Hanford Site
A DOE-EM site in Washington state and the nation’s largest nuclear cleanup project, home to millions of gallons of high-level radioactive tank waste and the Waste Treatment Plant built to vitrify it.
-
Cleanup & Remediation
Hanford Plutonium Finishing Plant Open-Air Demo to Resume Today
Open-air demolition of the Plutonium Finishing Plant at the Hanford Site in Washington state is scheduled to resume today after being suspended for more than 15 months. It will be the first demolition at the plant since the airborne spread of radioactive contamination was discovered in December 2017. Workers for Hanford cleanup contractor CH2M Hill […]
-
Cleanup & Remediation
Three Teams Said Vying for Hanford Tank Closure Contract
Three teams are believed to be vying for the 10-year, $13 billion Tank Closure Contract at the Energy Department’s Hanford Site in Washington state, according to an industry source. Proposals by vendor teams hoping to succeed AECOM-led Washington River Protection Solutions were due March 21. The Energy Department is scheduled to hear oral presentations by […]
-
Cleanup & Remediation
Hanford Costs, Schedule Can be Improved: DOE Cleanup Chief
The Department of Energy could take steps to reduce the cost, shorten the schedule, and increase the efficiency of environmental remediation at the Hanford Site in Washington state, according to the agency’s top nuclear cleanup official. Anne White made her fifth trip to Hanford last week on the first anniversary of her March 29, 2018, […]
-
Cleanup & Remediation
Big Savings Anticipated in ‘End State’ Cleanup Approach, DOE Says
The Energy Department Office of Environmental Management (EM) expects to speed cleanup of its nuclear sites by decades and save “$100s of millions” in life-cycle costs, according to the Donald Trump administration’s fiscal 2020 budget request. The request, issued in March, would trim the DOE nuclear remediation appropriation from $7.2 billion in fiscal 2019 to […]
-
Cleanup & Remediation
Perma-Fix Aims to Renew Permit, Keep Test Bed Initiative at Wash. Facility
Perma-Fix Environmental Services said Monday it is progressing toward renewal of its Washington state Dangerous Waste Regulations permit for its low-level and mixed-low-level radioactive waste processing facility in the city of Richland. The permit for the Perma-Fix Northwest plant, near the Department of Energy’s Hanford Site, expired in 2010 and has yet to be renewed. […]
-
Cleanup & Remediation
DOE Cites CH2M Over Hanford Radiological Contamination Incidents
The Department of Energy on Monday issued preliminary notices of violation to CH2M Hill Plateau Remediation Co. over repeated incidents of radiological contamination spread at the Hanford Site in Washington state. Radioactive particles were found outside the established radiological control boundary of the Plutonium Finishing Plant demolition site in 2017 and 2018. The Energy Department […]
-
Cleanup & Remediation
Perry Still Skeptical of Using Uranium Barter to Help Fund Cleanup
Energy Secretary Rick Perry suggested Tuesday he is ready to again suspend his agency’s past practice of bartering excess government uranium to help pay for environmental remediation at the Portsmouth Site in Ohio. “I agree with you,” Perry told Sen. John Barrasso (R-Wyo.), a vocal opponent of the practice, during a Senate Energy and Natural […]
-
Cleanup & Remediation
DOE Cites CH2M Over Hanford Radiological Contamination Incidents
The Department of Energy on Monday issued preliminary notices of violation to CH2M Hill Plateau Remediation Co. over repeated incidents of radiological contamination spread at the Hanford Site in Washington state. Radioactive particles were found outside the established radiological control boundary of the Plutonium Finishing Plant demolition site in 2017 and 2018. The Energy Department […]
-
Cleanup & Remediation
Washington State Seeks Quick End to Hanford Workers’ Comp Lawsuit
The state of Washington on March 22 asked a federal judge to rule in its favor without going to trial in the Hanford Site workers’ compensation lawsuit filed by the Department of Justice in December. The Justice Department sued the state in U.S. District Court for Eastern Washington, saying a new state law that increases […]
-
Cleanup & Remediation
Appeals Court Denies Petition for Hanford Pension Lawsuit Hearing
The full U.S. Court of Appeals for the Federal Circuit has rejected a petition to rehear a case asking that full pension benefits be reinstated for up to 500 people who worked at the Hanford Site in Washington state. It issued the denial Tuesday without comment. Retirees of Lockheed Martin Services Inc. in February petitioned […]
-
Cleanup & Remediation
Energy Dept. Explains $400M Funding Drop for Hanford
The Department of Energy plans in fiscal 2020 to cut funding for cleanup at the Hanford Site in Washington state in part because of progress made and projects completed, according to detailed budget documents released Monday. In total, funding for the two DOE offices at Hanford would drop by more than $400 million from current […]
-
Contracts & Procurement
Wrap Up: Auditor Retained to Look at Hanford Tank Proposals
The Department Energy’s Office of Environmental Management retained a firm to audit proposals for the potential 10-year, $13 billion Tank Closure Contract at the Hanford Site in Washington state. A contract valued at about $415,000 was awarded to Maryland-based CohnReznick, which has done fee-reasonableness audits for DOE in the past. The contract for the proposal […]
-
Cleanup & Remediation
Perry Vows to Clean Up Hanford Even While Tightening Belt
Energy Secretary Rick Perry on Tuesday defended his agency’s proposed $400 million-plus budget reduction at the Hanford Site in Washington state, even while the cost of cleanup is on the rise. “On one hand the department is telling us the mission is going to become exponentially more expensive,” even as it cuts the remediation budget […]
-
Cleanup & Remediation
Energy Dept. Explains $400M Funding Drop for Hanford Cleanup
The Department of Energy plans in fiscal 2020 to cut funding for cleanup at the Hanford Site in Washington sate in part because of progress made and projects completed, according to detailed budget documents released Monday. In total, funding for the two DOE offices at Hanford would drop by more than $400 million from current […]
-
Budget & Policy
Trump Administration Details Fiscal 2020 DOE Cleanup Budget Request
The Donald Trump administration on Monday rolled out its full fiscal 2020 budget request for the Energy Department’s Office of Environmental Management, which faces a roughly $700 million funding decrease from the current level. Overall, funding for the cleanup office would drop from almost $7.2 billion in fiscal 2019 to about $6.5 billion proposed for […]
-
Cleanup & Remediation
Washington State Says Workers Comp Law With Protections for Hanford Contractors is Constitutional
A federal judge should declare a new Washington state workers compensation law constitutional and block a jury trial in a lawsuit brought by the Department of Justice, the state wrote in a Friday court filing. The Justice Department has sued the state in the U.S. District Court for Eastern Washington, arguing that the law, enacted […]
-
Contracts & Procurement
Auditor Lined up for Hanford Tank Closure Contract Proposals
The Department Energy’s Office of Environmental Management retained a firm to audit proposals for the potential 10-year, $13 billion Tank Closure Contract at the Hanford Site in Washington state. A contract valued at about $415,000 was awarded to Maryland-based CohnReznick, which has done fee-reasonableness audits for DOE in the past. The contract for the proposal audit […]
-
High-Level & Tank Waste
Hanford Test Bed Initiative Suffers Another Permit Setback
The Washington state Department of Ecology has denied the Department of Energy’s application for a permit to cover Test Bed Initiative (TBI) work at the Hanford Site, but expressed support for the project. Despite the initial setback, the letter of denial issued March 15 also said there is a better and possibly quicker way for […]
-
Contracts & Procurement
Hanford Support Services Provider Gets Temporary Extension
The Department of Energy plans to extend the contract for Mission Support Alliance (MSA) to provide site-wide services at the Hanford Site in Eastern Washington by up to six months. Hanford DOE Manager Brian Vance said in a memo to site employees Tuesday that Richland Operations Office Deputy Manager Joe Franco was notifying MSA that […]
-
High-Level & Tank Waste
Wrap Up: H-Canyon Producing 100,000 Gallons of Annual Liquid Waste
The H-Canyon processing facilities at the Energy Department’s Savannah River Site (SRS) in South Carolina currently generate roughly 100,000 gallons per year of radioactive liquid waste, a figure expected to grow to about 200,000 per year in fiscal 2022. After fiscal 2022, the amount of liquid waste going from H-Canyon into the SRS liquid waste […]
-
Contracts & Procurement
Canada Probe of SNC-Lavalin Not Sure Red Light on U.S. Business
By John Stang and Wayne Barber While it faces a potential 10-year ban on contracts with the Canadian government, SNC-Lavalin’s legal woes north of the border do not appear to automatically translate to similar troubles in the United States. The Montreal-based engineering and construction multinational is the parent company to Department of Energy contractor Atkins […]
-
Contracts & Procurement
Hanford Support Services Provider Gets Contract Extension
The Department of Energy plans to extend the contract for Mission Support Alliance (MSA) to provide site-wide services at the Hanford Site in eastern Washington state by up to six months. Hanford DOE Manager Brian Vance said in a memo to site employees Tuesday that Richland Operations Office Deputy Manager Joe Franco was notifying MSA […]
-
Budget & Policy
DOE Budget Would Slash Hanford Cleanup Funding, Boost Savannah River
The Department of Energy is proposing a $417 million cut to funding for environmental remediation at the Hanford Site in Washington state, while boosting spending for liquid waste management at the Savannah River Site in South Carolina by $91 million. On March 11, the agency rolled out the broad outlines of its fiscal 2020 budget […]
-
Contracts & Procurement
Wrap Up: AVANTech Welcomes New Business Development Executive
Columbia, S.C.-based Energy Department subcontractor AVANTech recently hired Mark Ping as its senior vice president of business development for utility services. Ping’s nuclear career spans more than 35 years and includes experience in radioactive water treatment, wet waste processing, and disposal, the company said in a Feb. 19 press release. The company is a provider […]
-
Transuranic Waste
Energy Department Sorting Through Comments on High-Level Waste
The Department of Energy does not know yet what action it will take on its proposed reinterpretation of the definition of high-level radioactive waste (HLW), Secretary for Environmental Management Anne Marie White said last week. “We don’t have a real distinct schedule on that. Again, we are trying to take our time and be deliberative,” […]
-
Budget & Policy
Budget Proposal for DOE Cleanup Office Comes in Under Fiscal 2019 Request
The Donald Trump administration has proposed a $6.5 billion budget for the Energy Department’s Office of Environmental Management in fiscal 2020, slightly less than the $6.6 billion requested last year but 11 percent below the $7.2 billion eventually enacted by Congress. The office’s funding for the budget year that began Oct. 1 is its largest […]
-
Contracts & Procurement
Contractors Have Plenty of Questions on Two Hanford Procurement Notices
Prospective contractors have peppered the Energy Department with questions about two requests for proposals issued in February for the Hanford Site in Washington state. The DOE Office of Environmental Management recently posted 75 questions raised by the contractor community about the potential 10-year, $13 billion Tank Closure Contract. The cleanup office posted another 28 questions […]
-
Transuranic Waste
Hanford Studies Resuming WIPP Shipments
The Department of Energy’s Carlsbad Field Office (CBFO) is talking with officials in Washington state about long-term plans for resuming shipments of transuranic waste from the Hanford Site to the Waste Isolation Pilot Plant in New Mexico. It has been eight years since DOE sent waste from the former plutonium production complex to the underground […]
-
Cleanup & Remediation
Wash. State Pressed to Expedite Perma-Fix Permit Update
Local community leaders are urging the Washington state Department of Ecology to expedite completing an environmental impact statement (EIS) and a revised permit for Perma-Fix Northwest in Richland, Wash., near the Hanford Site. The Department of Ecology said at a public meeting Wednesday in Richland on the scope of the EIS that the permit application […]
-
Cleanup & Remediation
Wash. State Urged to Accelerate Perma-Fix Permit Update
Local community leaders are urging the Washington state Department of Ecology to expedite completing an environmental impact statement (EIS) and a revised permit for Perma-Fix Northwest in Richland, Wash., near the Hanford Site. The Department of Ecology said at a public meeting Wednesday in Richland on the scope of the EIS that the permit application […]