At West Valley: Huge, Contaminated Melting Pot Headed for Disposal in October
PHOENIX — Heavy equipment left over from a successful liquid-waste disposal operation at the West Valley Demonstration Project should be entombed in concrete in Texas by October, a DOE contractor said here Wednesday at the 2016 Waste Management Conference. Some 600,000 gallons of high-level liquid waste leftover from West Valley, the only U.S. site ever […]
-
Transuranic Waste
NWP Eyes Quick Ramp-Up for WIPP Shipments
The Waste Isolation Pilot Plant (WIPP) near Carlsbad, N.M., will be able to store about five shipments of transuranic waste a month after it reopens to new shipments later this year, but the prime contractor at the underground Energy Department facility said here that number could quickly double. “We hope to get it up to […]
-
Cleanup & Remediation
At Los Alamos: State to Release Draft of New Cleanup Rules in March
PHOENIX — The public could get its first look at a new proposed consent agreement governing DOE cleanup of legacy nuclear waste at the Los Alamos National Laboratory (LANL) near Los Alamos, N.M. on March 30, a state official said here at the 2016 Waste Management Conference. “We’re targeting March 30 for the document to go up for […]
-
- Moniz Stands Firm on Pu Disposal, ACP, Hanford
- Hanford ORP Tank AY-102 Pumping Starts
- Whistleblower Alleged WRPS Wasted $20M on Leaky Hanford Tank
- DOE Gets Two More Years to Plan Disposal of Hanford TRU
- DOE Axes North Dakota Borehole Project
- Design Continues Despite Concerns About Oak Ridge Landfill
- At Hanford: DOE Issues Hanford Tank Contract RFI
- At LANL: DNFSB Schedules Hearing on LANL Area G
- At Nevada: DOE Taking Applications for Nevada SSAB
- At Oak Ridge: New Y-12 Mercury Treatment Design Advances
- Wrap Up: Moniz Still Confident in December WIPP Reopening
-
Cleanup & Remediation
Design Continues Despite Concerns About Oak Ridge Landfill
While concerns have been raised about the proposed location of the Department of Energy’s new CERCLA landfill in Oak Ridge, Tenn., a DOE contractor is continuing to work on design of the waste-disposal facility. The department is evaluating a number of sites on the government’s Oak Ridge Reservation because of concerns raised by environmental regulators […]
-
Plutonium Pit Production
Moniz Stands Firm on Pu Disposal, ACP, Hanford
Energy Secretary Ernest Moniz was on the defensive this week in the first two congressional hearings of the year to dive deeply into his department’s budget request for legacy nuclear cleanup in fiscal 2017, with the White House’s proposal to change a long-established strategy for disposing of 34 metric tons of surplus, weapon-usable plutonium taking […]
-
High-Level & Tank Waste
Whistleblower Alleged WRPS Wasted $20M on Leaky Hanford Tank
A former employee of Energy Department contractor Washington River Protection Solutions (WRPS) alleged the company bilked the federal government out of $20 million by covering up a leak in the double-shelled liquid-waste Tank AY-102 at the Hanford Site near Richland, Wash., according to a recently unsealed court documents. In a whistleblower complaint filed under seal in 2013 in […]
-
High-Level & Tank Waste
Hanford ORP Tank AY-102 Pumping Starts
The Department of Energy and its tank farm contractor met their deadline to start emptying waste from double-shell Tank AY-102 with several thousand gallons of liquid removed by Thursday afternoon. “The state is pleased with the efforts of DOE and Washington River Protection Solutions to meet the terms of the settlement agreement, even starting waste […]
-
Transuranic Waste
DOE Gets Two More Years to Plan Disposal of Hanford TRU
The Energy Department has received two more years to come up with a plan for sending transuranic waste stored at the Hanford Site near Richland, Wash., to New Mexico for permanent disposal, but the waste must still be shipped out by 2030, according to a recently formalized modification to the site’s master cleanup agreement. DOE, […]
-
Cleanup & Remediation
At LANL: DNFSB Schedules Hearing on LANL Area G
Following up on remaining safety issues related to the hazardous waste repository at the Los Alamos National Laboratory’s Area G, the Defense Nuclear Facilities Safety Board has announced plans to hold a public hearing in Santa Fe on March 22. In a prepared statement DNFSB Chairman Joyce Connery said, “With the upcoming wildfire season, the […]
-
Cleanup & Remediation
At Nevada: DOE Taking Applications for Nevada SSAB
The Energy Department said Tuesday it is taking applications for membership on the Nevada Site Specific Advisory Board, which provides citizen feedback about the agency’s ongoing nuclear operations and cleanup activities at the Nevada National Security Site. “Ideal candidates are private citizens living in communities near the [the site] who are willing to volunteer their […]
-
- DOE Firm on WIPP Reopening Date, Despite Safety Pause
- Radioactive Contamination Spread Reported at Hanford
- Worker Plunges Into Septic Tank at Hanford
- Highly Contaminated Glove Boxes Removed from Hanford PFP
- Despite Drain From Lost NNSA Contracts, BWXT Earnings Strong in 2015
- Graham Slams Proposal to Close MOX Plant
- Alexander to Introduce Waste Interim Storage Legislation
- At Hanford: Remaining Hanford Costs Tagged at $107.7B
- At Savannah River: HB Line Facility to Exit Deliberate Ops in March
- At Idaho: DOE to Test New Groundwater Remedies by 2019
- Wrap Up: Moab Contractor Earns High Marks
- Corrections and Clarifications
-
Interim Storage & Waste Disposal
Alexander to Introduce Waste Interim Storage Legislation
U.S. Sen. Lamar Alexander (R-Tenn.) said Wednesday that he will champion a change in law that would allow the Department of Energy to contract private companies in storing nuclear waste. The move would clear the way for DOE’s search for consent-based interim sites that would house spent nuclear fuel and high-level radioactive waste now stored […]
-
Decommissioning
Highly Contaminated Glove Boxes Removed from Hanford PFP
The Plutonium Finishing Plant is another step closer to being torn down after decades of work to clean out the heavily contaminated facility at the Hanford Site in Washington state. This week the Department of Energy announced that both of the 12-foot-tall glove boxes in the plant’s main processing building had been cut up, removed, […]
-
Cleanup & Remediation
Corrections and Clarifications
An article in the Feb. 12 edition of Weapons Complex Monitor, “Hanford Liquid Cleanup OK in Budget, but Big Cuts for Other Areas Proposed,” should have said: The total cost of the Hanford Waste Treatment Plant, including Bechtel’s $11.4 billion prime contract to build the facility, is $12.3 billion. The White House for 2017 requested […]
-
Cleanup & Remediation
Wrap Up: Moab Contractor Earns High Marks
Moab uranium mill tailings remediation project contractor Portage Inc. earned 84 percent of its potential award fee for fiscal 2015, the Department of Energy said on Thursday. The $1.26 million fee came with a rating of “very good” for the year. The department’s Office of Environmental Management particularly lauded Portage’s work in recovering from a […]
-
Cleanup & Remediation
At Idaho: DOE to Test New Groundwater Remedies by 2019
With groundwater cleanup at the Energy Department’s Idaho Site progressing slower than expected, DOE is giving itself until September 2019 to test out some fixes, an agency official told members of an agency-chartered citizen group last week. That is according to slides Nicole Badrov, a senior DOE manager in Idaho, presented to the Idaho National […]
-
Cleanup & Remediation
Worker Plunges Into Septic Tank at Hanford
A worker at the Energy Department’s Hanford Site near Richland, Wash., on Jan. 21 plunged 4 feet into an old septic tank he was attempting to dig out of the ground to clear space for plumbing that eventually will pipe liquid waste out of leaky underground waste storage tanks. The man, a subcontractor for Hanford tank-farm […]
-
Contracts & Procurement
Despite Drain From Lost NNSA Contracts, BWXT Earnings Strong in 2015
Not yet a year removed from spinning off its power-generation business, 2015 income from continuing operations at the now-nuclear-focused BWX Technologies rose nearly 9 percent year over year in 2015, despite a profit drain associated with the loss of two big contracts in the DOE nuclear enterprise in 2014. Analysts were upbeat about the news, […]
-
Budget & Policy
Graham Slams Proposal to Close MOX Plant
South Carolina’s senior senator exploded at Energy Department officials on Tuesday, demanding to know why nobody has been fired for the White House’s apparent flip-flop on turning 34 metric tons of surplus weapon-usable plutonium into fuel for commercial nuclear plants. “This is what’s wrong with the government!” Sen. Lindsey Graham (R-S.C.) shouted at National Nuclear […]
-
Transuranic Waste
DOE Firm on WIPP Reopening Date, Despite Safety Pause
The same week non-nuclear air contamination halted recovery efforts in parts of the Waste Isolation Pilot Plant near Carlsbad, N.M., Energy Department officials in Washington insisted the underground waste storage facility will be ready to reopen by December. On Wednesday, two days after WIPP prime contractor Nuclear Waste Partnership (NWP) evacuated portions of the facility due […]
-
Cleanup & Remediation
At Hanford: Remaining Hanford Costs Tagged at $107.7B
Remaining Hanford Costs Tagged at $107.7B The remaining cleanup costs at the Hanford Site plus some limited long-term stewardship come to $107.7 billion, according to the 2016 Hanford Lifecycle Scope, Schedule and Cost Report. The estimate a year ago was $110.2 billion. The report has been a requirement of the Tri-Party Agreement for the last […]
-
Cleanup & Remediation
At Savannah River: HB Line Facility to Exit Deliberate Ops in March
HB Line, a facility that assists the Savannah River Site’s H Canyon facility in processing nuclear materials, is expected to exit a reduced work phase next month as site contractor Savannah River Nuclear Solutions (SRNS) advances toward resumption of full normal operations. SRNS, the Savannah River Site’s management and operations contractor, self-induced an operational safety […]
-
Cleanup & Remediation
Radioactive Contamination Spread Reported at Hanford
The Environmental Protection Agency has asked the Department of Energy to prepare a corrective action report by the third week of April after the spread of radioactive contamination was discovered at the Hanford Site following a November windstorm. Some contamination from the 618-10 Burial Ground was found across Route 4, a public road between the […]
-
National Laboratories
LANL Environmental Budget Falls Short of State Hopes
At $189 million, the $4 million requested increase for Los Alamos National Laboratory environmental management operations for fiscal 2017 is smaller than some in the state hoped to see. Stakeholders for the Department of Energy facility, including Ryan Flynn, New Mexico environment secretary and the nuclear weapons laboratory’s principal state regulator, were hoping for a […]
-
- Contractors Involved In WIPP Accidents Get Citations, but No Fines, From DOE
- Advisory Board Knocks New Central Hanford Cleanup Milestones
- Hanford Plutonium Finishing Plant Gets New Managers
- Industry Preps for Fight Over Proposed Uranium Cleanup ‘Tax’
- LANL Environmental Budget Falls Short of State Hopes
- Huntington Ingalls’ Earnings Down Slightly in Quarter, Up For 2015
- At Oak Ridge
- At Savannah River
- At Portsmouth
- At Hanford
- Wrap Up
- Clarification
-
Transuranic Waste
Clarification
A Feb. 12 story in the Weapons Complex Monitor should have said Energy Secretary Ernest Moniz has discussed interring 34 metric tons of weapons-usable plutonium at the Waste Isolation Pilot Plant near Carlsbad, N.M., but has not formally proposed doing so. The story also should have said Moniz told reporters WIPP might begin accepting diluted plutonium shipments […]
-
Decommissioning
Hanford Plutonium Finishing Plant Gets New Managers
New management has been assigned to the Hanford Site’s Plutonium Finishing Plant and work is being rescheduled after continuing safety problems. “Over the past few months, we’ve experienced a number of safety-related events that, while they didn’t cause any serious injury, are unacceptable,” said John Ciucci, president of CH2M Hill Plateau Remediation Co., in a […]
-
Uranium Enrichment & Fuel Cycle
Industry Preps for Fight Over Proposed Uranium Cleanup ‘Tax’
Industry is again girding for a policy fight over a White House proposal to partially fund legacy uranium cleanup in Ohio, Kentucky, and Tennessee with private contributions that professional groups are calling a new tax on nuclear power. At issue is the White House’s request that Congress reauthorize industry payments, via additional charges on domestic utilities, to the Uranium […]
-
Naval Nuclear Propulsion
Huntington Ingalls’ Earnings Down Slightly in Quarter, Up For 2015
Defense contractor Huntington Ingalls on Thursday reported a slight drop in year-over-year net earnings for its latest quarter but a significant spike in full-year income. Fourth-quarter net income dropped from $52 million in fourth-quarter 2014 to $50 million in the three-month period ending 2015. Conversely, net income rose from $338 million for all of 2014 […]