Bechtel
A major engineering and construction contractor with long-standing roles across the weapons complex, including waste treatment plant construction and national laboratory management.
-
Nuclear Weapons & Stockpile
Pantex Confirms First COVID-19 Case
There is at least one confirmed case of COVID-19 among the workforce of the Pantex Plant in Amarillo, Texas, where the National Nuclear Security Administration (NNSA) assembles and disassembles nuclear weapons for maintenance and modernization. In a statement, Pantex said the employee became ill at work on March 25. The site said it did not […]
-
Cleanup & Remediation
Hanford Hiring Consultant to Help With Hot Startup of Waste Plant
The Department of Energy plans to issue a potential four-year, $1 million contract for consultant Jeffrey Trent to assist in “hot commissioning” of the Waste Treatment Plant at the Hanford Site in Washington state. The notice for the planned no-bid contract was posted earlier this month by the Hanford Office of River Protection on a […]
-
Cleanup & Remediation
Energy Dept. Hiring Consultant to Help Guide Hanford Waste Plant to Hot Startup
The Department of Energy plans to issue a potential four-year, $1 million contract for consultant Jeffrey Trent to assist in “hot commissioning” of the Waste Treatment Plant at the Hanford Site in Washington state. The notice for the planned no-bid contract was posted earlier this month by the Hanford Office of River Protection on a […]
-
Cleanup & Remediation
Hanford Tells Only ‘Essential’ Employees to Report to Work
The Energy Department’s Hanford Site in Washington state has instructed only “essential personnel” to report to work effective immediately under a “temporary planning operations status” due to COVID-19. “Unless contacted by your supervisor, all federal, contractor, subcontractor, and craft employees should not report to work,” according to a notice Sunday on a website for the […]
-
Uranium Enrichment & Fuel Cycle
Energy Dept. Uranium Complex Modernization Costs Estimated at $7.4B Through 2026
On top of the $6.5 billion required to build the Uranium Processing Facility by 2026, the National Nuclear Security Administration (NNSA) will have to spend nearly $1 billion to modernize other facilities needed to support the next-generation weapon-uranium hub, according to the Government Accountability Office (GAO). The spending figure comes from an integrated master schedule […]
-
Uranium Enrichment & Fuel Cycle
Energy Dept. Uranium Complex Modernization Costs Estimated at $7.4B Through 2026
On top of the $6.5 billion required to build the Uranium Processing Facility by 2026, the National Nuclear Security Administration (NNSA) will have to spend nearly $1 billion to modernize other facilities needed to support the next generation weapon-uranium hub, according to the Government Accountability Office (GAO). The spending figure comes from an integrated master […]
-
Transuranic Waste
Tank Waste Facilities in Idaho, South Carolina to Begin Operations This Year
PHOENIX — By the end of 2020, the Energy Department’s Office of Environmental Management expects to start operation of facilities in Idaho and South Carolina that will convert radioactive tank waste into stable forms for eventual disposal, agency officials said here Monday. The Salt Waste Processing Facility (SWPF) at the Savannah River Site in South […]
-
Cleanup & Remediation
Nuclear Waste Conference Still On Amid Coronavirus Outbreak
Nuclear cleanup contractors, including those planning to participate in a major waste conference next week, are trying to conduct business as usual while simultaneously grappling with the risk posed by the global coronavirus outbreak. On Thursday afternoon, the Nuclear Regulatory Commission announced it would cancel its annual Regulatory Information Conference, scheduled for March 10-12 just […]
-
Cleanup & Remediation
Idaho Cleanup Industry Day Draws Major Contractors
Roughly 90 representatives from some of the Energy Department’s major contractors registered for an industry day last week on the potential 15-year, $6.4 billion cleanup contract for the Idaho National Laboratory. The Energy Department issued the draft request for proposals for the award last month. It followed that up with a tour, informational program, and […]
-
Cleanup & Remediation
Idaho Cleanup Industry Day Draws Major Contractors
Roughly 90 representatives from some of the Energy Department’s major contractors registered for an industry day last week on the potential 15-year, $6.4 billion cleanup contract for the Idaho National Laboratory. The Energy Department issued the draft request for proposals for the award last month. It followed that up with a tour, informational program, and […]
-
Delivery Systems & Nuclear Triad
Bechtel, Kratos Get Spots on Northrop Grumman’s GBSD Team
Northrop Grumman tapped Bechtel National and Kratos Defense & Security Solutions to provide construction services and specialized transportation equipment for the Ground-Based Strategic Deterrent (GBSD) intercontinental ballistic missile production program the aerospace giant hopes to win this summer. Northrop Grumman is the only bidder for the estimated $25 billion engineering and manufacturing development contract to […]
-
Delivery Systems & Nuclear Triad
Bechtel, Kratos Get Spots on Northrop Grumman’s GBSD Team
Northrop Grumman tapped Bechtel National and Kratos Defense & Security Solutions to provide construction services and specialized transportation equipment for the Ground-Based Strategic Deterrent (GBSD) intercontinental ballistic missile production program the aerospace giant hopes to win this summer. Northrop Grumman is the only bidder for the estimated $25 billion engineering and manufacturing development contract to […]
-
High-Level & Tank Waste
Subcontractor Picked to Provide Containers, Spare Melter for Hanford Vitrification Plant
Utah-based Petersen Inc. has scored two subcontracts worth $37.8 million to provide stainless-steel containers and an extra melter for the Waste Treatment and Immobilization Plant (WTP) being built at the Energy Department’s Hanford Site in Washington state. Plant construction and operations prime Bechtel National announced the award Tuesday. The vitrification plant will convert much of […]
-
Cleanup & Remediation
Feds Moving Ahead With Nationwide Deactivation, Decommissioning Contract
The Energy Department declined several requests from prospective vendors to extend the Feb. 3 deadline for bidding on a potential 10-year, $3 billion Nationwide Deactivation, Decommissioning, and Removal Contract for excess facilities. The Environmental Management Consolidated Business Center last month published 152 questions and answers from potential bidders on the final request for proposals (RFP) […]
-
Cleanup & Remediation
Search for ‘Good as Glass’ Option for Much Hanford Waste Remains Elusive, Panel Says
An independent team of experts on Friday said more homework is needed before the Department of Energy can pick a reliable and cost-effective means to treat low-activity tank waste at the Hanford Site in Washington state that cannot be accommodated through vitrification. A National Academies of Sciences, Engineering, and Medicine panel issued its fourth and […]
-
High-Level & Tank Waste
Subcontractor to Provide Containers, Spare Melter for Hanford Vitrification Plant
Utah-based Petersen Inc. has scored a $37.8 million subcontract to provide stainless-steel containers and an extra melter for the Waste Treatment and Immobilization Plant (WTP) being built at the Energy Department’s Hanford Site in Washington state. Plant construction and operations prime Bechtel National announced the award Tuesday. The vitrification plant will convert much of Hanford’s […]
-
Cleanup & Remediation
Savannah River Integrated Mission Contract Could Last 15 Years, DOE Says
The Department of Energy on Friday confirmed the potential $21-billion integrated mission contract for the Savannah River Site in South Carolina will last up to 15 years. “Task orders may be placed any time during the 10 year ordering period and the execution of the actual work may extend up to 5 years” afterward, a […]
-
Cleanup & Remediation
Feds to Skip Draft RFP for Savannah River Integrated Mission Contract
The Energy Department’s Office of Environmental Manage on Thursday issued procurement-related documents for the planned “integrated mission” contract at the Savannah River Site in South Carolina. To speed the award, the nuclear cleanup office said it will not issue the standard draft version of the request for proposals for the potential 10-to-15-year, $21 billion award […]
-
Cleanup & Remediation
Lawmakers Intend to Secure More Dough for Hanford
Key Pacific Northwest lawmakers in the House and Senate pledged this week to ensure the Energy Department’s Hanford Site in Washington state gets more than the nearly $2 billion proposed in President Donald Trump’s fiscal 2021 budget. The two DOE offices that oversee cleanup and radioactive waste management at the former plutonium manufacturing complex would […]
-
Transuranic Waste
Draft RFP Released for Energy Dept. Idaho Cleanup Contract
The Energy Department on Tuesday issued a draft request for proposals for the potential 10-to-15-year, $6.4 billion contract for the Idaho Cleanup Project. The work at the Idaho National Laboratory includes operation of the Integrated Waste Treatment Unit, management and disposal of both low-level radioactive and transuranic waste, decommissioning old facilities, and spent fuel management […]
-
Cleanup & Remediation
Hanford Contract Award Protests Updated
Vendors have recently updated protests filed with the Government Accountability Office over two new contract awards, together potentially worth $14 billion, for work at the Energy Department’s Hanford Site in Washington state. Both additions were filed since Jan. 27 by corporate teams that days earlier filed protests against DOE awards for Hanford Site Mission Essential […]
-
Budget & Policy
D.C. Observers Expect Continuing Resolution for Fiscal 2021 Budget
WASHINGTON, D.C. – A hyper-partisan political climate, as reflected by the impeachment trial of President Donald Trump and the start of presidential primaries, reduces the chances of timely passage of appropriations bills to fund the government for fiscal 2021, issue watchers said last week. The Energy Department and other federal agencies are likely to be […]
-
Cleanup & Remediation
Hanford Contract Award Protests Updated
Vendors appear to have recently updated protests filed with the Government Accountability Office over two new contract awards, together potentially worth $14 billion, for work at the Energy Department’s Hanford Site in Washington state. Both additions were filed since Jan. 27 by corporate teams that days earlier filed protests against DOE awards for Hanford Site […]
-
Budget & Policy
D.C. Observers Betting on Continuing Resolution for Fiscal 2021 Budget
WASHINGTON, D.C. – A hyper-partisan political climate, as reflected by the impeachment trial of President Donald Trump and the start of presidential primaries this month, reduces the chances of timely passage of appropriations bills to fund the government for fiscal 2021, issue watchers said last week. The Energy Department and other federal agencies are likely […]
-
High-Level & Tank Waste
Study Finds Corrosion Potential in High-Level Waste Disposal
Interactions between processed high-level radioactive waste and stainless-steel containers could undermine long-term safe geologic disposal of the material, researchers at Ohio State University said in a study published this week. “The corrosion that is accelerated by the interface interaction between dissimilar materials could profoundly impact the service life of the nuclear waste packages, which, therefore, […]
-
Cleanup & Remediation
Federal-State Talks on Hanford Cleanup Stuck at Starting Line
Wide-ranging talks between the U.S. Department of Energy and the Washington state Department of Ecology on radioactive waste issues at the Hanford Site have apparently not progressed beyond the starting line. “The parties are still working through some preliminary arrangements,” Ecology spokesman Randy Bradbury said in a Jan. 23 email. The agencies confirmed in October […]
-
Cleanup & Remediation
Hanford Contract Bid Protest Lineup Now Set
The Government Accountability Office should by the end of April rule on challenges to $14 billion worth of Energy Department contract awards at the Hanford Site in Washington state. With the deadline now passed for additional challenges, the GAO has single protests on its docket for each award: the 10-year, $10-billion Hanford Central Plateau cleanup […]
-
Cleanup & Remediation
Hanford Central Plateau Contract Award Draws Protest
A Bechtel-led joint venture filed a protest Tuesday with the U.S. Government Accountability Office (GAO) over the December award of a potential 10-year, $10-billion cleanup contract at the Hanford Site in Washington state. The Project W Restoration partnership is headed by Bechtel National, and the other members are Tetra Tech and EnergySolutions, an industry source […]
-
Contracts & Procurement
Bid Protest Filed Over Hanford Central Plateau Award
A Bechtel-led joint venture filed a protest Tuesday with the U.S. Government Accountability Office (GAO) over the December award of a potential 10-year, $10-billion cleanup contract at the Hanford Site in Washington state. The Project W Restoration partnership is led by Bechtel National, and the other members of the venture are Tetra Tech and EnergySolutions, […]
-
Cleanup & Remediation
Hanford Guards Union Denied Access to Subcontract Deal With Bechtel
The U.S. National Labor Relations Board ruled Jan. 9 that a labor union representing security guards at the Waste Treatment Plant under construction at the Energy Department’s Hanford Site is not entitled to see the contract under which they are employed. The NLRB ruling finds that Waste Treatment Security Guards Union 161 holds no legal […]