DOE EM Debriefs Teams on SRS Liquid Waste Contract; Protests Expected
-
Commercial Low-Level Waste
Time Runs Out for Bidding on DOE Waste Disposal Contract
Time ran out Monday for companies to submit proposals on a five-year low-level radioactive waste disposal contract with the Energy Department Office of Environmental Management, business that is now held by Waste Control Specialists and EnergySolutions. The Energy… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a subscriber to […]
-
Contracts & Procurement
Jacobs Engineering Wasn’t Only Suitor for CH2M Hill
When engineering company and Energy Department contractor CH2M was looking for potential merger partners this past spring, eventual buyer Jacobs Engineering wasn’t the only party showing interest, CH2M noted in a mammoth filing Tuesday with the U.S. Securities… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a subscriber to […]
-
Budget & Policy
Senate Passes Measure to Secure PILT Payments
With the House of Representatives already planning to look at the issue, the Senate on Oct. 19 approved a measure that could result in more predictable Payments in Lieu of Taxes (PILT) for communities surrounding federal facilities, including many across the Energy… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in […]
-
High-Level & Tank Waste
SRS Waste Facility Remains in Deliberate Ops
A major waste treatment facility at the Energy Department’s Savannah River Site as of this week remained in deliberate operations, more than four months after it was placed into the slowed work mode due to multiple safety-related incidents. Officials at… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a subscriber […]
-
Budget & Policy
NRC IG to Explore DNFSB Culture During Fiscal 2018
The Nuclear Regulatory Commission Inspector General’s Office plans in the current federal budget year to review the most serious potential vulnerabilities facing the Defense Nuclear Facilities Safety Board as part of the IG’s responsibility to examine management… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a subscriber to view […]
-
Cleanup & Remediation
Hanford Cleanup Contractor Earns $14.1M Award Fee for FY16
CH2M Hill Plateau Remediation Co. (CHPRC) has been awarded 92 percent of the fee available for fiscal 2016, the Department of Energy announced Monday. That compares to 95 percent the previous year. The Hanford Site cleanup contractor earned $14.1 million of $15.4… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in […]
-
Cleanup & Remediation
Groundwater Contamination Could Outlast UCOR Contract at Oak Ridge
Groundwater contamination at the site of old Oak Ridge Gaseous Diffusion Plant in Tennessee may persist beyond 2020, when the Department of Energy’s current $2.5 billion cleanup contract with URS-CH2M Oak Ridge (UCOR) ends. David Adler, director of DOE’s Oak… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a […]
-
Decommissioning
Piketon Mayor Urges Senators to Oppose Portsmouth Disposal Cell
Piketon, Ohio, Mayor Billy Spencer is urging the state’s U.S. senators to oppose funding to build the on-site disposal cell for waste from cleanup of the Portsmouth Gaseous Diffusion Plant. “DOE has made it clear that they fully intend to bury radioactive,… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in […]
-
Cleanup & Remediation
Wrap up: EM-1 Owendoff Briefs DNFSB
In a closed-door meeting Thursday, the acting head of the Energy Department’s nuclear cleanup program briefed the Defense Nuclear Facilities Safety Board on the 45-day review of his office’s operations and other key issues. An entry on the DNFSB calendar says… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as […]
-
Cleanup & Remediation
Correction
The Salt Waste Processing Facility that has been built by Parsons Government Services at the Department of Energy’s Savannah River Site in South Carolina should be commissioned by the end of 2018. An article in the Oct. 20 edition of Weapons Complex Monitor misstated… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be […]