Publications: ExchangeMonitor Morning Briefing
-
Decommissioning
Florida Agency Urges Conditions on Crystal River Decommissioning Contract
The upcoming decommissioning of the Crystal River nuclear power plant needs more government oversight, some type of independent monitor, and better guarantees against cost overruns, a Florida government watchdog agency told the state Public Service Commission last week. “We ask you to order some modest changes” in the decommissioning contract, Charles Rehwinkel, an attorney for the […]
-
Cleanup & Remediation
No Need to Transfer FUSRAP to Energy Dept., House Panel Says
There remains no need to transfer management of the Formerly Utilized Sites Remedial Action Program (FUSRAP) from the U.S. Army Corps of Engineers to the Department of Energy, the House Appropriations Committee said Sunday. The Trump administration proposed relocating the 46-year-old cleanup program in budget requests both for the current fiscal 2020 and for the […]
-
Plutonium Pit Production
House Spending Bill Would Blank W93 Warhead, Continue Plutonium Pit Investment
A 2021 spending bill up for debate today in the House Appropriations Committee would prohibit development of a proposed new nuclear warhead for the Navy while upping investments in infrastructure to produce new plutonium triggers — but not by as much as the National Nuclear Security Administration (NNSA) wants. That is according to a detailed […]
-
Budget & Policy
House Proposal Restores Funding for Major DOE Cleanup Jobs
A trio of major Energy Department nuclear cleanup sites targeted for fiscal 2021 funding cuts by the White House would be restored at least to current levels in the House of Representatives, according to newly released details of a committee spending package. The House Appropriations Committee on Sunday released the detailed legislative report for its […]
-
- Portsmouth, Paducah Move to Phase 2 of DOE Restart
- Senate Confirms Connery, Summers to DNFSB Seats
- Oak Ridge Landfill Draft ROD Pushed Back to December
- Ex-LANL Physicist’s Last Day in Court Again Delayed as Attorney Seeks Way Around Prison Sentence
- Y-12 Finishes Overhaul of Fire Protection System
- NRC Issues Report on Decommissioning Community Advisory Boards
- Army Corps Slims Funding Estimate for FUSRAP Contract
-
Nuclear Weapons & Stockpile
Y-12 Finishes Overhaul of Fire Protection System
Consolidated Nuclear Security (CNS) has replaced nearly 10,000 sprinkler heads at the Y-12 National Security Complex in Tennessee, completing a $46 million retrofit of safety hardware last touched in the 1960s, according to a press release this week. The new sprinkler heads, installed in six different facilities, replace some that were at or near the […]
-
Cleanup & Remediation
Army Corps Slims Funding Estimate for FUSRAP Contract
The Army Corps of Engineers has slimmed the annual funding expected to be available for the next contract for cleanup of the Luckey Site in Ohio under the Formerly Utilized Sites Remedial Action Program (FUSRAP). In a second set of responses to vendor questions on the procurement, posted online Wednesday, the Army Corps said contractors […]
-
Cleanup & Remediation
Portsmouth, Paducah Move to Phase 2 of DOE Restart
The Portsmouth Site in Ohio and the Paducah Site in Kentucky have received approval from the Energy Department to bring back additional personnel who have largely been off-site for months during the COVID-19 pandemic. “Your commitment to enhanced safety and deliberate restart of planned project activities has paved the way for moving to Phase 2 […]
-
Nuclear Weapons & Stockpile
Senate Confirms Connery, Summers to DNFSB Seats
The Senate has approved the nominations of Thomas Summers and Joyce Connery to seats on the Defense Nuclear Facilities Safety Board (DNFSB). The Senate approved the two by voice vote on July 2, according to the website Congress.gov. That came after both were nominated in May and then reported out of the Senate Armed Services […]
-
Cleanup & Remediation
Oak Ridge Landfill Draft ROD Pushed Back to December
The Energy Department has delayed publication of a draft record of decision (ROD) for a new 2.2-million-cubic yard landfill for the Oak Ridge Site in Tennessee by up to six months. Energy Department Office of Environmental Management officials at Oak Ridge agreed in April, after consulting with state and federal regulators, to push back publication […]
-
Decommissioning
NRC Issues Report on Decommissioning Community Advisory Boards
Community advisory boards for nuclear power plants in decommissioning benefit from being formed early in the process and with a clear framework for their operation, the Nuclear Regulatory Commission said in a report made public Thursday. The agency was required to prepare the report, on best practices for establishment and operation of the local panels, […]
-
National Laboratories
Ex-LANL Physicist’s Last Day in Court Again Delayed as Attorney Seeks Way Around Prison Sentence
A federal judge has delayed sentencing the former Los Alamos National Laboratory physicist who pleaded guilty to lying about his connection to a Chinese talent recruitment program, giving the defense attorney a chance to persuade the court not to send his client to prison. It is the second sentencing delay for Turab Lookman, who worked […]
-
- House Panel Advances $49.6B Energy Appropriations Bill
- Three Big NNSA Production Sites Return to Normal Ops, With Max Telework
- Savannah River COVID-19 Case Count Stands at 70
- New Hanford Contractors Still Waiting for DOE Green Light
- Goldstein to Retire After Six Years as Livermore Director, 36 Years at Lab
- Los Alamos DP Road Cleanup Would Receive $50M Under House Bill
- BWXT Hires New President for Medical Isotope Business
-
Cleanup & Remediation
Savannah River COVID-19 Case Count Stands at 70
The Savannah River Site in South Carolina as of Wednesday had confirmed 70 cases of COVID-19 among its workforce, the most known within the facilities of the Department of Energy nuclear complex. The Energy Department this week recorded the first COVID-19-related death among the site’s 11,000-person workers. Officials said Monday that an employee of operations […]
-
Budget & Policy
House Panel Advances $49.6B Energy Appropriations Bill
The House Appropriations energy and water development subcommittee needed just 30 minutes Tuesday to advance its latest funding bill for consideration by the full committee. Subcommittee members proposed no amendments to the $49.6 billion appropriations legislation covering the Department of Energy and other agencies, but did air complaints on matters including the level of nuclear-weapon […]
-
Cleanup & Remediation
Los Alamos DP Road Cleanup Would Receive $50M Under House Bill
A spending plan advanced by the House Appropriations energy and water development subcommittee Tuesday would provide $50 million for the Energy Department’s Los Alamos National Laboratory (LANL) to clean up recently discovered contamination along a nearby public road. The money for investigation and remediation of an area along DP Road in Los Alamos County would […]
-
Contracts & Procurement
BWXT Hires New President for Medical Isotope Business
A nuclear medicine specialist is taking over as head of BWX Technologies’ medical isotope business after a stint as an adviser to a rival company. Martyn Coombs will on July 20 succeed Tom Burnett as president of BWXT ITG Canada, according to a press release Monday. Burnett is retiring. Coombs will assume profit and loss […]
-
National Laboratories
Goldstein to Retire After Six Years as Livermore Director, 36 Years at Lab
William Goldstein confirmed Tuesday he will retire as director of the Department of Energy’s Lawrence Livermore National Laboratory, as soon as the nation’s second nuclear-design facility finishes the potentially lengthy search for a replacement. Goldstein became the Livermore, Calif., lab’s 12th director on March 31, 2014. He joined the lab’s Physics Directorate in 1984 and […]
-
Contracts & Procurement
New Hanford Contractors Still Waiting for DOE Green Light
Although they withstood bid protests in April, winners of two multibillion-dollar contracts at the Hanford Site in Washington state still have not received Department of Energy notices to proceed to the jobs. Neither Hanford/s new support services contractor, nor the new contractor for cleanup of the Central Plateau, have gotten the go-ahead yet, an agency […]
-
Nuclear Weapons & Stockpile
Three Big NNSA Production Sites Return to Normal Ops, With Max Telework
The National Nuclear Security Administration’s (NNSA) three major production sites have returned to normal operations with maximum telework even as cases of COVID-19 rise again around the nation. This means many support services workers are back on-site at the nuclear-weapon facilities, even while people who can easily work remotely continue to do so. A spokesperson […]
-
- No Big Raise for NNSA In House Panel’s FY21 Spending Bill
- House Bill Would Keep DOE Nuclear Cleanup at $7.5B in Fiscal 2021
- House Panel Backs $27.5 Million for DOE Interim Waste Storage Work
- Appropriations Bill Meets NRC Budget Request
- Amendment to Senate NDAA Reduces Proposed Pentagon Influence Over NNSA Budget
- Death From COVID-19 Confirmed at Savannah River Site
- LANL Still ‘Investigating’ Potential Employee Plutonium Intake
- DOE Plans Extensions for Hanford Tank Manager, Lab Testing Vendor
- Navarro Avoids Bid Protest on New Nevada Environmental Contract
- Massachusetts’ Court Petition on Pilgrim Plant Sale Withdrawn
-
Contracts & Procurement
Navarro Avoids Bid Protest on New Nevada Environmental Contract
Navarro Research and Engineering faces no challenges to Energy Department contract it won last month for a potential 10-year, $350 million contract to continue providing environmental services at the Nevada National Security Site. The Energy Department awarded the contract to the incumbent on June 17. The window for protest to the Government Accountability Office (GAO) […]
-
Budget & Policy
No Big Raise for NNSA In House Panel’s FY21 Spending Bill
A House Appropriations panel on Monday followed through with its promise not to grant a $20-billion budget request for civilian nuclear weapons programs in a fiscal 2021 spending bill that would also forbid preparation for a nuclear yield-test, limit Pentagon influence on Department of Energy budgets, and potentially slow development of a proposed new nuclear […]
-
Budget & Policy
Amendment to Senate NDAA Reduces Proposed Pentagon Influence Over NNSA Budget
The Senate last week adopted language that would scale back, but not eliminate, some of the new oversight and influence the chamber’s Armed Services Committee proposed to give the Pentagon over civilian nuclear weapons budgets via the fiscal 2021 National Defense Authorization Act (NDAA). On Thursday, the Senate unanimously adopted an amendment from Sens. Maria […]
-
National Laboratories
LANL Still ‘Investigating’ Potential Employee Plutonium Intake
The Los Alamos National Laboratory in New Mexico is still investigating whether any of 15 employees working on plutonium-238 oxide were internally contaminated with the material last month after the apparent puncture of a glove-box glove. “Fifteen Laboratory workers are being evaluated for potential exposure. The area inside the Plutonium Facility where this occurred has […]
-
Contracts & Procurement
DOE Plans Extensions for Hanford Tank Manager, Lab Testing Vendor
The Energy Department last week said it plans up to yearlong extensions to existing contracts at the Hanford Site in Washington state for management of underground tank waste and laboratory testing services. Washington River Protection Solutions’ (WRPS) long-term contract, now valued at about $7.8 billion, could be extended to Sept. 30, 2021, according to a […]
-
Budget & Policy
House Bill Would Keep DOE Nuclear Cleanup at $7.5B in Fiscal 2021
The House Appropriations Committee indicated Monday it plans to fund the Energy Department’s Office of Environmental Management at $7.46 million for fiscal 2021. The nuclear cleanup funding is roughly equal to the amount appropriated for fiscal 2020, which ends Sept. 30, and an increase of $1.4 billion from the request submitted in February by the […]
-
Cleanup & Remediation
Death From COVID-19 Confirmed at Savannah River Site
The Energy Department confirmed Monday that an employee of the prime contractor for the Savannah River Site in South Carolina has died as a result of COVID-19. “I regret to inform you that we have lost a member of the SRNS [Savannah River Nuclear Solutions] team to a COVID-related death,” SRNS President and CEO Stuart […]
-
Decommissioning
Massachusetts’ Court Petition on Pilgrim Plant Sale Withdrawn
The commonwealth of Massachusetts’ court challenge to the transfer of the federal license for the Pilgrim Nuclear Power Station is being dismissed with prejudice, which would prevent it from being refiled. The parties to the petition for review filed the dismissal agreement on June 30 in the U.S. Court of Appeals for the District of […]
-
Budget & Policy
Appropriations Bill Meets NRC Budget Request
The Nuclear Regulatory Commission would receive its full budget request for the upcoming 2021 federal fiscal year via the House Appropriations energy and water development legislation unveiled Monday. That covers $849.9 million for the core operations at the federal regulator, plus just under $13.5 million for the NRC Inspector General’s Office. That would be good […]