National Nuclear Security Administration (NNSA)
The NNSA is the semi-autonomous DOE agency responsible for the U.S. nuclear weapons stockpile, naval reactor propulsion, and nuclear nonproliferation programs. Reporting covers warhead life extension, plutonium pit production, site contracts, budget requests, and the agency’s laboratory and production plant complex.
-
Plutonium Pit Production
Congress should ‘move forward’ with NNSA’s plan for plutonium pits, Armed Services chair says
The National Nuclear Security Administration has not won Rep. Adam Smith’s (D-Wash.) unconditional trust, but it has convinced him to authorize the agency’s plan to produce plutonium pits in two states, the House Armed Services chair told reporters Wednesday. “Yes, I believe we are going to move forward with what the NNSA [National Nuclear Security […]
-
Uranium Enrichment & Fuel Cycle
Three weapons uranium systems at Y-12 delayed along with Uranium Processing Facility
Three uranium processing systems for nuclear weapons at the Y-12 National Security Complex in Oak Ridge, Tenn., will be delayed for six months or more, a federal nuclear safety agency reported last week. Y-12’s electrorefining and direct chip melt front-loading furnace projects each will be delayed six months, according to a recent report by the […]
-
Plutonium Pit Production
South Carolina to divvy up plutonium settlement money this week
State lawmakers in South Carolina were set this week to approve distribution of $525 million from a federal settlement the state won in 2020 after the Department of Energy failed to meet deadlines for removing plutonium from the Savannah River Site. The bicameral state legislature’s House and Senate each were set to convene at 12 […]
-
Transuranic Waste
WIPP, NNSA seeking closer cooperation on waste disposal plans
SUMMERLIN, NEV. — With the National Nuclear Security Administration hoping to see the Department of Energy’s Los Alamos National Laboratory in New Mexico producing 30 plutonium pits by 2026, the organization is working closely with the Waste Isolation Pilot Plant on plans for the increased transuranic waste levels, speakers told the RadWaste Summit Wednesday. With […]
-
Budget & Policy
Strategic forces subcommittee approves Nuclear Weapons Council changes, Pantex modernization study for NDAA
The House Armed Services strategic forces subcommittee approved its contributions to the fiscal year 2023 National Defense Authorization Act Wednesday, kicking up to the full committee a package of reforms for the Nuclear Weapons Council and an order to study modernization of the Pantex Plant, among other things. The subcommittee completed its markup without debate […]
-
Transuranic Waste
WIPP, NNSA seeking closer cooperation on waste disposal plans
SUMMERLIN, NEV. — With the National Nuclear Security Administration hoping to see the Department of Energy’s Los Alamos National Laboratory in New Mexico producing 30 plutonium pits by 2026, the organization is working closely with the Waste Isolation Pilot Plant on plans for the increased transuranic waste levels, speakers told Radwaste Summit Wednesday. With the […]
-
Budget & Policy
Nuclear Weapons Council changes among early published details of House’s fiscal ‘23 NDAA
Legislation unveiled Tuesday would put the deputy secretary of defense on the Nuclear Weapons Council once a year and attempt to put the Pentagon on the hook for some risk management in the Department of Energy’s nuclear-weapons enterprise. The proposal by the House Armed Services strategic forces subcommittee is part of the National Defense Authorization […]
-
Nuclear Weapons & Stockpile
COVID cases quadruple at NNSA sites in May, mirroring national upswing at summer’s start
Confirmed, active cases of COVID-19 among contractors and civil servants working on site at National Nuclear Security Administration facilities more than quadrupled over the month of May, according to data provided Friday by a spokesperson at agency headquarters in Washington. The semiautonomous Department of Energy nuclear-weapons agency had 547 confirmed cases, up from 132 confirmed […]
-
Uranium Enrichment & Fuel Cycle
DUF6 incumbent gets six more months to accommodate competition for follow-on work with DUF4 element
The Atkins-led Mid-America Conversion Services will get six more months tacked onto its contract to process depleted uranium hexafluoride in Ohio and Kentucky while the Department of Energy solicits bids for a follow-on contract that will include new work for active nuclear weapons programs. The incumbent, which also includes Westinghouse and Fluor, will now be […]
-
National Laboratories
Los Alamos to take delivery of new high-performance computer system in 2023
The Los Alamos National Laboratory’s new high-performance computing system, called Venado, assembled by Hewlett Packard and to be delivered in 2023, will be the first in the U.S. powered by the Grace central processing unit designed by Nvidia, the lab said. The lab announced the impending delivery of its next high-performance computer system at this […]
-
Nuclear Weapons & Stockpile
DOE, DNFSB nail down details of board oversight in the Order 140.1 era
The Department of Energy and the Defense Nuclear Facilities Safety Board this week wrapped up key details of a memorandum of understanding they inked in February pledging full cooperation on safety at federal nuclear-weapons installations. The 19-page supplement announced by the Defense Nuclear Facilities Safety Board (DNFSB) in a Wednesday press release fleshes out specifics […]
-
Stockpile Stewardship
Los Alamos to take delivery of new high-performance computer system in 2023
The Los Alamos National Laboratory’s new high-performance computing system, called Venado, assembled by Hewlett Packard and to be delivered in 2023, will be the first in the U.S. powered by the Grace central processing unit designed by Nvidia, the lab said. The lab announced the impending delivery of its next high-performance computer system last week […]
-
Non-Proliferation
NNSA helos scanning Los Angeles ahead of Summit of the Americas
The National Nuclear Security Administration’s airborne, radiation-sniffing Nuclear Emergency Support Team was to begin the first of four days of background sampling over Los Angeles on Wednesday ahead of the Ninth Summit of the Americas, the agency said. Ahead of the meeting of government, industry and community representatives from each American continent, a low-flying National […]
-
Nuclear Weapons & Stockpile
NNSA administrator talks posture review, war in Ukraine, radical change in the enterprise during annual meeting of labs professionals
In a virtual address to a gathering of nuclear weapons professionals on Thursday, the head of the National Nuclear Security Administration touted the White House’s Nuclear Posture Review for its support of civilian nuclear weapon programs, advocated for more exports of peaceful nuclear-energy technology and said that Russia’s war in Ukraine has resurrected old nonproliferation […]
-
Plutonium Pit Production
SRS-area congressman asks appropriators to keep pits whole, reject proposed H-Canyon cut
A Georgia congressman released a written request that House appropriators accept the White House’s funding request for the Savannah River Site’s proposed plutonium pit factory and reject a proposed cut for the site’s H-Canyon chemical separations plant. Rep. Rick Allen (R-Ga.) made the requests ahead of Wednesday’s scheduled Member’s Day hearing, an annual exercise in […]
-
Innovation & Infrastructure
As decades-long modernization slog ramps up, GAO looks into advanced manufacturing across NNSA enterprise
The National Nuclear Security Administration could do a better job tracking the performance of some $300 million worth of research and development activities in its Advanced Manufacturing Development program, the Government Accountability Office wrote in a report published May 20. The semiautonomous Department of Energy nuclear weapons agency “may be using inconsistent measures across individual […]
-
Non-Proliferation
DOE sites took shipments of Japanese HEU from reactors in March
Some nonproliferation news came out of President Joe Biden’s first trip to Asia this week, when Biden and Japanese Prime Minister Fumio Kishida announced the Savannah River Site and Y-12 National Security complex had taken delivery of a combined 30 kilograms of uranium from three Japanese facilities. The shipment, completed in March, was part of […]
-
National Laboratories
Cerro Pelado fire 92% contained; Sandia wildfire forced evacuation of DOE National Training Center
The big Cerro Pelado wildfire outside Los Alamos that has been burning for a month has grabbed the headlines, but it was neither the only wildfire in New Mexico nor the only one to break out near a National Nuclear Security Administration nuclear-weapons site recently. At the Sandia National Laboratories last week, workers reported the […]
-
Uranium Enrichment & Fuel Cycle
Paducah contract with DUF4 for NNSA out for bids
The Department of Energy this week opened bidding for a pair of new long-term contracts to manage Cold War uranium-enrichment cleanup in Ohio and Kentucky, one of which includes some work for active nuclear weapons programs. The agency’s Office of Environmental Management, the nuclear-weapons cleanup steward, posted final solicitations online. The scheduled last day for […]
-
Contracts & Procurement
DOE releases final solicitations for next Portsmouth, Paducah contracts
The Department of Energy on Wednesday opened bidding for a pair of new long-term contracts to manage Cold War uranium-enrichment cleanup in Ohio and Kentucky, one of which includes some work for active nuclear weapons programs. The agency’s Office of Environmental Management, the nuclear-weapons cleanup steward, posted final solicitations online. The scheduled last day for […]
-
National Laboratories
Sandia wildfire forced evacuation of DOE National Training Center
The big Cerro Pelado wildfire outside Los Alamos that has been burning for a month has grabbed the headlines, but it was neither the only wildfire in New Mexico nor the only one near a National Nuclear Security Administration nuclear-weapons site last week. At the Sandia National Laboratories last week, workers reported the much smaller […]
-
Non-Proliferation
DOE sites took shipments of Japanese HEU from reactors in March
Some nonproliferation news came out of President Joe Biden’s first trip to Asia today, when Biden and the Japanese prime minister announced the Savannah River Site and Y-12 National Security complex had taken delivery of a combined 30 kilograms of uranium from three Japanese facilities. The shipment, completed in March, was part of a four-year […]
-
Innovation & Infrastructure
As decades-long modernization slog ramps up, GAO looks into advanced manufacturing across NNSA enterprise
The National Nuclear Security Administration could do a better job tracking the performance of some $300 million worth of research and development activities in its Advanced Manufacturing Development program, the Government Accountability Office wrote in a report published Friday. The semiautonomous Department of Energy nuclear weapons agency “may be using inconsistent measures across individual projects […]
-
Plutonium Pit Production
Plutonium pit master sked coming this year; first W80-4 cruise missile warhead likely late, NNSA admin testifies
This year, the National Nuclear Security Administration will finish an integrated master schedule for building a new plutonium pit manufacturing complex and this summer, and this summer, it will quantify delays to the W80-4 nuclear cruise missile warhead, the head of the agency told Senators Thursday. “We are in the process of integrating those schedules […]
-
Nuclear Weapons & Stockpile
Personnel change in upper echelons of NNSA Production Office
Carlos Alvardo will temporarily step in as the No. 2 fed at the National Nuclear Security Administration’s Pantex Plant in Amarillo, Texas, with Gabriel Pugh, the plant’s most recent deputy manager, leaving for the Department of Energy’s National Training Center, according to an internal email. Sunday was Alvardo’s first day as acting deputy manager at […]
-
National Laboratories
Cerro Pelado wildfire increasingly contained; Los Alamos lab employees can return to work
The Cerro Pelado wildfire that started nearly a month ago in northern New Mexico was more than 70% contained, making it safe for employees who had been telecommuting to come back to work, the lab said. Employees who had been working remotely were cleared to return to work inside the fence on Tuesday, according to […]
-
Plutonium Pit Production
Plan to get plutonium-pit factories back on track coming in ‘early fall,’ official tells lawmakers
It will take all summer to finalize a plan aimed at hastening construction of a key nuclear-weapon-component factory that has fallen behind schedule in South Carolina, a Pentagon official said Tuesday in a congressional hearing. It is nearly the end of the annual budget-hearing season in Washington, and federal agencies including the National Nuclear Security […]
-
Contracts & Procurement
NNSA kills controversial award to manage main weapons production sites; plans multiyear extension for incumbent
In a blow to Fluor and Amentum, the National Nuclear Security Administration this week canceled a potentially 10-year, $28-billion contract for a joint venture of the two companies to manage the agency’s main nuclear-weapon production sites. At the same time, the semiautonomous Department of Energy nuclear weapons agency announced it would extend the Bechtel-led incumbent […]
-
Nuclear Weapons & Stockpile
Uranium Processing Facility will be eight months late, NNSA says
The NNSA’s new facility for manufacturing nuclear-weapon secondary stages will not be completed until August 2026: eight months later than expected, the head of the National Nuclear Security Administration told Senators Wednesday in a hearing. Bechtel National, under contract to the Bechtel-led site prime Consolidated Nuclear Security, has been building the current incarnation of the […]
-
Nuclear Weapons & Stockpile
Uranium Processing Facility will be eight months late, NNSA says
The NNSA’s new facility for manufacturing nuclear-weapon secondary stages will not be completed until August 2026: eight months later than expected, the head of the National Nuclear Security Administration told Senators Wednesday in a hearing. Bechtel National, under contract to the Bechtel-led site prime Consolidated Nuclear Security, has been building the current incarnation of the […]