Publications: ExchangeMonitor Morning Briefing
-
Contracts & Procurement
Operations Contractor SRNS Again Scores High for Savannah River Work in Fiscal 2019
Fluor-led Savannah River Nuclear Solutions (SRNS) took home $25.6 million or 95% of its nearly $27 million in available fee for management and operation of the Energy Department’s Savannah River Site in South Carolina between Aug. 1, 2018 and July 31, 2019. The just-released fee determination scorecard from the DOE Office of Environmental Management shows […]
-
Transuranic Waste
Idaho Shipments to WIPP Paused Briefly in November Due to Problem Drum
The U.S. Energy Department’s Waste Isolation Pilot Plant in New Mexico briefly held up some shipments of transuranic waste from the Idaho National Laboratory in November after discovery of a hole in one drum, according to the Defense Nuclear Facilities Safety Board (DNFSB). The 4 millimeter-hole was discovered Nov. 2 by WIPP inspectors in a […]
-
Budget & Policy
Head of U.S. Nuclear Industry Council Dies
David Blee, president and CEO of the U.S. Nuclear Industry Council business consortium, died Sunday apparently while visiting family in Kentucky. His death was confirmed Monday by USNIC Director Caleb Ward. “From what I understand, David had a negative reaction with the medication he was taking to get over his cold,” Ward said in a […]
-
Contracts & Procurement
Perma-Fix Joint Venture Scores $15M Cleanup Contract at DOE Lab
A joint venture of Perma-Fix Environmental Services and ERRG in December sealed a contract worth at least $15 million for cleanup services at the U.S. Department of Energy’s Lawrence Berkeley National Laboratory in California. The 18-month contract covers remediation, construction, and waste management at the Alameda County complex, according to a Dec. 23 press release […]
-
Decommissioning
Holtec Projects $2.3 Billion Price Tag for Indian Point Decommissioning
Holtec International believes it can complete decommissioning of the three nuclear reactors at the Indian Point Energy Center in upstate New York in 12 to 15 years at a cost of $2.3 billion, according to a new filing with the U.S. Nuclear Regulatory Commission. Power company Entergy said in April it would sell the Buchanan, […]
-
- No NNSA Decision on Next-Gen Enrichment Tech as December Draws to Close
- Head of U.S. Nuclear Industry Council Dies
- Comment Period on Disposal of Savannah River Defense Waste Extended
- DOE Sets Deadline for Savannah River Lab Contract Briefings
- Holtec Projects $2.3 Billion Price Tag for Indian Point Decommissioning
- Perma-Fix Joint Venture Scores $15M Cleanup Contract at DOE Lab
- Publication Notice
-
Uranium Enrichment & Fuel Cycle
No NNSA Decision on Next-Gen Enrichment Tech as December Draws to Close
If the U.S. National Nuclear Security Administration (NNSA) still plans to select its preferred technology for the nation’s next domestic uranium enrichment plant by the end of 2019, the agency is taking the decision down to the last few hours of the year. It was around this time of year in 2016 that the semiautonomous […]
-
Contracts & Procurement
DOE Sets Deadline for Savannah River Lab Contract Briefings
Potential bidders on the management and operations contract for the U.S. Department of Energy’s Savannah River National Laboratory in South Carolina have until noon ET on Jan. 9 to sign up for briefings. The Energy Department is providing new details on its Jan. 16 industry day for the stand-alone lab contract. The DOE Office of Environmental […]
-
Budget & Policy
Publication Notice
Weapons Complex Morning Briefing will not be published Wednesday in observance of New Year’s Day. Look for the next issue in your inbox on Thursday.
-
Defense Low-Level Waste
Comment Period on Disposal of Savannah River Defense Waste Extended
The U.S. Department of Energy is extending the comment period by more than a month on its draft environmental assessment for the plan to treat and dispose of about 10,000 gallons of recycled wastewater from the Savannah River Site at a low-level radioactive waste site located out of South Carolina. Stakeholders now have until Feb. […]
-
Plutonium Pit Production
MOX Services Played Fast and Loose With Subcontract Costs, DOE IG Says
MOX Services, prime contractor for the canceled Mixed Oxide Fuel Fabrication Facility (MFFF), played fast and loose with federal contracting rules, the U.S. Department of Energy’s inspector general wrote in a scathing report published days before the winter holiday. The audit, which focused on MOX Services’ administration of project subcontractors, identified some $8.5 million in […]
-
Cleanup & Remediation
Lawyer Tapped to Lead Wash. State Ecology Department
Gov. Jay Inslee (D) has picked a state lawyer to lead the Washington Department of Ecology. Laura Watson succeeds Maia Bellon, who announced her retirement on Dec. 2 after leading the state agency since 2013. The Department of Ecology, through its Nuclear Waste Program, regulates the U.S. Department of Energy’s Hanford Site, as well as […]
-
Transuranic Waste
Energy Dept. Appoints New Acting Manager for WIPP
A veteran of 28 years in the commercial nuclear power industry is the new acting manager for the U.S. Department of Energy office that oversees the Waste Isolation Pilot Plant (WIPP) in New Mexico. Greg Sosson was apparently appointed to the temporary detail earlier this month, according to the Carlsbad Field Office website. Sosson joined […]
-
Delivery Systems & Nuclear Triad
General Dynamics Takes $300M Trident II Support Contract
The U.S. Navy on Dec. 16 awarded General Dynamics Mission Systems a $300 million contract for fiscal years 2020-2023 for U.S. and U.K. Trident II (D-5) support work. This specifically covers Trident II fleet ballistic missiles submarine fire control system, guided missile submarine attack weapon control system, and support equipment rework facility support. Most of […]
-
Decommissioning
Fort Belvoir Reactor Decommissioning to End in 2025, Army Corps Says
The U.S. Army Corps of Engineers (USACE) expects to complete decommissioning of a long-retired nuclear power plant at Fort Belvoir, Va., in 2025, after which the property would be available for unrestricted use. The five-year schedule would cover the full scope of decommissioning the SM-1 reactor and associated infrastructure: site preparation, material removal, disassembly, cleanup, […]
-
Contracts & Procurement
Savannah River Environmental Draft RFP Due Out Soon
The U.S. Energy Department anticipates by early February issuing a draft request for proposals (RFP) for waste management at the Savannah River Site in South Carolina. The DOE Office of Environmental Management said in a Dec. 23 procurement notice the draft solicitation for what it now calls the Savannah River Site Integrated Mission Completion Contract […]
-
Cleanup & Remediation
New Mexico Meeting to Focus on 2016 Los Alamos Consent Order
The New Mexico Environment Department (NMED) has scheduled a Jan. 9 public meeting to discuss a consent order signed with the U.S. Energy Department in 2016 that updated remediation plans for the Los Alamos National Laboratory. The meeting will begin at 5:30 p.m. MT at the University of New Mexico-Los Alamos campus on University Drive, NMED […]
-
- Savannah River Environmental Draft RFP Due Out Soon
- MOX Services Played Fast and Loose With Subcontract Costs, DOE IG Says
- Energy Dept. Appoints New Acting Manager for WIPP
- New Mexico Meeting to Focus on 2016 Los Alamos Consent Order
- Fort Belvoir Reactor Decommissioning to End in 2025, Army Corps Says
- Energy Department Moves Ahead With Mercury Storage Plans at WCS
- Lawyer Tapped to Lead Wash. State Ecology Department
- General Dynamics Takes $300M Trident II Support Contract
-
Commercial Low-Level Waste
Energy Department Moves Ahead With Mercury Storage Plans at WCS
Waste Control Specialists (WCS) this month received approval from the Texas Commission on Environmental Quality to provide long-term storage of elemental mercury at its Andrews County waste facility for the U.S. Department of Energy. The Energy Department said in a Dec. 27 press release that the Texas regulators approved a modification to the Dallas-based company’s […]
-
- Energy Dept. Eyes Stand-Alone Management Contract for Savannah River Lab
- Hanford Contract Debriefs Wait Until After the Holidays
- NNSA Tweaking Plan to Implement Safety Board Recommendations for Pantex
- NNSA Takes Delivery of New Radiation Monitoring Aircraft
- GAO Wants More Efficient Management of 3 Gaseous Diffusion Plants
- Strategic Management Solutions Loses Bid Protest Over DOE Tech Support Contract
- Feds Urged to Halt Weapon-Grade Uranium Exports for Isotope Production
- Publication Notice
-
Contracts & Procurement
Strategic Management Solutions Loses Bid Protest Over DOE Tech Support Contract
The Government Accountability Office (GAO) on Tuesday denied a bid protest over a five-year, $137 million contract issued to a Professional Project Services (Pro2Serve) affiliate to provide technical support to the U.S. Energy Department’s Portsmouth/Paducah Project Office (PPPO). A rival bidder, Strategic Management Solutions Inc. (SMSI), filed its initial protest on Sept. 9, followed by […]
-
Cleanup & Remediation
GAO Wants More Efficient Management of 3 Gaseous Diffusion Plants
The U.S. Government Accountability Office wants the Department of Energy to fulfill a 2007 pledge to manage three former uranium enrichment plants in an integrated manner. The DOE Office of Environmental Management is supervising cleanup of retired facilities in Piketon, Ohio, Paducah, Ky., and Oak Ridge, Tenn., as three independent sites, which is costly and […]
-
Non-Proliferation
Feds Urged to Halt Weapon-Grade Uranium Exports for Isotope Production
A group of 11 nuclear security and health experts on Wednesday urged the heads of the U.S. Departments of Energy and Health and Human Services to find that the federal government no longer needs to export weapon-grade uranium for foreign production of the medical isotope molybdenum-99 (Mo-99). The American Medical Isotopes Production Act (AMIPA), enacted […]
-
Budget & Policy
Publication Notice
Weapons Complex Morning Briefing will not be published during the week of Dec. 23-27, in observance of the Christmas holiday. Look for the next edition in your inbox on Monday, Dec. 30.
-
Contracts & Procurement
Energy Dept. Eyes Stand-Alone Management Contract for Savannah River Lab
The U.S. Department of Energy is considering a stand-alone contract for management of its Savannah River National Laboratory in South Carolina. The DOE Office of Environmental Management on Wednesday issued a request for information/sources sought notice for management and operations of the government lab, which is currently under the full Savannah River Site contract. The […]
-
Nuclear Weapons & Stockpile
NNSA Tweaking Plan to Implement Safety Board Recommendations for Pantex
The U.S. National Nuclear Security Administration (NNSA) is revising its plan to implement recommendations the Defense Nuclear Facilities Safety Board made this year about the Pantex nuclear-weapon servicing plant. “The Department of Energy has accepted the need to revise and update our implementation plan,” James McConnell, NNSA associate administrator for safety, infrastructure, and operations, said […]
-
Contracts & Procurement
Hanford Contract Debriefs Wait Until After the Holidays
The U.S. Energy Department debriefings on two major contract awards announced this month at the Hanford Site in Washington state will wait until January, two sources said this week. On Dec. 12, Central Plateau Cleanup Co., comprised of AECOM, Fluor, and Atkins affiliates, won the potential 10-year, $10 billion contract for ongoing remediation of Hanford’s […]
-
Non-Proliferation
NNSA Takes Delivery of New Radiation Monitoring Aircraft
JOINT BASE ANDREWS, Md. — The U.S. National Nuclear Security Administration (NNSA) took delivery of three new radiation monitoring aircraft recently and put them on display here Wednesday at one of two home bases for the airborne leg of the agency’s counterterrorism office. The three new King Air 350ER airplanes provided by Textron Aviation of […]
-
- DOE Inching Toward Full 2020 Appropriations as Bills Cruise Through Congress
- Hanford Would Receive $2.5B in Energy and Water Appropriations Compromise
- Nevada Demands Oral Arguments in Plutonium Lawsuit
- Part of W80 Budget Going to Sea-Launched Cruise Missile Study
- DNFSB Would Have to Keep 110 Full-Time Employees Under Proposed 2020 Budget
- Bids for Energy Dept. Nationwide Deactivation Contract Due in February
- NRC Rejects Requests for Immediate Stay of Pilgrim Plant License Transfer
- Veolia to Build Facility to Control Runoff from Portsmouth X-326 Building Demolition
- Senate Committee Advances Nominee for NRC Inspector General
-
Life Extension Programs
Part of W80 Budget Going to Sea-Launched Cruise Missile Study
Congress wants the National Nuclear Security Administration to slide about $5.5 million from the maintenance budget for the W80 cruise-missile warhead into a Pentagon study to select a design for a nuclear-tipped, sea-launched cruise missile, according to a compromise 2020 spending bill that would fund the agency through September. The Donald Trump administration proposed studying […]