Hanford Site
A DOE-EM site in Washington state and the nation’s largest nuclear cleanup project, home to millions of gallons of high-level radioactive tank waste and the Waste Treatment Plant built to vitrify it.
-
Vitrification & Grout
Bechtel wins 92% of potential high-level waste fee for 2023 vit plant work
During the past calendar year, Bechtel National won $9.5 million, or 92% of a potential $10.3 million, from the Department of Energy for work on the High-Level Waste Facility at the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state. Between Jan. 1, 2023 and Dec. 31, 2023, Bechtel earned 92% of […]
-
Contracts & Procurement
Hanford tanks would make BWXT-led groups environmental primes at Hanford, SRS
The Department of Energy’s decision to re-award a potential $45-billion contract for liquid radioactive waste management at the Hanford Site in Washington state to a BWX Technologies-led group could put the company at the helm of two major nuclear-weapons cleanups. DOE announced Friday the re-award of the Integrated Tank Disposition contract to Hanford Tank Waste […]
-
Reindustrialization & Redevelopment
Qualified developers of carbon-free power sought for DOE Hanford Site
The Department of Energy officially said Friday it is seeking competitive bids from qualified parties to help develop carbon-free electric power projects of at least 200 megawatts at the Hanford Site in Washington state. Proposals are due April 15, tax day, in response to the request for qualifications published March 1 in the system for […]
-
Contracts & Procurement
BWXT earnings rise in 2023, fourth quarter; Hanford award a ‘wild card’
Earnings rose at BWX Technologies, Lynchburg, Va., for 2023, which the maker of nuclear naval reactors and manager of nuclear weapons sites attributed Tuesday mostly to favorable adjustments on government contracts. For the year, net earnings were $246.3 million, or $2.68 per share, up about 7.7% from $238.6 million, or $2.60 a share in 2023. […]
-
Contracts & Procurement
Upon further review, DOE re-awards mega-dollar Hanford tank contract to BWXT-led group
After federal litigation, the Department of Energy has again chosen a BWX Technologies-led group as winner of the Integrated Tank Disposition contract, potentially worth $45 billion over a decade. In a Thursday press release, the DOE Office of Environmental Management announced the selection of Hanford Tank Waste Operations & Closure to oversee closure of underground […]
-
Cleanup & Remediation
Wrap Up: DUF6 contractor faces $382K fine; Hanford tank pipeline deadline extended; INL has money in reserve; more
Atkins-led Mid-America Conversion Services has 30 days to contest $382,500 in Department of Energy fines stemming from allegations that the contractor failed to ensure a crane used in Depleted Uranium Hexafluoride Conversion at the Portsmouth Site in Ohio was maintained in a safe manner. The contractor “has not acknowledged these nuclear safety deficiencies, they have […]
-
Contracts & Procurement
Proposals due this month from subs seeking Hanford electrical work
Proposals are due by the end of February from subcontractors interested in overhauling the electric power infrastructure within Area 100 of the Department of Energy’s Hanford Site in Washington state, according to an updated procurement notice. Proposals in response to the solicitation launched by Leidos-led Hanford Mission Integration Solutions, which acts as city manager for […]
-
Cleanup & Remediation
DOE offers details on partial Hanford 222-S Lab evacuation
The partial evacuation Tuesday afternoon at the 222-S Laboratory at the Department of Energy’s Hanford Site in Washington state was done as a precaution after “about a thimble full” of a legacy chemical was discovered prior to disposal, an agency spokesperson said in Wednesday emails. The evacuation of 50 to 60 people, initially reported by […]
-
Cleanup & Remediation
DOE offers details on partial Hanford 222-S Lab evacuation
The partial evacuation Tuesday afternoon at the 222-S Laboratory at the Department of Energy’s Hanford Site in Washington state was done as a precaution after “about a thimble full” of a legacy chemical was discovered prior to disposal, an agency spokesperson said in Wednesday emails. The evacuation of 50 to 60 people, initially reported by […]
-
Cleanup & Remediation
Hanford 222-S Lab reportedly evacuated
The 222-S Laboratory at the Department of Energy’s Hanford Site in Washington state was evacuated Tuesday afternoon due to concerns over chemical exposure, the Tri-City Herald reported. The evacuation occurred around 2:20 p.m. Pacific Time after an employee at the 222-S Laboratory, managed by Navarro-led Hanford Laboratory Management and Integration, handled a vial of the […]
-
Contracts & Procurement
Proposals due this month from subs seeking Hanford electrical work
Proposals are due by the end of February from subcontractors interested in overhauling the electric power infrastructure within Area 100 of the Department of Energy’s Hanford Site in Washington state, according to an updated procurement notice. Proposals in response to the solicitation launched by Leidos-led Hanford Mission Integration Solutions, which acts as city manager for […]
-
Cleanup & Remediation
Ex-NASCAR racer taking another run at Newhouse’s Hanford seat
Rep. Dan Newhouse (R-Wash.), a member of the House Appropriations Committee who champions increased cleanup funding for the Department of Energy’s Hanford Site, will have a primary challenger again this cycle for his fourth district congressional seat. So far, there are only two announced candidates for a nonpartisan primary scheduled for Aug. 6: Newhouse and […]
-
Cleanup & Remediation
Washington comment period for 2,000-gallon test-bed permit starts in March
In roughly a month the Washington state Department of Ecology will take comments on a Department of Energy proposal that could lead to offsite solidification and disposal of 2,000 gallons of less-radioactive tank waste from the Hanford Site in Washington state. The 45-day public comment period, on whether to grant a Research, Development, and Demonstration […]
-
High-Level & Tank Waste
DOE moves closer to startup of second Hanford vit plant melter
The Department of Energy said Tuesday workers have installed startup heaters to warm up the second 300-ton melter for the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state. The 18 temporary startup heaters are meant to raise the operating temperature of the second melter to 2,100 degrees Fahrenheit, DOE said in […]
-
Cleanup & Remediation
Ex-NASCAR racer taking another run at Newhouse’s Hanford seat
Rep. Dan Newhouse (R-Wash.), a member of the House Appropriations Committee who champions increased cleanup funding for the Department of Energy’s Hanford Site, will have a primary challenger again this cycle for his fourth district congressional seat. So far, there are only two announced candidates for a nonpartisan primary scheduled for Aug. 6: Newhouse and […]
-
High-Level & Tank Waste
DOE moves closer to startup of second Hanford vit plant melter
The Department of Energy said Tuesday workers have installed startup heaters to warm up the second 300-ton melter for the Waste Treatment and Immobilization Plant at the Hanford Site in Washington state. The 18 temporary startup heaters are meant to raise the operating temperature of the second melter to 2,100 degrees Fahrenheit, DOE said in […]
-
Cleanup & Remediation
Washington comment period for 2,000-gallon test-bed permit starts in March
In roughly a month the Washington state Department of Ecology will take comments on a Department of Energy proposal that could lead to offsite solidification and disposal of 2,000 gallons of less-radioactive tank waste from the Hanford Site in Washington state. The 45-day public comment period, on whether to grant a Research, Development, and Demonstration […]
-
High-Level & Tank Waste
WRPS looking for potential subs to refurbish underground tank pipeline
The Department of Energy contractor in charge of tank waste at the Hanford Site in Washington state is shopping for potential subcontractors capable of refurbishing up to 10 miles of underground pipeline for double-shelled waste-storage tanks. Amentum-led Washington River Protection Solutions published its notice seeking expressions of interest in the project on Jan. 30. Replies are due […]
-
High-Level & Tank Waste
Hanford gradually overcoming hurdles toward making glass, panel told
Department of Energy contractors at the Hanford Site in Washington state are making headway on remaining problems before crews can start turning some less-radioactive tank waste at the property into a solid glass form, the Hanford Advisory Board heard Tuesday. After making a batch of non-radioactive test glass in December, DOE wants to start vitrification of direct-feed-low-activity-waste […]
-
High-Level & Tank Waste
Hanford gradually overcoming hurdles toward making glass, panel told
Department of Energy contractors at the Hanford Site in Washington state are making headway on remaining problems before crews can start turning some less-radioactive tank waste at the property into a solid glass form, the Hanford Advisory Board heard Tuesday. After making a batch of non-radioactive test glass in December, DOE wants to start vitrification […]
-
High-Level & Tank Waste
WRPS looking for potential subs to refurbish underground tank pipeline
The Department of Energy contractor in charge of tank waste at the Hanford Site in Washington state is shopping for potential subcontractors capable of refurbishing up to 10 miles of underground pipeline for double-shelled waste-storage tanks. Amentum-led Washington River Protection Solutions published its notice seeking expressions of interest in the project on Jan. 30. Replies […]
-
Transuranic Waste
Completing WIPP airflow project, cold commissioning of Hanford vit plant targeted for 2024
The Department of Energy’s nuclear cleanup branch thinks it could complete major infrastructure projects in New Mexico and South Carolina during calendar year 2024, the agency said Tuesday. The DOE Office of Environmental Management’s top priorities for 2024 include final testing of a new underground ventilation system at the Waste Isolation Pilot Plant (WIPP) in New Mexico; […]
-
Contracts & Procurement
New Environmental Management contracts prove elusive for 2023
Although the Department of Energy’s nuclear cleanup wing awarded two multibillion-dollar environmental deals in 2023, work has not started on any of the four contracts it prioritized for the past calendar year. On paper at least, DOE’s Office of Environmental Management awarded the $45-billion Hanford Site Integrated Tanks contract in Washington state along with the […]
-
Transuranic Waste
Completing WIPP airflow project, cold commissioning of Hanford vit plant targeted for 2024
The Department of Energy’s nuclear cleanup branch thinks it could complete major infrastructure projects in New Mexico and South Carolina during calendar year 2024, the agency said Tuesday. The DOE Office of Environmental Management’s top priorities for 2024 include final testing of a new underground ventilation system at the Waste Isolation Pilot Plant (WIPP) in […]
-
Cleanup & Remediation
Case over Hanford contractor’s alleged billing abuse percolated since 2021
Before unsealing their case in January, federal prosecutors had for two years investigated whistleblower claims that the landlord contractor at the Hanford Site in Washington state fraudulently inflated its labor bills while leaving key fire systems tests undone. U.S. District Judge Stanley Bastian, appointed to the federal bench by President Barack Obama, granted a motion […]
-
Cleanup & Remediation
Justice accuses Hanford landlord of overbilling while letting fire protection tasks slide
The federal prosecutor for Eastern Washington state filed a complaint in federal district court accusing the Department of Energy’s landlord contractor for the Hanford Site of fraudulently padding labor charges for fire safety by millions of dollars. The case against Hanford Mission Integration Solutions (HMIS), a joint venture of Leidos, Centerra and Parsons, was announced […]
-
High-Level & Tank Waste
Hanford wraps up preparation of future landfill for canisters of solidified waste
A Department of Energy environmental contractor has finished preparing the Integrated Disposal Facility at the Hanford Site in Washington to store canisters of solidified low-level radioactive waste beginning in 2025, DOE said Tuesday. The Integrated Disposal Facility (IDF) was built in 2006 at the center of the Hanford complex. Now, the Amentum-led Central Plateau Cleanup […]
-
Cleanup & Remediation
State Hanford regulator to take new Washington Ecology post in February
David Bowen, the top state regulator assigned to the Department of Energy’s Hanford Site, has accepted a new job within the Washington Department of Ecology, the state agency said Tuesday. Bowen, who has been with Ecology since 2016 and led the Nuclear Waste Program since December 2020, has been appointed director of the agency’s central […]
-
Cleanup & Remediation
Federal prosecutor accuses Hanford landlord of overcharges for lax fire protection
The federal prosecutor for Eastern Washington state has filed a complaint in federal district court accusing the Department of Energy’s landlord contractor for the Hanford Site of fraudulently padding labor charges for fire safety by millions of dollars. The case against Hanford Mission Integration Solutions (HMIS), a joint venture made up of Leidos, Centerra and […]
-
High-Level & Tank Waste
Hanford wraps up preparation of future landfill for canisters of solidified waste
A Department of Energy environmental contractor has finished preparing the Integrated Disposal Facility at the Hanford Site in Washington to store canisters of solidified low-level radioactive waste beginning in 2025, DOE said Tuesday. The Integrated Disposal Facility (IDF) was built in 2006 at the center of the Hanford complex. Now, the Amentum-led Central Plateau Cleanup […]