Vitrification & Grout
Coverage of the technologies used to stabilize and immobilize radioactive waste — including glass vitrification and cementitious grouting — for long-term storage and disposal.
-
Vitrification & Grout
Hanford treatment plant simulates waste solidification, makes and packs glass cylinder
HANFORD SITE, WASH. — Workers at the Department of Energy’s Hanford Site filled its first canister with melted non-radioactive glass last week, the site’s leaders announced Monday. “It was not obvious to everyone except this team that we’d be here today,” said the Department of Energy’s Hanford Manager Brian Vance at a Monday ceremony at […]
-
Vitrification & Grout
Hanford to start testing second low-activity-waste melter in December
Trials on the slate for this winter will follow-up successful tests, announced last week by the Department of Energy, of the first melter at the Hanford Site’s Waste Treatment and Immobilization Plant. Conducted on Oct. 26 and Oct. 30, the tests consisted of melting glass beads together to be poured into a cylindrical canister. The […]
-
Vitrification & Grout
Hanford to start testing second low-activity-waste melter in December
Trials on the slate for this winter will follow-up successful tests, announced last week by the Department of Energy, of the first melter at the Hanford Site’s Waste Treatment and Immobilization Plant. Conducted on Oct. 26 and Oct. 30, the tests consisted of melting glass beads together to be poured into a cylindrical canister. The […]
-
High-Level & Tank Waste
Bechtel responds to DOE Inspector General on waste treatment plant cost estimates
Bechtel National this week pushed back against a Department of Energy Office of Inspector General audit report that questioned the reliability of the contractor’s cost estimates for the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state. “We believe that the report overlooks relevant factual data that is essential for consideration prior […]
-
High-Level & Tank Waste
Bechtel responds to DOE Inspector General on waste treatment plant cost estimates
Bechtel National Wednesday pushed back against a Department of Energy Office of Inspector General audit report that questioned the reliability of the contractor’s cost estimates for the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state. “We believe that the report overlooks relevant factual data that is essential for consideration prior to […]
-
High-Level & Tank Waste
DOE Inspector General not sold on Bechtel cost estimates for vit plant
Three years after Bechtel and a fellow contractor at the Department of Energy’s Hanford Site in Washington state paid about $58 million to settle fraud claims, DOE’s Office of Inspector General still lacks confidence in Bechtel’s cost estimates, according to a new report. In an audit report out last week, DOE’s Office of Inspector General […]
-
High-Level & Tank Waste
Hanford’s pre-treated waste might not meet vit plant criteria
A storage tank spoiled a batch of liquid radioactive waste at the Hanford Site that was thought to be clean enough for disposal, according to a contractor memo seen by the Exchange Monitor. The waste from Hanford’s tank farm, part of a less-radioactive tranche that is supposed to be solidified starting in 2025 by the […]
-
Vitrification & Grout
Grout could be cheaper than glass for much Hanford low-level tank waste, GAO says
In a follow-up to prior reports, the Government Accountability Office said again Friday that using concrete-like grout would be a cheaper way to solidify the less-radioactive tank waste at the Department of Energy’s Hanford Site in Washington state. The Savannah River Site in South Carolina has treated 4 million gallons of its radioactive salt waste […]
-
Vitrification & Grout
Grout could be cheaper than glass for much Hanford low-level tank waste, GAO says
In a follow-up to prior reports, the Government Accountability Office said again Friday that using concrete-like grout would be a cheaper way to solidify the less-radioactive tank waste at the Department of Energy’s Hanford Site in Washington state. The Savannah River Site in South Carolina has treated 4 million gallons of its radioactive salt waste […]
-
High-Level & Tank Waste
Chemical safety changes sought by DOE at Hanford Waste Treatment Plant
The Department of Energy and Bechtel National should make several upgrades to the chemical safety program for the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state, according to DOE’s enforcement wing. While Bechtel and subcontractor Waste Treatment Completion Co. have a “generally adequate” chemical safety program, until key improvements are made, […]
-
High-Level & Tank Waste
Chemical safety changes sought by DOE at Hanford Waste Treatment Plant
The Department of Energy and Bechtel National should make several upgrades to the chemical safety program for the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state, according to DOE’s enforcement wing. While Bechtel and subcontractor Waste Treatment Completion Co. have a “generally adequate” chemical safety program, until key improvements are made, […]
-
Vitrification & Grout
White touts Hanford grout test during National Cleanup Workshop
ARLINGTON, VA — A planned test to solidify 2,000 gallons of low-level radioactive tank waste from the Hanford Site into a concrete-like grout could pave the way for a second method of treating waste at the former plutonium production complex near Richland, Wash., the Department of Energy’s top nuclear-cleanup official said here Tuesday. During the […]
-
Vitrification & Grout
White touts Hanford grout test during National Cleanup Workshop
ARLINGTON, VA — A planned test to solidify 2,000 gallons of low-level radioactive tank waste from the Hanford Site into a concrete-like grout could pave the way for a second method of treating waste at the former plutonium production complex near Richland, Wash., the Department of Energy’s top nuclear-cleanup official said here Tuesday. During the […]
-
High-Level & Tank Waste
Feds line up next pretreatment cycle for Hanford liquid waste, plan next steps on grouting
The Department of Energy is more than halfway toward its goal of removing cesium from a million gallons of liquid radioactive waste at the Hanford Site in Washington state, a prerequisite for solidifying the waste in the coming years, a DOE manager told the Hanford Advisory Board Aug. 23 Cesium removal should resume in September […]
-
High-Level & Tank Waste
Feds line up next pretreatment cycle for Hanford liquid waste, plan next steps on grouting
The Department of Energy is more than halfway toward its goal of removing cesium from a million gallons of liquid radioactive waste at the Hanford Site in Washington state, a prerequisite for solidifying the waste in the coming years, a DOE manager told the Hanford Advisory Board Aug. 23 Cesium removal should resume in September […]
-
High-Level & Tank Waste
Hanford practices early steps of waste solidification at treatment plant
Workers at the Hanford Site in Washington state last week practiced three early steps of solidifying liquid radioactive waste inside glass, a site contractor said Tuesday in a press release. Personnel poured glass beads called frit into a heated melter at the Waste Treatment and Immobilization Plant, liquifying the glass in a first-ever trial run […]
-
High-Level & Tank Waste
Hanford practices early steps of waste solidification at treatment plant
Workers at the Hanford Site in Washington state last week practiced thee early steps of solidifying liquid radioactive waste inside glass, a site contractor said Tuesday in a press release. Personnel poured glass beads called frit into a heated melter at the Waste Treatment and Immobilization Plant, liquifying the glass in a first-ever trial run […]
-
Defense Low-Level Waste
Wrap Up: Ground broken on Oak Ridge landfill; Battelle picks new lab boss; Perma-Fix, Local 598 reach grout deal and more
The Department of Energy, contractor United Cleanup Oak Ridge and various state and local officials broke ground Wednesday on a new $550-million low-level radioactive waste landfill at the Oak Ridge Site in Tennessee, DOE said in a press release. The new Environmental Management Disposal Facility will provide onsite disposal of debris generated as DOE continues […]
-
High-Level & Tank Waste
Melter 1 heat up complete at Hanford Waste Treatment Plant, DOE says
The first melter at the Department of Energy’s waste-solidification plant at the Hanford Site in Washington state has reached its operating temperature of 2,100 degrees Fahrenheit, the agency and contractor Bechtel National said this week. The milestone for the Waste Treatment and Immobilization Plant (WTP) completed the heat up process that started June 24, DOE […]
-
Vitrification & Grout
DOE to start baking cost of grout into upcoming Hanford system plan analysis
At the request of the Government Accountability Office, the Department of Energy will start including costs for grouting some tank waste as part of its long-term planning for the Hanford Site in Washington state, according to a report released this week. In the report, the Government Accountability Office (GAO) recommends DOE consider, in consultation with […]
-
High-Level & Tank Waste
Melter 1 heat up complete at Hanford Waste Treatment Plant, DOE says
The first melter at the Department of Energy’s waste-solidification plant at the Hanford Site in Washington state has reached its operating temperature of 2,100 degrees Fahrenheit, the agency and contractor Bechtel National said late Monday. The milestone for the Waste Treatment and Immobilization Plant (WTP) completed the heat up process that started June 24, DOE […]
-
Vitrification & Grout
DOE resumes long-delayed heatup of melter at Hanford vit plant
The Department of Energy resumed heating the first melter at the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state, a process on hold since fall, the agency said this week. Resumption of the heatup was signaled last month by the acting head of the DOE Office of Environmental Management, William (Ike) […]
-
Vitrification & Grout
DOE resumes long-delayed heatup of melter at Hanford vit plant
The Department of Energy resumed heating the first melter at the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state, a process on hold since fall, the agency said Monday. Resumption of the heatup was signaled last month by the acting head of the DOE Office of Environmental Management, William (Ike) White […]
-
Vitrification & Grout
Hanford grout test advances, DNFSB chair wants full board
WASHINGTON, D.C.— Grouting low-level radioactive waste at the Department of Energy’s Hanford Site in Washington state, fully staffing a federal safety watchdog and other topics generated attention here Thursday at an annual meeting of a federal contractors group Thursday. The DOE’s acting head of the Office of Environmental Management, William (Ike) White told the Energy […]
-
Vitrification & Grout
State officials conditionally onboard with grouting of Hanford low-level waste
Washington and Oregon officials agreed Tuesday that concrete-like grout could be used instead of glass to solidify a significant portion of Hanford’s radioactive liquid waste, as long as the grouted waste is taken off-site. Suzanne Dahl, tank waste manager for the Washington Ecology Department and Matt Hendrickson, her counterpart at the Oregon Department of Energy, […]
-
Vitrification & Grout
State officials conditionally onboard with grouting of Hanford low-level waste
Washington and Oregon officials agreed Tuesday that concrete-like grout could be used instead of glass to solidify a significant portion of Hanford’s radioactive liquid waste, as long as the grouted waste is taken off-site. Suzanne Dahl, tank waste manager for the Washington Ecology Department and Matt Hendrickson, her counterpart at the Oregon Department of Energy, […]
-
Vitrification & Grout
National Academies sees strong case for grouting waste at Hanford; public session set for June
A long-awaited report released Monday from the National Academies finds a “strong technical case” for using concrete-like grout to augment operation of the Waste Treatment and Immobilization Plant at the Department of Energy’s Hanford Site in Washington state. The report from the National Academies of Sciences, Engineering, and Medicine lauded a study by DOE’s Savannah […]
-
Vitrification & Grout
Hanford WTP melter heat-up could resume within weeks, White says
Crews at the Department of Energy’s Hanford Site in Washington state are doing electrical testing, setting the stage to again start heating up the first melter at the Waste Treatment and Immobilization Plant, the agency’s acting nuclear cleanup boss said this week. “At Hanford we resumed our electrical testing for the vitrification plant,” William (Ike) […]
-
Vitrification & Grout
IWTU now running with 100% radioactive waste, EM boss White tells board
A $1.4-billion facility to convert sodium-bearing waste into a solid granular form at the Department of Energy’s Idaho National Laboratory is now running with 100% radioactive waste, the head of the $8-billion nuclear cleanup office said Monday. The Integrated Waste Treatment Unit (IWTU) at the Idaho National Lab is now “at 100% waste feed,” William […]
-
Budget & Policy
Idaho county’s case for INL impact payments already rejected by courts, feds say
Butte County, Idaho has already tried and failed to convince federal courts the locality is entitled to “impact payments” because of ongoing storage of spent nuclear fuel at the Department of Energy’s Idaho National Laboratory, according to Justice Department legal papers filed Monday. “Plaintiff already tested—and lost—its theory that it was entitled to impact assistance […]