Managers for the Department of Energy’s Waste Isolation Pilot Plant (WIPP) near Carlsbad, N.M., said recently a new two-story administrative building is planned on the surface of the nation’s only disposal site for defense-related transuranic waste.
“A new two-story administration building for our mining and underground operations team will be constructed near the primary personnel hoist,” Ryan Flynn, deputy program manager for DOE’s Bechtel-led prime Salado Isolation Mining Contractors, said during a Nov. 4 public meeting. A cost-estimate and timeline have not been set, DOE said this week. The building will provide space for mining personnel as well as WIPP’s mine rescue team, Flynn said. He did not immediately provide a timetable or cost estimate for the administrative building.
On another subject, Flynn and other WIPP representatives said they expect that Panel 8 will be filled with transuranic waste in mid-2028. WIPP will then start emplacing waste in underground Panel 11 shortly thereafter, Flynn said.
An affiliate of Navarro Research & Engineering said Monday it has purchased a proprietary artificial intelligence (AI)-related platform to assist Navarro in its work with Department of Energy and National Nuclear Security Administration (NNSA) clients.
Navarro.IQ has bought the Wastepoint AI platform and other technology assets from Silica-X Holdings, according to the Nov. 16 news release. Silica-X is a company that tries to turn landfills into “mines of the future,” according to its website.
The Navarro press release said platform inventors, Philip Galland and Robert Hust, have joined Navarro, which is based in Oak Ridge, Tenn. “The acquisition of this platform represents an important investment to further expand Navarro’s ability to apply advanced artificial intelligence and knowledge technologies to some of our client’s most complex technical challenges,” said Susana Navarro, Ph.D., the president and CEO of Navarro.
Construction of a new $36 million Analytical Gas Laboratory at the Pantex Plant has reached the halfway point, with crews completing structural steel framing and insulated metal panels one year after breaking ground.
The 12,750-square-foot facility will provide advanced diagnostic equipment and testing capabilities supporting national security weapons programs and components. The project is one of four Pantex infrastructure investments using a streamlined commercial-standards approach for non-nuclear projects.
Other projects include an Environmental Sampling Facility, a second Flexible Support Facility and a new Maintenance Facility. The lab is scheduled for completion next September.
The Tennessee Valley Authority (TVA) board of directors has moved Mike Skaggs from interim CEO status to permanent CEO, following a strong fiscal 2026, the board said in a Nov. 12 press statement.
Skaggs became interim CEO and president of the federally-owned utility after Don Moul retired from the position in the summer of this year. He previously served as TVA’s chief operating officer from 2018 to 2021, before coming back to the utility.
“Mike has brought stability to TVA, and he has restored trust. Trust with local power companies, elected officials, industry leaders and our employees – he really has brought everything together,” TVA Board Chair Mitch Graves said in the release. “Mike has also helped provide process and strategic planning, always with TVA’s mission and our 3 E’s – energy, environmental stewardship and economic development – as the focus.”