Publications: ExchangeMonitor Morning Briefing
-
Reactor Licensing & Regulation
NRC Commissioner Wright Nominated to Full Term
The White House on Jan. 6 nominated Nuclear Regulatory Commission member David Wright to a full five-year term, through June 30, 2025. The move came as no surprise – the Trump administration had stated in November it intended to reappoint Wright. Wright’s nomination was referred to the Senate Environment and Public Works Committee. As of […]
-
- Bid Protest Filed Over Hanford Central Plateau Award
- DNFSB Hopes to Meet With Brouillette By March
- NRC Commissioner Wright Nominated to Full Term
- Former LANL Physicist to Change Not Guilty Plea to Lying About Chinese Gov’t Connection
- Bill Would Increase New Mexico Oversight of Radioactive Waste Storage
- Huntington Ingalls Picks New Columbia Program Director
- Another Group Argues Case Against SONGS Spent-Fuel Storage
- West Valley Task Force Buoyed by Reauthorization, Security Funding
-
Contracts & Procurement
Bid Protest Filed Over Hanford Central Plateau Award
A Bechtel-led joint venture filed a protest Tuesday with the U.S. Government Accountability Office (GAO) over the December award of a potential 10-year, $10-billion cleanup contract at the Hanford Site in Washington state. The Project W Restoration partnership is led by Bechtel National, and the other members of the venture are Tetra Tech and EnergySolutions, […]
-
Interim Storage & Waste Disposal
Bill Would Increase New Mexico Oversight of Radioactive Waste Storage
Legislation introduced Wednesday in the New Mexico Senate would update the responsibilities of the state Radioactive Waste Consultation Task Force to include oversight of commercial spent nuclear fuel storage. The task force was established in the 1978 state Radioactive and Hazardous Materials Act, largely to act as the New Mexico government’s negotiator for siting, licensing, […]
-
Cleanup & Remediation
West Valley Task Force Buoyed by Reauthorization, Security Funding
Passage of a law to reauthorize the U.S. Energy Department’s cleanup of the West Valley Demonstration Project in New York state drew kudos Wednesday from participants at a local meeting. The measure, which passed the U.S. Senate on Dec. 2 and was subsequently signed into law by President Donald Trump on Dec. 20, would reauthorize […]
-
Naval Nuclear Propulsion
Huntington Ingalls Picks New Columbia Program Director
Huntington Ingalls Industries (HII) said Monday it has appointed Brandi Smith as program director for the U.S. Navy’s Columbia-class submarine program at the company’s Newport News Shipbuilding division. There was no incumbent Columbia program director at HII, according to a Tuesday email from a spokesperson for the shipbuilding subcontractor for the Navy’s next nuclear-armed ballistic-missile […]
-
Cleanup & Remediation
UniTech Names New Vice President
Massachusetts-based UniTech Services Group has made Michael Bovino its new vice president, effective Jan. 1. Bovino brings 35 years of management and contamination control experience to the post at the nuclear services company. The executive is a 29-year veteran of UniTech and its parent, UniFirst Corp., most recently serving as division general manager responsible for […]
-
Decommissioning
New York Lawmakers Have Questions on Indian Point Sale
Three members of New York state’s delegation to Congress have posed a long list of questions to Holtec International regarding its plans to acquire and decommission the Indian Point Energy Center. The lawmakers submitted their questions to Holtec President and CEO Kris Singh in writing on Nov. 21, 2019. Their letter was posted to the […]
-
Cleanup & Remediation
California Regulators Hope to Issue Final Santa Susana Environmental Reports by Summer
The California Department of Toxic Substances Control is “making every effort” to publish the final versions of two long-awaited environmental reports for cleanup of the Santa Susana Field Laboratory in this summer, a spokesman said this month. The state agency oversees remediation of the 2,800-acre site in Ventura County, about 30 miles northwest of downtown […]
-
Decommissioning
Nuclear Decommissioning Trusts Held $64.7B at End of 2018
Decommissioning trust funds for 119 operational and retired nuclear power reactors together held $64.7 billion at the end of 2018, according to the latest update from the U.S. Nuclear Regulatory Commission. Agency staff on Dec. 31 provided the NRC commissioners with its review of the 2019 decommissioning funding status reports from nuclear utilities. The report, […]
-
- NNSA Boss Unhappy With Rumored $17.5B Budget Request for 2021, Report Says
- California Regulators Hope to Issue Final Santa Susana Environmental Reports by Summer
- Savannah River Contractor Must Pay Another $295K to Former Employee
- California Watchdog Argues for NRC Suspension of SONGS Decommissioning
- New York Lawmakers Have Questions on Indian Point Sale
- Nuclear Decommissioning Trusts Held $64.7B at End of 2018
- UniTech Names New Vice President
-
Budget & Policy
NNSA Boss Unhappy With Rumored $17.5B Budget Request for 2021, Report Says
The head of the U.S. National Nuclear Security Administration (NNSA) is deeply unhappy with a rumored budget request of roughly $17.5 billion for the upcoming 2021 fiscal year, a new digital publication reported Tuesday. The figure would prevent the semiautonomous Energy Department branch from meeting the goals set out in the 2018 Nuclear Posture Review, […]
-
Decommissioning
California Watchdog Argues for NRC Suspension of SONGS Decommissioning
A California advocacy group took its latest crack Tuesday at persuading the U.S. Nuclear Regulatory Commission to order a halt to decommissioning of the San Onofre Nuclear Generating Station (SONGS). The NRC’s Petition Review Board heard Public Watchdogs’ case for approval of a 25-page petition filed in September. The meeting was not a hearing, but […]
-
Cleanup & Remediation
Savannah River Contractor Must Pay Another $295K to Former Employee
A former employee of the liquid waste contractor for the U.S. Energy Department’s Savannah River Site has been awarded $240,107 in front pay she would have earned if the company had not unfairly denied her employment after she was initially laid off. In addition, U.S. District Judge J. Michelle Childs ruled on Jan. 17 that […]
-
- MOX Services Hit With Misused Funds, Retaliation Claims in Unsealed Suit
- Potential Bidders Have Many Questions About DOE National Deactivation Contract
- NNSA Pledges Several Steps Toward Common Financial Reporting This Year
- BWXT Vice President Becomes Chief Administrative Officer
- Orano Completes Highest Heat-Load Spent Fuel Transfer
-
Interim Storage & Waste Disposal
Orano Completes Highest Heat-Load Spent Fuel Transfer
The logistics branch of nuclear company Orano at the end of 2019 wrapped up the transfer to dry storage of spent fuel canisters with the highest heat load to date at U.S. power plants, according to a Jan. 15 press release. At the customer’s request, Orano is not identifying the nuclear power plant where the […]
-
Budget & Policy
NNSA Pledges Several Steps Toward Common Financial Reporting This Year
The U.S. National Nuclear Security Administration (NNSA) pledged to this year implement several incremental steps toward a common financial reporting system that Congress has ordered put in place by December, according to a new Government Accountability Office (GAO) report. The GAO’s report includes a letter from NNSA Administrator Lisa Gordon-Hagerty describing three steps the agency […]
-
Cleanup & Remediation
BWXT Vice President Becomes Chief Administrative Officer
Lynchburg, Va. -based BWX Technologies has promoted Richard Loving to a newly created post of senior vice president and chief administrative officer (CAO). Loving has been senior vice president for human resources at BWXT since mid-2016. He has about 40 years of management experience in manufacturing, energy, and government operations, according to a press release. […]
-
Plutonium Pit Production
MOX Services Hit With Misused Funds, Retaliation Claims in Unsealed Suit
A recently unsealed lawsuit accuses a former U.S. Department of Energy contractor at the Savannah River Site’s now-canceled plutonium recycling plant of filings thousands of dollars’ worth of false claims by paying out relocation packages to an employee who never actually moved. Then, when employee Peter Michael Wanco Jr. resigned from MOX Services after allegedly […]
-
Contracts & Procurement
Potential Bidders Have Many Questions About DOE National Deactivation Contract
The U.S. Energy Department’s request for proposals (RFP) for the Nationwide Deactivation, Decommissioning, and Removal contract has seemingly sparked significant interest from the contractor community. Vendors submitted 152 questions in response to the agency procurement for the potential 10-year, $3 billion award. The DOE Office of Environmental Management in December released the final request for […]
-
- NNSA Extends JASONs Contract for One Year
- Extra Week Provided for Savannah River Lab Contract Comments
- Senator Questions Potential Reduction in NRC Spent-Fuel Storage Inspections
- Entergy Sues Feds Again Over Spent Fuel Storage Costs
- NRC Cites Two Violations at Westinghouse Fuel Plant
- EPA Honors Energy Department for Fernald Cleanup
- Publication Notice
-
Contracts & Procurement
NNSA Extends JASONs Contract for One Year
The U.S. National Nuclear Security Administration (NNSA) is extending its contract with the panel of scientists known as JASON for up to a year, while the Pentagon works to resurrect its old arrangement with the group. The semiautonomous Department of Energy nuclear weapons agency retained the JASONs last year for a trio of studies including […]
-
Cleanup & Remediation
EPA Honors Energy Department for Fernald Cleanup
The U.S. Energy Department’s Fernald Preserve in Ohio, a former Superfund site, has been honored for reuse by the U.S. Environmental Protection Agency (EPA). “The Fernald site has come full circle with restoration, creating one of the largest man-made wetlands in Ohio,” said DOE’s Office of Legacy Management Deputy Manager Peter O’Konski, during a November […]
-
Reactor Licensing & Regulation
Senator Questions Potential Reduction in NRC Spent-Fuel Storage Inspections
One senator on Wednesday questioned the U.S. Nuclear Regulatory Commission’s consideration of cutting back on inspections of spent fuel storage facilities at the nation’s nuclear power plants. Sen. Tom Carper (D-Del.) raised the issue during a hearing of the Senate Environment and Public Works Committee featuring testimony from two senior NRC officials. “When we have […]
-
Reactor Licensing & Regulation
NRC Cites Two Violations at Westinghouse Fuel Plant
The U.S. Nuclear Regulatory Commission last week cited a Westinghouse fuel facility in South Carolina with two violations of federal nuclear rules, but details were scarce this week. The two Severity Level IV violations were identified in an inspection of the Columbia Fuel Fabrication Facility (CFFF) from Nov. 18-21, 2019, according to a Jan. 10 […]
-
Interim Storage & Waste Disposal
Entergy Sues Feds Again Over Spent Fuel Storage Costs
The Louisiana branch of power company Entergy this week filed another lawsuit seeking to recoup ongoing expenses incurred due to the federal government’s breach of its legal mandate to remove spent fuel from the River Bend Station nuclear power plant. This is the third such lawsuit filed by Entergy Louisiana and its predecessor, Entergy Gulf […]
-
Contracts & Procurement
Extra Week Provided for Savannah River Lab Contract Comments
Comments on the U.S. Energy Department’s request for information (RFI) on a possible stand-alone management contract for the Savannah River National Laboratory (SRNL) in South Carolina are now due by 3 p.m. ET Jan. 29. The DOE Office of Environmental Management announced the one-week extension for market research comments in a Tuesday notice on a […]
-
Budget & Policy
Publication Notice
Weapons Complex Morning Briefing will not be published Monday in observance of Martin Luther King Jr. Day. Look for the next issue in your inbox on Tuesday, Jan. 21.
-
- Bid Protest Filed Over Hanford Site Services Contract
- DOE Inspector General Urges More Clarity, Standardization on Hanford Radiation Records
- Nevada Plutonium Lawsuit Continuing at Least to Early March
- Centerra Parent Downgraded by Credit Raters, Signs Forbearance Agreement
- B52 Loses Nuclear Gravity Bombs, Per Air Force Order
- NRC Accepting Hearing Petitions for SHINE Isotope Plant License
- Waste Management Symposia Hires New Manager
- Correction
-
Cleanup & Remediation
DOE Inspector General Urges More Clarity, Standardization on Hanford Radiation Records
The U.S. Energy Department Office of Inspector General (IG) is urging management at the Hanford Site in Washington state to provide more clarity and standardization in its recordkeeping for employee radiation dose. Greater use of standard forms and clearer lines of authority would better ensure that accurate employee histories of radiation dosage are kept, according […]