Plutonium downblending operations at the Department of Energy’s Savannah River Site (SRS) will end in September 2028, signaling the nation’s transition to recycling the plutonium so it can be used as fuel for nuclear power reactors.
Jeffrey Bentley, the chief engineer in the SRS Operations Office, said Tuesday that once downblending ceases, it will take a few months to finish shipping the downblended plutonium off site. That should be completed by March 2029, he said.
Bentley gave the update to the SRS Citizens Advisory Board (CAB) during the group’s bimonthly meeting. He said the future shift in plutonium operations is in response to President Donald Trump’s May 2025 Executive Order, which calls for the DOE Secretary to “establish a program to dispose of surplus plutonium by processing and making it available to industry in a form that can be utilized for the fabrication of fuel for advanced nuclear technologies.”
Bentley said this initiative still meets the goal of ridding South Carolina of surplus plutonium, but instead allows the material to be repurposed. “You hear a lot about small modular reactors, or SMRs. That’s what we’re talking about,” he said. “They want to use some of this plutonium as a surrogate. So that is what we’re going to do now.”
All told, Bentley said SRS will contribute about eight metric tons of the total 19.7 metric tons that DOE is offering to various companies, who will fund the production of mixed oxide fuel. At least two of the companies, Curio Energy and Newcleo, announced Monday their deal with DOE to use their own technology and resources to create mixed oxide products from DOE plutonium.
“The plan is to have continuous milestones throughout the process, to ensure that the companies are able to meet their end of the bargain,” Bentley explained.
DOE previously attempted plutonium recycling through the failed MOX project, which included the SRS Mixed Oxide Fuel Fabrication Facility (MFFF). The Energy Department spent more than $8 billion on construction, from 2007 to 2018, when the project was shuttered due to delays and cost overruns. South Carolina subsequently sued the federal government, alleging broken promises and being left on the hook with unwanted plutonium in the state.
The legal battle ended in 2020, with South Carolina being awarded $600 million and a promise that the 9.5 tons of plutonium at SRS intended for MOX will be removed from the state by 2037. Bentley said that, to date, 1.76 metric tons of that material has been removed.
The federal government’s switch from downblending does not include the plutonium previously intended for MOX. It states: “The Secretary of Energy shall halt the surplus plutonium dilute and dispose program except with respect to the Department of Energy’s legal obligations to the State of South Carolina.”