quarter ended Dec. 31 were $17.8 million, or $0.79 a share, down from $53.7 million, or $3.20 a share, in the year-ago quarter. Quarterly revenue was […]
-
Uranium Enrichment & Fuel Cycle
Centrus, Fluor team up for Piketon uranium enrichment plant expansion
Centrus Energy has agreed to a strategic partnership with Fluor, which will serve as engineering, procurement and construction contractor for the planned expansion of an Ohio uranium enrichment plant. The Bethesda, Md.-based Centrus will collaborate with Fluor through subsidiary American Centrifuge Operating, according to its Wednesday press release. The subsidiary operates the American Centrifuge Plant […]
-
Uranium Enrichment & Fuel Cycle
Land clearing commences for Paducah uranium enrichment projects
Work crews are cutting trees and clearing land to prepare for construction of two modern uranium enrichment projects at the Department of Energy’s Paducah Site in Kentucky, DOE said last week. About 100 acres of land are being cleared at Paducah to make way or an enrichment plant planned by California-based nuclear technology startup, General […]
-
Uranium Enrichment & Fuel Cycle
DOE solicits information from states on nuclear lifecycle hubs
The Department of Energy issued a request for information (RFI) Wednesday seeking states interested in hosting Nuclear Lifecycle Innovation Campuses. The proposed campuses must support capabilities of the full nuclear fuel cycle, such as fuel fabrication, enrichment, reprocessing spent nuclear fuel and disposal of waste, according to DOE’s press release. The approach could be more […]
-
Advanced Nuclear & SMRs
BWXT cites progress on TRISO fuel production for Antares
BWX Technologies said it has made “significant progress” in the production of tri-structural isotropic (TRISO) for Antares Nuclear and is on track to have it completed by the July 4 deadline. Antares is one of 10 companies that were selected for DOE’s advanced reactor pilot program. The program seeks to have at least three reactors […]
-
Uranium Enrichment & Fuel Cycle
Five companies tapped for DOE nuclear fuel recycling awards
The Department of Energy has awarded over $19 million to five nuclear companies to research and develop fuel recycling technology for spent nuclear fuel. According to DOE’s Feb. 5 press release, the five selected companies were: Chicago-based Alpha Nur will research and validate a process that recovers highly enriched uranium from used fuel by domestic […]
-
Uranium Enrichment & Fuel Cycle
DOE to restart uranium recovery at SRS
The Department of Energy said Wednesday it will resume uranium recovery operations at the Savannah River Site in South Carolina, utilizing the H-Canyon facility. The uranium recovery work will help recover key isotopes that are currently hard to obtain in the United States and support scientific research as well as medical applications and commercial uses, […]
-
Cleanup & Remediation
DOE’s Oak Ridge boss Olds adds interim Portsmouth/Paducah role
The head of the Department of Energy’s Environmental Management field office in Tennessee, Eric Olds, is also temporarily overseeing DOE’s Portsmouth/Paducah Project Office. While Olds remains the manager of the Oak Ridge Office of Environmental Management, he now is also serving as the interim acting manager for the Portsmouth/Paducah Project Office (PPPO), a department spokesperson […]
-
Uranium Enrichment & Fuel Cycle
DOE to restart uranium recovery at SRS
The Department of Energy said Wednesday it will resume uranium recovery operations at the Savannah River Site in South Carolina, utilizing the H-Canyon facility. The uranium recovery work will help recover key isotopes that are currently hard to obtain in the United States and support scientific research as well as medical applications and commercial uses, […]
-
Uranium Enrichment & Fuel Cycle
Jarrell to lead DOE NE nuclear fuel cycle; Murray heads to EM
The Department of Energy’s Office of Nuclear Energy this week tapped longtime nuclear complex supervisor Josh Jarrell to become deputy assistant secretary for nuclear fuel cycle. Separately two industry sources have told Exchange Monitor in the past week that Office of Nuclear Energy executive, Paul Murray, is moving over to DOE’s Office of Environmental Management. […]
-
Uranium Enrichment & Fuel Cycle
Jarrell to lead DOE NE nuclear fuel cycle; Murray heads to EM
The Department of Energy’s Office of Nuclear Energy this week tapped longtime nuclear complex hand Josh Jarrell to become deputy assistant secretary for nuclear fuel cycle. Separately two industry sources have told Exchange Monitor in the past week that Office of Nuclear Energy executive, Paul Murray, is moving over to DOE’s Office of Environmental Management. […]
-
Uranium Enrichment & Fuel Cycle
DOE to restart uranium recovery at SRS
The Department of Energy said Wednesday it will resume uranium recovery operations at the Savannah River Site in South Carolina, utilizing the H-Canyon facility. The uranium recovery work will help recover key isotopes that are currently hard to obtain in the United States and support scientific research as well as medical applications and commercial uses, […]