Vol. 4, No. 282

Corporate Execs Don’t Expect Hanford Tank Contract Soon

Executives with a couple companies hoping to win at least a share of the mega-dollar Tank Closure Contract at the Energy Department’s Hanford Site in Washington suggested this week the award will be delayed a few months. That was a shared message during quarterly… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must […]
  • AECOM Upbeat About Spinoff of Government-Contracting Unit

    The top brass at AECOM has received plenty of positive feedback since announcing June 17 that it would spin off the business segment that contracts with the Department of Energy and other federal agencies. “We are moving ahead of schedule” toward separating… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged […]

  • BWXT Halfway Through Submarine Missile Tube Fixes; Threatens Exit From Business

    BWX Technologies is about halfway through repairing 12 submarine missile tubes it welded incorrectly in 2018, Rex Geveden, president and CEO of the Lynchburg, Va., nuclear-hardware and fuel provider told investors Tuesday. Under multiple subcontracts to Columbia-… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a subscriber to […]

  • Another Group of MFFF Workers Laid Off

    As the calendar flipped to August, the Mixed Oxide Fuel Fabrication Facility delivered nearly 30 more layoff notices that will reduce the facility to a skeleton crew of around 350 employees, according to a recent post on a South Carolina government-affiliated website.  CB&I… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be […]

  • Army Corps Reactor Decommissioning RFP Delayed

    The U.S. Army Corps of Engineers (USACE) said Tuesday it has delayed by about three weeks releasing a request for proposals for decommissioning its SM-1 nuclear power reactor at Fort Belvoir, Va. The procurement notice, previously expected around July 29, is now… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged […]

  • NRC Urged to Proceed With Pilgrim Plant License Transfer Review

    The U.S. Nuclear Regulatory Commission should disregard the commonwealth of Massachusetts’ request for a 90-day stay on its review of the license transfer application for the Pilgrim Nuclear Power Station, the plant’s owner and prospective buyer said Monday. “The… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a […]

  • Energy Department Issues Notice for Remediation at Knolls Laboratory

    The U.S. Energy Department on Tuesday issued a sources sought/request for information for remediation of the Knolls Atomic Power Laboratory and the Kesselring Site, both in New York state. The agency wants to gauge small business interest in a potential contract… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in […]

  • NRC Spends $479 From Nuclear Waste Fund Balance

    The U.S. Nuclear Regulatory Commission in June continued to spend next to nothing from its remaining balance from the federal fund intended to pay for a nuclear waste disposal facility. The agency spent only $479 from the Nuclear Waste Fund for unspecified “program… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be […]