Delivering first Columbia-class sub by 2028 still hard but doable, sub chief says

ARLINGTON, Va. – The Navy’s first submarine czar last week said while it will still be difficult to deliver the first Columbia-class ballistic missile submarine on time by the 2028 goal, he is more optimistic it is achievable following production process improvements.

In April, Vice Adm. Robert Gaucher, director of submarine programs, a dual-hatted post consisting of the Defense Department’s Direct Reporting Portfolio Manager Submarines (DRPM SUBS) and the Department of the Navy’s Program Acquisition Executive (PAE) Undersea, said the 2028 target was a “heavy lift” that would require the Navy and industry acting and operating differently to be deployed on time.

At the time he also said the Navy would not rush delivery of the USS District of Columbia (SSN-826) at the expense of production for the class as a whole due to the program’s importance.

Speaking at the Naval Submarine League’s annual symposium here last week, Gaucher explained why his outlook has grown more optimistic.

“I personally track the weekly hours earned on the USS District of Columbia, and I review them directly with the presidents of Huntington Ingalls and Electric Boat during our weekly Construction and Maintenance Operations Center, or CMOT, brief,” Gaucher said. “Last spring, weekly earnings on USS District of Columbia were flatlined, and without change, would have had almost no chance of delivering in 2028.”

“Frankly, when I looked at the weekly earnings back in February, March, and April, the straight line math of hours left divided by hours per week ended up taking about four years,” Gaucher added. “So that is well past 2028. And that did not give me high confidence.”

Gaucher said to improve matters he met with the leaders of submarine prime contractor General Dynamics to talk about changes needed “and I challenged them to work to hit a target that almost doubled their hours per week by July 1st. So that was between the end of April and July 1st. We missed July 1st. But a few weeks later, on July 20th, we hit our goal, and we stabilized since then, and have since pushed to more than double from the spring as of mid-October.”

The Navy’s end-of-year target for SSBN-826 production will have them earning higher weekly hours at a rate of nearly 2.5 times the rate from the second quarter of fiscal year 2026 last spring, he said. Gaucher displayed a slide during his presentation that said this means the build rate on SSBN-826 has increased by 40%.

Now SSBN-826 production is on plan to achieve pressure hull completion in the next one to two months, which at the start of 2026 Gaucher said seemed ‘highly unlikely.”

These are major speed upgrades on production of the first Columbia-class ballistic missile submarine, but Gaucher said delivery by 2028 is still a heavy lift with plenty of work to do, but he said that is now “absolutely achievable” with further improvements. “My confidence grows each week as we review deck plate performance, align on goals, improve our production planning, and address day-to-day production bottlenecks,” he said.

Exchange Monitor affiliate Defense Daily first published a version of this story.