Vol. 4, No. 108

Bechtel Earns 47.9% of Available 2018 Fee for Hanford Waste Treatment Plant

The Department of Energy on Tuesday gave Bechtel National a rating of “satisfactory,” and 47.9% of the maximum performance fee available for 2018, for its work on the Waste Treatment Plant at the Hanford Site in Washington state. That performance evaluation was good for $3.77 million out of a total available $7.87 million in the […]
  • Energy Dept. Extends Portsmouth Infrastructure Incumbent Contract

    The Energy Department’s Office of Environmental Management is picking up North Wind-led Portsmouth Mission Alliance’s (PMA) 22-month contract option for infrastructure support services at the Portsmouth Site in Ohio. The department on Tuesday announced the extension, valued at an estimated $67 million, one day before the three-year base contract with the North Wind-Swift & Staley […]

  • DNFSB Staff Locked Out of Meetings at Nuke Sites Due to DOE Order

    WASHINGTON — The Department of Energy locked Defense Nuclear Facilities Safety Board (DNFSB) staff out of meetings at at least one defense nuclear site, a member of the independent federal nuclear health-and-safety watchdog said here Tuesday. At a public meeting, board member Joyce Connery said DNFSB staff at a site she did not identify were denied […]

  • Nevada Wants Appeals Court to Force Removal of Plutonium From State

    A panel of appeals judges will hear oral argument from Nevada by early October about why the Department of Energy should remove a half metric ton of weapon-usable plutonium from the Nevada National Security Site’s Device Assembly Facility. That is according to a Monday order in which the Ninth Circuit Court of appeals told the […]

  • Expert Wanted for Deposition in Nevada Plutonium Lawsuit Retired From DOE

    A key figure in multiple federal lawsuits involving weapon-usable plutonium moved last year to the Nevada National Security Site from the Savannah River Site in South carolina has retired from the Department of Energy, the agency confirmed Tuesday. Henry Allen Gunter left DOE after a long federal career, a spokesperson for DOE’s Environmental Management Office […]

  • MOX Services, Subcontractor Say They Weren’t Part of Fraud Scheme at Savannah River

    CB&I AREVA MOX Services and a former subcontractor say they should not have to pay the $19.2 million the United States is seeking in a lawsuit. In separate documents filed in federal court, the companies said they had no knowledge of alleged schemes to defraud the government while working at the now-canceled plutonium recycling facility […]

  • Energy Department’s Idaho Waste Plant Liability Approaches $6 Million

    By the end of April, the state of Idaho will have assessed $5.86 million in total penalties against the Department of Energy for failure to start operating the Integrated Waste Treatment Unit (IWTU) at the Idaho National Laboratory years ago. But DOE and contractor Fluor Idaho are doing their third extended test run of the […]

  • Lockheed Martin Soars in First Quarter of 2019

    Lockheed Martin blew open the door in its first-quarter financials with a strong showing across all of its operating segments and the company increased its guidance for earnings, sales, and cash this year. Net income jumped a whopping 42 percent to $1.7 billion, $5.99 earnings per share (EPS), from $1.2 billion ($4.02 EPS) a year […]

  • FirstEnergy Revenue Flat, Earnings Down in 1Q

    FirstEnergy Corp. is optimistic about limiting the impact of the bankruptcy of subsidiary FirstEnergy Solutions on the parent corporation’s financial picture, according to slides to be presented today during a quarterly earnings presentation. The slides were attached to a quarterly filing Tuesday with the U.S. Securities & Exchange Commission. It says FirstEnergy and its subsidiary […]

  • Centrus Energy Virtual Stockholder Meeting Set for June 6

    Maryland-based Centrus Energy will hold its annual stockholders online meeting at 10 a.m. ET on June 6. “You will be able to participate in the meeting, vote, and submit questions during the meeting by visiting www.virtualshareholdermeeting.com/LEU2019,” and entering a control number mailed to shareholders, Centrus President and CEO Daniel Poneman and Board Chairman Mikel Williams […]

Get Published in ExchangeMonitor Publications