Publications: ExchangeMonitor Morning Briefing
-
Decommissioning
Massachusetts Plans Stay Request on License Transfer Approval for Pilgrim Plant
The commonwealth of Massachusetts has signaled it will request a hold on the anticipated approval from the U.S. Nuclear Regulatory Commission this week of the license transfer application for the Pilgrim Nuclear Power Station. Staff at the federal regulator indicated in a filing last week that it was prepared around Aug. 21 to authorize the […]
-
Interim Storage & Waste Disposal
Full Consent for Nuclear Waste Disposal ‘An Excuse to Do Nothing,’ Senators Told
Requiring comprehensive consent to build a nuclear waste disposal site is “an excuse to do nothing,” according to a leader in the Nevada county that would be home to the long-delayed repository under Yucca Mountain. “To believe that any controversial project in the 21st century will get consent from every level of government – state, […]
-
Contracts & Procurement
Hanford Tank Contractor Extension Could be Worth $725M
The AECOM-led incumbent vendor that is managing underground radioactive waste tanks at the Hanford Site in Washington state expects its latest contract extension from the U.S. Energy Department could be worth $725 million. The business extension will keep Washington River Protection Solutions (WRPS) on the job for up to 12 months, from Oct. 1, 2019, […]
-
- Hanford Tank Contractor Extension Could be Worth $725M
- Jacobs to Buy Wood Group Nuclear Business
- After Appeals Defeat, Nevada Wants Judge for Force Plutonium Out
- Savannah River Ends Interim Salt Waste Processing, Prepares for SWPF Startup
- Bechtel, DOE Take Another Step Toward Completing Hanford Vit Plant
- National Academies Urges More Study on Hanford Low-Activity Waste Treatment Options
- Centrus Ticks First Milestone in New Centrifuge Contract
- Energy Department Starts Market Research on Technical Support for WIPP Office
- Massachusetts Plans Stay Request on License Transfer Approval for Pilgrim Plant
- Former NNSA No. 2 to Lead Government Affairs for Nevada Site Contractor
- Full Consent for Nuclear Waste Disposal ‘An Excuse to Do Nothing,’ Senators Told
- Holtec Transport Cask Gets NRC Approval
- Calif. Senators Urge Federal Action on Used Nuclear Fuel Removal
-
Interim Storage & Waste Disposal
Holtec Transport Cask Gets NRC Approval
The U.S. Nuclear Regulatory Commission has certified Holtec International’s latest spent nuclear fuel transportation package. The Camden, N.J., energy technology company last week announced the approval following a review that began in February 2018, which will allow it to deploy the HI-STAR 100MB. Management expects it will be used to ship spent fuel from nuclear […]
-
Decommissioning
Jacobs to Buy Wood Group Nuclear Business
Jacobs Engineering on Tuesday said it would pay £250 million ($302 million) to acquire the nuclear branch of the Scotland-based John Wood Group. The deal is expected to be sealed in the first quarter of 2020, pending regulatory approval in the United Kingdom according to the companies. “This acquisition brings deep technical expertise with unique […]
-
Decommissioning
Calif. Senators Urge Federal Action on Used Nuclear Fuel Removal
A measure introduced in the California State Senate calls on the U.S. Congress and President Donald Trump to approve federal legislation that would prioritize removal of used fuel from power plants in the state. Senate Joint Resolution 11 was introduced on Aug. 12 by state Sens. Patricia Bates (R) and Bill Monning (D). It was […]
-
High-Level & Tank Waste
National Academies Urges More Study on Hanford Low-Activity Waste Treatment Options
While there could be cheaper alternatives to vitrifying all low-activity radioactive waste at the Hanford Site in Washington state, the Energy Department should do more vetting before committing to one or more of those options, according to a new assessment from a National Academies of Sciences, Engineering, and Medicine panel. The fiscal 2017 National Defense […]
-
Vitrification & Grout
Bechtel, DOE Take Another Step Toward Completing Hanford Vit Plant
The U.S. Energy Department and contractor Bechtel National reached a key milestone this week toward operation of the $17 billion Waste Treatment and Immobilization Plant at the Hanford Site in Washington state. The company and DOE’s Office of River Protection held a ribbon-cutting ceremony Monday to mark the start of testing on equipment within an […]
-
Nuclear Weapons & Stockpile
Former NNSA No. 2 to Lead Government Affairs for Nevada Site Contractor
Neile Miller, former principal deputy administrator of the National Nuclear Security Administration (NNSA), has joined Nevada National Security Site operating contractor Mission Support and Test Services as head of government affairs, the company announced Monday. Miller was No. 2 at the semiautonomous Department of Energy nuclear weapons agency from August 2010 through June 2013, according […]
-
Transuranic Waste
Energy Department Starts Market Research on Technical Support for WIPP Office
The Department of Energy’s Office of Environmental Management is doing early planning for a new technical assistance contract for the office in southeastern New Mexico that oversees the Waste Isolation Pilot Plant (WIPP). On Monday, the federal agency issued a request for information (RFI)/sources sought notice for interested businesses with the necessary expertise to serve […]
-
- Hanford Central Plateau, Tank Contractors Expected to Get Stopgap Extensions
- Appeals Court Tosses Nevada’s Request to Block Already-Completed Plutonium Shipment
- NRC Readies to Approve Pilgrim Plant Sale
- WIPP Contractor Gets New Leadership
- SRS Employee Restricted From Radiological Work After Unexplained Dose
- Radiation Contamination Incident Batters International Isotopes’ Earnings
- Contract Appeals Board Again Orders DOE to Pay Idaho Contractor Dispute Fees
- DOE Wants Capability Statements for Nationwide Decommissioning Procurement
- NRC Schedules Meetings on Decommissioning Advisory Boards
-
Cleanup & Remediation
Radiation Contamination Incident Batters International Isotopes’ Earnings
International Isotopes on Wednesday reported a net loss of nearly $1.2 million for the second quarter of 2019, primarily due to expenses for ongoing remediation of a May radioactive contamination incident in Seattle. The net loss was close to four times the $332,279 loss reported in the same period of 2018, the Idaho Falls, Idaho, […]
-
Plutonium Pit Production
Appeals Court Tosses Nevada’s Request to Block Already-Completed Plutonium Shipment
A federal appeals court on Tuesday declined to overturn a lower court’s refusal to stop the National Nuclear Security Administration (NNSA) from carrying out an already-completed shipment of plutonium to Nevada. After deciding the appeal on briefs, without an oral argument from either Nevada or attorneys representing the NNSA, the U.S. Ninth Circuit Court of Appeals in […]
-
Decommissioning
NRC Readies to Approve Pilgrim Plant Sale
Staff at the U.S. Nuclear Regulatory commission said in a notice Tuesday it plans to approve the license transfer for the retired Pilgrim Nuclear Power Station in Massachusetts. The license transfer will enable owner Entergy to sell the single-reactor facility on Cape Cod to Holtec International for decommissioning. Staff expects to formally approve the transfer […]
-
Nuclear Weapons & Stockpile
SRS Employee Restricted From Radiological Work After Unexplained Dose
A worker at the Savannah River National Laboratory was restricted from radiological work for the rest of 2019 after receiving a dose of radiation somewhere off site that put him well above a key exposure threshold at the Aiken, S.C. site, a spokesperson for site contractor Savannah River Nuclear Solutions said Wednesday. The employee took […]
-
Contracts & Procurement
Contract Appeals Board Again Orders DOE to Pay Idaho Contractor Dispute Fees
The Civilian Board of Contract Appeals (CBCA) is again telling the U.S. Energy Department to pay a former cleanup contractor at the Idaho National Laboratory more than $33 million in fees. In a ruling issued Aug. 8, a three-judge panel for the CBCA said DOE’s reasoning for failing to pay CH2M-WG Idaho (WGI) the full […]
-
Decommissioning
NRC Schedules Meetings on Decommissioning Advisory Boards
The U.S. Nuclear Regulatory Commission has scheduled a series of public meetings to take public input on best practices for community advisory boards for nuclear power plants undergoing decommissioning. The meetings will contribute to the agency’s preparation of a report to Congress on best practices for forming and operating such local boards, as required by […]
-
Decommissioning
DOE Wants Capability Statements for Nationwide Decommissioning Procurement
The U.S. Energy Department’s Environmental Management Consolidated Business Center last week issued a sources sought notice/request for information for potential contractors for nationwide deactivation, decommissioning, and removal (DD&R) operations. Information provided by interested companies would support planning for “potential upcoming procurement(s)” for DD&R, waste management, and program support for DOE’s Offices of Environmental Management and […]
-
Contracts & Procurement
Hanford Central Plateau, Tank Contractors Expected to Get Stopgap Extensions
The U.S. Energy Department intends to extend the current contracts for both radioactive-waste tank operations and Central Plateau cleanup at the Hanford Site in Washington state for up to one year while it readies new awards. The current contract extensions for AECOM-led Washington River Protection Solutions (WRPS) and Jacobs subsidiary CH2M HILL Plateau Remediation are […]
-
Transuranic Waste
WIPP Contractor Gets New Leadership
The contractor that manages the Department of Energy’s Waste Isolation Pilot Plant (WIPP) in New Mexico will have new leadership starting next month. Sean Dunagan will succeed Bruce Covert as president and project manager for AECOM-led Nuclear Waste Partnership (NWP), according to an announcement Tuesday. He will begin with a two-week transition alongside Covert starting […]
-
Vitrification & Grout
DNFSB Closes Hanford Waste Treatment Plant Safety Recommendation
The U.S. Defense Nuclear Facilities Safety Board (DNFSB) has officially closed an 8-year-old recommendation that identified significant failings in the safety culture for the Waste Treatment Plant (WTP) being built at the Department of Energy’s Hanford Site in Washington state. “The Board has concluded that the Department of Energy has adequately addressed the underlying causes […]
-
Budget & Policy
Clarification
The story “Power Outage at Nevada Site Knocks JASPER Support Offline for Two Weeks” (Weapons Complex Morning Briefing, July 30, 2019) should have said that the Joint Actinide Shock Physics Experimental Research (JASPER) facility at the Nevada National Security Site simulates some of the effects of a nuclear detonation by propelling a non-nuclear target down […]
-
Uranium Enrichment & Fuel Cycle
Centrus to Finalize Contract for New Enrichment Cascade ‘This Year,’ CEO Says
The Department of Energy expects to release this year some $35 million in funding for Centrus Energy Corp. to begin building a new uranium enrichment cascade required to produce 600 kilograms of high-assay low-enriched uranium fuel by June 1, 2020, according to a letter contract filed Monday with the U.S. Securities and Exchange Commission. The […]
-
- Energy Dept. Investigating Portsmouth Contractor’s Radiation Protection Program
- Centrus to Finalize Contract for New Enrichment Cascade ‘This Year,’ CEO Says
- Cray Gets $600M NNSA Contract to Build ‘El Capitan’ Exascale Computer
- Insufficient Information Contributed to Waste-Processing Explosion, US Ecology Says
- DNFSB Closes Hanford Waste Treatment Plant Safety Recommendation
- Virginia Firm Takes $95M FUSRAP Contract
- Clarification
-
Innovation & Infrastructure
Cray Gets $600M NNSA Contract to Build ‘El Capitan’ Exascale Computer
The National Nuclear Security Administration (NNSA) has awarded Cray Inc. a $600-million contract to build the El Capitan exascale supercomputer, which the agency wants to start crunching numbers in 2023 at the Lawrence Livermore National Laboratory in California. Cray must deliver El Capitan in late 2022, the NNSA stated in a press release Tuesday. The machine […]
-
Uranium Enrichment & Fuel Cycle
Energy Dept. Investigating Portsmouth Contractor’s Radiation Protection Program
The U.S. Energy Department’s Office of Enterprise Assessments (EA) is investigating possible breaches of federal nuclear safety regulations by the cleanup contractor at the Portsmouth Site in Ohio. The probe involves “radiation protection program implementation deficiencies at the Portsmouth Gaseous Diffusion Plant,” according to an Aug. 8 notice of intent to investigate Fluor-BWXT Portsmouth. Investigators […]
-
Cleanup & Remediation
Virginia Firm Takes $95M FUSRAP Contract
The U.S. Army Corps of Engineers last week awarded a $95 million contract for environmental remediation in the St. Louis, Mo., area under the Formerly Utilized Sites Remedial Action Program (FUSRAP). HydroGeoLogic, headquartered in Reston, Va., overcame one other bidder for the cost-plus-fixed fee deal, according to an Aug. 8 procurement notice from the Pentagon. […]
-
Defense Low-Level Waste
Insufficient Information Contributed to Waste-Processing Explosion, US Ecology Says
US Ecology has indicated that a customer failed to provide it with necessary information about waste that caused an explosion that killed one worker and injured eight others while being processed at the company’s its Grand View, Idaho, facility. In an executive summary to the report on the company’s investigation of the Nov. 17, 2018, […]
-
Uranium Enrichment & Fuel Cycle
Pike County Meeting Planned to Discuss Portsmouth Contamination Sampling
The Scioto Valley Local School District in Ohio plans a community meeting Saturday to discuss radioactive contamination concerns at a middle school located about 2 miles from the Energy Department’s Portsmouth Site. Zahn’s Corner Middle School will be tested for radioactive byproducts released into the air by the Portsmouth Gaseous Diffusion Plant during past uranium […]