Vol. 5, No. 25

Pantex Confirms First COVID-19 Case

There is at least one confirmed case of COVID-19 among the workforce of the Pantex Plant in Amarillo, Texas, where the National Nuclear Security Administration (NNSA) assembles and disassembles nuclear weapons for maintenance and modernization. In a statement,… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a subscriber […]
  • Quarter of Fluor Idaho Workforce Still On-Site at INL

    Half of the 1,800-person workforce for the Idaho National Laboratory’s cleanup contractor was still working as of last week, according to the Department of Energy. Of those 900 Fluor Idaho employees, half were physically on-site and the others teleworking, a… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as […]

  • Electric Boat Chief Has COVID-19, Sub Builder ‘Dramatically’ Reducing Workers On Site

    The president of General Dynamics Electric Boat has tested positive for the COVID-19 virus while the company confirmed further changes to the workforce configuration to limit the disease’s spread within its facilities. In an April 4 message to employees, Electric… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as […]

  • Pa. Nuclear Power Plant Files First Request for Work-Hour Limits Exemption

    The Nuclear Regulatory Commission on Friday announced receipt of its first request from a nuclear power plant for an exception to the federal limits for work hours during the COVID-19 crisis. Exelon Generation filed the request Thursday for its two-reactor Limerick… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in […]

  • NAS Releases Final Report on Treating Supplement LAW at Hanford Site

    A viable program for treating supplemental low-activity waste at the Energy Department’s Hanford Site in Washington state can be developed for any one of three major technologies – vitrification, grouting, and steam reforming, according to an April 1 report… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a […]

  • New Prez Coming This Month for NNSA Kansas City Plant

    Eric Wollerman will become president of Honeywell Federal Manufacturing & Technologies effective April 30, the manager of the Kansas City National Security Campus announced. At the end of the month, the buck will stops with Wollerman at the National Nuclear… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as […]

  • NRC Spends $97 From Nuclear Waste Fund

    Nuclear Regulatory Commission spending from its Nuclear Waste Fund balance slipped below $100 in February, according to the agency’s monthly report to Congress. The outlay of $97 for unspecified program planning and support left the agency with a balance of $430,881… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in […]