Publications: ExchangeMonitor Morning Briefing
-
Contracts & Procurement
CEO Constable to Become Board Chair at Fluor
Irving, Texas-based Fluor said in a press release last week CEO David Constable will also become chairman of the company’s board of directors, with executive chairman Alan Boeckmann deciding not to seek re-election to the board during the upcoming shareholders meeting May 5. “Alan rejoined Fluor’s board as executive chairman in 2019 and has served […]
-
Cleanup & Remediation
New Acting Senior Adviser Added to EM Org Chart
Ben Harp, a Department of Energy manager for several years, has been appointed as an acting senior adviser at the $7.6-million Office of Environmental Management. Harp, a former deputy manager at the Office of River Protection at the Hanford Site in Washington state, is listed on the latest DOE Environmental Management (EM) organization chart published […]
-
Reactor Licensing & Regulation
UMass Test Reactor Can Use Fuel From Decommissioned WPI Research Plant, NRC Says
The University of Massachusetts’s research reactor can safely use fuel it obtained from a separate, decommissioned test reactor in the Bay State, the Nuclear Regulatory Commission determined in a license renewal document unveiled Monday. NRC approved UMass’s request to allow its Lowell, Mass., test reactor to use “slightly irradiated” aluminum-clad uranium-aluminide fuel it obtained from […]
-
Stockpile Stewardship
Livermore’s Nimble Series of Subcritical Experiments on Deck at NNSS
The Lawrence Livermore National Laboratory’s Nimble series of subcritical experiments, the next in line at the test site after Los Alamos’ Nightshade Series, was scheduled to run at least through Sept. 30, a lab official said last week. “We’re targeting Nimble to be done by the end of FY22 or the beginning of FY23,” Bradley […]
-
- Nuclear Energy Office Appointments Simmering on Backburner
- Net Earnings Dip at Jacobs But Revenue Remains Flat
- Cali Lawmakers Reintroduce Bill to Fast-Track SONGS Waste for Disposal
- Luján Posts Video Touting Recovery From Stroke, Plans Senate Return Soon
- DOE, Other Feds Embrace Pandemic Telecommuting, With Limits
- This Week
-
Interim Storage & Waste Disposal
Cali Lawmakers Reintroduce Bill to Fast-Track SONGS Waste for Disposal
A bipartisan bill unveiled last week aims to move a California nuclear power plant’s spent fuel inventory to the top of the Department of Energy’s collection list for when it finally starts accepting nuclear waste for disposal. If the “Spent Fuel Prioritization Act,” reintroduced Wednesday by Reps. Mike Levin (D-Calif.) and Darrell Issa (R-Calif.), became […]
-
Budget & Policy
Nuclear Energy Office Appointments Simmering on Backburner
People reportedly appointed to new senior leadership roles in the Department of Energy’s Office of Nuclear Energy, including one person who was supposed to lead the office, had yet to officially start their new jobs as of Monday, nearly a month after the personnel announcements hit. In mid-January, the White House announced that President Joe […]
-
Budget & Policy
This Week
Here are some events related to defense and civilian matters that the Exchange Monitor staff is tracking this week: 16: The Northern New Mexico Citizens’ Advisory Board meets virtually via Webex starting at 1 p.m. Mountain Time. 16: Nevada’s Environmental Management Site-Specific Advisory Board meets at 4 p.m. Pacific Time at Molasky Building, 15th Floor […]
-
Contracts & Procurement
Net Earnings Dip at Jacobs But Revenue Remains Flat
Net earnings from continuing operations fell at Jacobs, Dallas, in the first quarter of fiscal 2022, which the global engineering firm and Department of Energy contractor attributed largely to tax-related adjustments, according to financial results reported last week. Net earnings from continuing operations for the quarter ended Dec. 31, 2021, were $134 million, or $1.03 […]
-
Budget & Policy
DOE, Other Feds Embrace Pandemic Telecommuting, With Limits
A recent Government Accountability Office report confirms what most observers already assumed — the COVID-19 pandemic prompted much of the federal workforce at the Department of Energy and elsewhere to abandon their cubicles in favor of telecommuting, although the practice has its own hassles. The DOE found there were limits to its work-from-home efforts especially […]
-
Budget & Policy
Luján Posts Video Touting Recovery From Stroke, Plans Senate Return Soon
U.S. Sen. Ben Ray Luján said in a video released Sunday via Twitter “I’m on the road to recovery” from a recent stroke and should resume Senate votes in Washington, D.C., “in just a few short weeks.” First Luján, flanked by two members of his University of New Mexico medical team, said he will enter […]
-
- NNSA Planned to Extend Management Contract at Nuke Production Sites Amid Controversy About Follow-On Award
- NNSA Rethinking Mission of Nonproliferation Office; Review Imminent
- GOP Lawmakers Ask GAO to Audit NRC’s Regs for Advanced Reactors
- Oral Arguments Set Today in Paducah Litigation
- Hanford Lifecycle Cleanup Still Relies on Yucca-type Disposal Site
- DOE Announces New Appointees to Nuclear Energy Advisory Council
-
Contracts & Procurement
Oral Arguments Set Today in Paducah Litigation
A U.S. Court of Federal Claims judge is scheduled to hear oral arguments today on whether Department of Energy contractor Swift & Staley exceeds size limits for the $160-million Paducah Infrastructure Support Services set-aside contract awarded in December 2020 for the former gaseous diffusion plant in Kentucky. Although today’s hearing set for 11 a.m. Eastern […]
-
High-Level & Tank Waste
Hanford Lifecycle Cleanup Still Relies on Yucca-type Disposal Site
Something akin to the canceled Yucca Mountain high-level radioactive waste repository in Nevada is still central to disposal of thousands of canisters from the Department of Energy’s Hanford Site in Washington state, according to the lifecycle cost report published last week. The Bechtel-built Waste Treatment Plant at Hanford, expected to run for 40 years or […]
-
Advanced Nuclear & SMRs
GOP Lawmakers Ask GAO to Audit NRC’s Regs for Advanced Reactors
A pair of Republican legislators last week asked Congress’s investigative arm to look into whether the Nuclear Regulatory Commission is prepared to handle applications for future advanced nuclear reactors, according to a recent letter. The Government Accountability Office (GAO) should investigate NRC’s “preparedness to review and approve applications for advanced nuclear reactor designs,” Sen. Shelley […]
-
Budget & Policy
DOE Announces New Appointees to Nuclear Energy Advisory Council
The Department of Energy on Wednesday appointed nearly a half dozen nuclear scientists, engineers, policy experts and industry leaders to a federal council tasked with advising the agency on its current and future nuclear energy programs, according to a press release. Bill Magwood, director-general of the intergovernmental Nuclear Energy Agency, will chair the 11-person Nuclear […]
-
Contracts & Procurement
NNSA Planned to Extend Management Contract at Nuke Production Sites Amid Controversy About Follow-On Award
ALEXANDRIA, Va. — With transition to a follow-on contract derailed for now, the National Nuclear Security Administration planned to extend the existing site-management contract for two of its main nuclear-weapons production sites for up to a year, people familiar with the plans said this week. Incumbent Consolidated Nuclear Security (CNS), a team led by Bechtel […]
-
Non-Proliferation
NNSA Rethinking Mission of Nonproliferation Office; Review Imminent
ALEXANDRIA, VA — The National Nuclear Security Administration plans to reassess the priorities of its Office of Defense Nuclear Nonproliferation, senior administration officials said here this week. The review, which had yet to start as of Wednesday, will “reexamine the priorities and missions” of the Office of Defense Nuclear Nonproliferation (DNN) “in light of the […]
-
- NNSA Assessing COVID-Related Delays to Warhead Refurbs; Results in Spring
- Federal Law Does Not Allow Private Interim Storage, TX AG Argues
- Nevada Site Mining Project, Crucial for Subcritical’s Future, to be Baselined in June
- Oak Ridge Cleanup Winner Scored the Best on DOE Evaluation, GAO Finds
- DOE Closing Book on Hanford Plutonium Finishing Plant Cleanup
- DOE Hires Firm for Courting Black Engineers
- DOE to Brief SONGS Community on Interim Storage RFI This Week
-
Decommissioning
DOE to Brief SONGS Community on Interim Storage RFI This Week
Members of a California community hosting a former nuclear power plant should hear from the Department of Energy’s acting spent fuel chief this week about the agency’s effort to site a federal interim storage facility, according to a press release from the plant’s operator. Kim Petry, DOE’s acting assistant secretary for spent fuel and waste […]
-
Cleanup & Remediation
DOE Hires Firm for Courting Black Engineers
The Department of Energy’s Office of Environmental Management is issuing a no-bid contract to the minority-owned firm, Career Communications Group, to give the nuclear cleanup branch a presence at a black engineering conference later this month and help the office improve outreach to technically-savvy minority recruits. The DOE’s Cincinnati-based Environmental Management (EM) Consolidated Business Center […]
-
Interim Storage & Waste Disposal
Federal Law Does Not Allow Private Interim Storage, TX AG Argues
No existing federal law allowed the Nuclear Regulatory Commission to license a proposed commercial interim storage facility for spent nuclear fuel in Texas, the Lone Star State’s attorney general told a federal judge Monday, rolling out his long-awaited argument in the state’s lawsuit against the agency. NRC “lacks authority” to grant a license to Interim […]
-
Stockpile Stewardship
Nevada Site Mining Project, Crucial for Subcritical’s Future, to be Baselined in June
ALEXANDRIA, VA. — A mining and construction project at the Nevada National Security Site critical to the next generation of non-explosive, nuclear-stockpile testing should have its cost and schedule set in June, the head of the site’s management contractor said here Tuesday. An independent cost estimate of the U1a Complex Enhancements Project’s (UCEP) Infrastructure and […]
-
Contracts & Procurement
Oak Ridge Cleanup Winner Scored the Best on DOE Evaluation, GAO Finds
Expanding on its decision last week to deny a protest of the Department of Energy’s most recent cleanup contract at the Oak Ridge Site, the Government Accountability Office said Monday that the agency properly vetted a Veolia-led team’s proposal and took into consideration the team’s relevant past experience with cleanup jobs. The agency’s evaluation was […]
-
Life Extension Programs
NNSA Assessing COVID-Related Delays to Warhead Refurbs; Results in Spring
ALEXANDRIA, VA. — Maybe by March, the National Nuclear Security Administration will understand the extent to which COVID-19 has delayed modernization of U.S. nuclear weapons, the agency’s top Washington-based weapons official said here Tuesday. Programs under review include the W80-4 air-launched cruise missile warhead, which the agency said last year looked to be affected by […]
-
Cleanup & Remediation
DOE Closing Book on Hanford Plutonium Finishing Plant Cleanup
The Department of Energy’s Hanford Site in Washington state is done with its remediation of the Plutonium Finishing Plant, according to a recently-posted staff report from the Defense Nuclear Facilities Safety Board. The DOE Office of Environmental Management has approved Critical Decision 4 for the cleanup of the Plutonium Finishing Plant (PFP), “marking completion of […]
-
- Fluor Looking at Self-Performing Savannah River Pit Plant Construction
- Facing Legal Reality Check, NM Legislators Water Down Proposed Rad Waste Ban
- House Vote Expected Soon on Extending Budgets Through March 11
- As NNSA Mulls ‘Corrective Action’ on Disputed Production Sites Deal, No Transition Announced Yet
- COVID Caused Post-Vaccine Attrition at Sandia Procurement Shop; Materials Shortages Stretch Construction Schedules
- NRC Cans Request for Decommissioning Fund Regs Change
- Updated Hanford COVID Vax Complaint Has Same Defects, Feds Argue
- DOE Closing Book on Hanford Plutonium Finishing Plant Cleanup
- DOE Deputy Turk Briefed on DNFSB During Closed Meeting in January
-
Cleanup & Remediation
Updated Hanford COVID Vax Complaint Has Same Defects, Feds Argue
While more than 300 plaintiffs are now listed, an amended complaint last month by guards and other anti-vaccine workers at the Department of Energy’s Hanford Site in Washington has the same central weakness as the original one rejected by a federal judge, government lawyers said in a filing last week. U.S. District Judge Thomas Rice […]
-
Budget & Policy
DOE Deputy Turk Briefed on DNFSB During Closed Meeting in January
Deputy Secretary of Energy David Turk met privately with the Defense Nuclear Facilities Safety Board Jan. 27, a board spokesperson confirmed Monday. Members of the Defense Nuclear Facilities Safety Board (DNFSB) leadership of DOE and its $7.5-billion Office of Environmental Management “try to meet periodically to discuss updates,” in closed sessions, DNFSB associate director for […]
-
Interim Storage & Waste Disposal
Facing Legal Reality Check, NM Legislators Water Down Proposed Rad Waste Ban
A bill making its way through the New Mexico state legislature aimed at blocking a proposed interim storage facility for spent nuclear fuel in the state will no longer ban the storage of such waste outright, according to amendments adopted in committee Monday. A package of amendments on House Bill 127, adopted by unanimous vote […]