DOE Proposes to Keep SRS Liquid Waste Incumbent on the Job Through 1Q 2019

Having already granted one contract extension, the U.S. Energy Department proposes to keep incumbent Savannah River Remediation (SRR) in charge of liquid waste management at the Savannah River Site in South Carolina into 2019. In a March 21 notice on a federal… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged […]
  • White Could be Sworn as DOE Cleanup Boss This Week

    Anne Marie White should be sworn in this week as assistant secretary of energy for environmental management, an industry source said Tuesday. The Senate confirmed White’s nomination on Thursday by voice vote, but the Energy Department is apparently waiting for… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as […]

  • New NNSA Nonproliferation Head Still Not in Place

    A couple working days after the Senate confirmed his nomination, the Department of Energy still had not sworn in Brent Park as deputy administrator for defense nuclear nonproliferation at the National Nuclear Security Administration. Park, a nuclear physicist,… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a subscriber […]

  • Army Corps Wrapping Up STURGIS Decommissioning

    The U.S. Army Corps of Engineers anticipates completing decommissioning of the reactor on the radioactively contaminated STURGIS barge by June, after which what remains of the former floating nuclear power plant will be transported for shipbreaking. “We’re… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a subscriber to […]

  • EnergySolutions Backs Early Use of Nuclear Plant Decommissioning Funds

    Nuclear services provider EnergySolutions supports allowing use of nuclear power plant decommissioning trust funds for certain operations even before the facility ceases operation, an executive said last week. “We are very supportive of using the decommissioning… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in as a subscriber to view […]

  • Correction

    The final funding level in the Energy Department’s fiscal 2018 omnibus for the Portsmouth Site is roughly $448 million. The overall fiscal 2019 DOE budget request for Portsmouth is about $415 million. Totals cited in a Tuesday Weapons Complex Morning Briefing… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Morning Briefing! You must be logged in […]