DOE Budget Plan Doubles Funding for WIPP Ventilation
-
Interim Storage & Waste Disposal
House Panel Advances Pro-Yucca Nuclear Waste Bill
Disputes over several pieces of language did not stop the House Energy and Commerce environment subcommittee on Thursday from sending legislation to advance interim and permanent storage of U.S. nuclear waste to the full panel for consideration. Democrats offered… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a subscriber […]
-
Transuranic Waste
DOE Seeks Permission to Keep Waste Above Ground at WIPP for Another Year
Twenty-six containers of transuranic waste shipped to the Waste Isolation Pilot Plant (WIPP) for disposal years ago might not be buried there until 2018, the Energy Department disclosed on June 9 in a regulatory filing. Hundreds of containers of transuranic waste… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as […]
-
Cleanup & Remediation
Hanford 618-10 Burial Ground Cleanup Nears Completion
The last of the 94 vertically buried pipes filled with radioactive waste have been removed from the Hanford Site’s 618-10 Burial Ground, and other cleanup work there is nearing completion, according to the Department of Energy and cleanup contractor CH2M Hill… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as […]
-
Interim Storage & Waste Disposal
NRC Reviewing DOE Three Mile Island Waste Storage Extension Request
The Nuclear Regulatory Commission on June 9 said it has begun the technical review of the Energy Department’s request for a 20-year license extension for storage in Idaho of debris from the Three Mile Island nuclear power plant. The Energy Department submitted… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a […]
-
Decommissioning
NRC Staff OKs American Centrifuge Waste Shipments
Nuclear Regulatory Commission staff on Tuesday authorized shipment by road of various forms of waste from the shuttered American Centrifuge project in Ohio to the Department of Energy’s Nevada National Security Site. The approval was signed on the same day that… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as […]
-
High-Level & Tank Waste
Hanford Waste Treatment Plant’s First Melter Assembled
Bechtel National workers have completed assembling the first melter at the Hanford Site’s Waste Treatment Plant, the Department of Energy announced Thursday. Completion of the project earned the contractor $4.275 million in incentive pay. The melter is one of… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a subscriber […]
-
High-Level & Tank Waste
Melter Swap at SRS Facility Signals Progress During Liquid Waste Outage
The Savannah River Site is on pace to restart liquid waste operations “toward the end of the year,” according to a SRS Facebook post that also detailed progress in switching out melters at one of the site’s main waste processing facilities. The update Monday says… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged […]
-
Cleanup & Remediation
Advisory Committee Pushes for Increased Monitoring of SRS Drone Issue
A committee of the Savannah River Site Citizens Advisory Board (CAB) this week urged the Energy Department to step up efforts to regulate drone flights over the facility in South Carolina. Tuesday’s vote came two months after the CAB’s Strategic and Legacy… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as […]
-
Cleanup & Remediation
DOE Contractor Wants Discrimination Lawsuit Dismissed
The liquid waste contractor for the Department of Energy’s Savannah River Site in South Carolina wants a federal judge to throw out a discrimination lawsuit, saying the former employee and plaintiff “has failed to state a claim upon which relief can be… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a […]
-
Cleanup & Remediation
Wrap Up: Parties Request Another Delay in Hanford Chemical Vapors Trial
Plaintiffs and defendants in the lawsuit over chemical vapors protection for workers at the Hanford Site in Washington state have asked for another delay in the trial as they try to reach a settlement agreement. The trial already has been postponed twice to allow… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be […]