A DOE site in South Carolina supporting nuclear materials management, tritium production, high-level waste treatment, and planned plutonium pit production.

  • DOE rolling out document on HALEU preparation at SRS

    The Department of Energy is publishing its Supplement Analysis and Amended Record of Decision for blending down roughly 2.2 metric tons of highly enriched uranium in order to make about 3.1 metric tons of high-assay low-enriched uranium (HALEU) at the Savannah River Site in South Carolina. The document should soon be published in the Federal […]

  • DOE selects four complex sites for AI data center deployment

    The Department of Energy has picked four nuclear complex sites to be used for deployment of new artificial intelligence (AI) data centers. DOE announced the Idaho National Laboratory, Oak Ridge Site in Tennessee, Paducah Gaseous Diffusion Plant site in Kentucky and the Savannah River Site in South Carolina will host the AI data centers, according […]

  • DOE selects four nuclear complex sites for AI data center deployment

    The Department of Energy has picked four nuclear complex sites to be used for deployment of new artificial intelligence (AI) data centers. DOE announced the Idaho National Laboratory, Oak Ridge Site in Tennessee, Paducah Gaseous Diffusion Plant site in Kentucky and the Savannah River Site in South Carolina will host the AI data centers, according […]

  • SRS targets August ribbon-cutting for Advanced Manufacturing center

    The Savannah River Site in South Carolina hopes to officially open its $66 million, offsite research center next month, following a greenlight this week from the Department of Energy to begin operations. During a bimonthly meeting of the Savannah River Site (SRS) Citizens Advisory Board, Edwin DeShong, field boss for the Office of Environmental Management […]

  • DOE to roll out document on HALEU preparation at SRS

    The Department of Energy should soon publish its Supplement Analysis and Amended Record of Decision for blending down roughly 2.2 metric tons of highly enriched uranium in order to make about 3.1 metric tons of high-assay low-enriched uranium (HALEU) at the Savannah River Site in South Carolina. The document should soon be published in the […]

  • SRS targets August ribbon-cutting for Advanced Manufacturing center

    The Savannah River Site in South Carolina hopes to officially open its $66 million, offsite research center next month, following a greenlight this week from the Department of Energy to begin operations. During a bimonthly meeting of the Savannah River Site (SRS) Citizens Advisory Board, Edwin DeShong, field boss for the Office of Environmental Management […]

  • HASC releases NDAA text with nuclear energy working group, two-site pits

    The House Armed Service’s starting version of the National Defense Authorization Act (NDAA) would authorize $25.4 billion to the National Nuclear Security Administration (NNSA) and establish a New Advanced Nuclear Energy Working Group. The House Armed Services Committee (HASC) will mark up the bill at 10 a.m. Eastern time Tuesday, July 15 in Rayburn House […]

  • SRS crews could double-stack 300 waste canisters in fiscal 2025

    Crews at the Department of Energy’s Savannah River Site (SRS) are expected to double-stack 300 canisters of vitrified high level waste this fiscal year ending Sept. 30.  That figure would continue a decade-long mission that is conserving space at the South Carolina complex, according to the DOE.    To date, liquid waste contractor BWX Technologies-led Savannah […]

  • DOE makes headway on emptying SRS tanks

    The Department of Energy’s Savannah River Site in South Carolina said June 17 it has removed waste from two more radioactive waste tanks at the 310-square-mile facility near the Georgia state line. Tanks 11 and 15 are the fourth and fifth waste tanks in 12 months to meet the “preliminary cease waste removal” designation, DOE’s […]

  • DOE makes headway on emptying SRS tanks

    The Department of Energy’s Savannah River Site in South Carolina said June 17 it has removed waste from two more radioactive waste tanks at the 310-square-mile facility near the Georgia state line. Tanks 11 and 15 are the fourth and fifth waste tanks in 12 months to meet the “preliminary cease waste removal” designation, DOE’s […]

  • SRS waste contractor completes pipe upgrades during outage

    Pipe modifications in a tank farm at the Department of Energy’s Savannah River Site in South Carolina are winding down and should be complete in July, according to DOE.  The utility work at the 310-square-mile site near Aiken, S.C., comes  during a planned outage, which began on April 28 and is on track to finish […]

  • SRS waste contractor completes pipe upgrades during outage

    Pipe modifications in a tank farm at the Department of Energy’s Savannah River Site in South Carolina are winding down and should be complete in July, according to DOE.  The utility work at the 310-square-mile site near Aiken, S.C., comes  during a planned outage, which began on April 28 and is on track to finish […]

  • Advanced Manufacturing center nearly ready to go, SRS boss says

    SAVANNAH, GA. — The Department of Energy’s Savannah River National Laboratory in South Carolina should receive a certificate of completion for the offsite Advanced Manufacturing Collaborative this summer, Edwin Deshong said Wednesday. During the Radwaste Summit, Deshong gave a brief update on the status of the new research and meeting facility being built a few […]

  • Griffin tapped as new SRNS CEO, replacing departing Carr

    The Department of Energy’s prime contractor at the Savannah River Site in South Carolina has turned to a former DOE executive with more than 35 years in nuclear management to succeed its retiring CEO. Flour-led Savannah River Nuclear Solutions (SRNS) Friday June 6 announced Jeff Griffin, a senior vice president, has been picked to succeed […]

  • SRS relying on SWPF improvements to treat more liquid waste

    SAVANNAH, GA. – Despite its stops and starts, the Salt Waste Processing Facility is central to helping the Department of Energy address liquid radioactive waste at the Savannah River Site before 2024, a DOE executive said Wednesday. Since coming online about five years ago, the plant has treated more than 11 million gallons of salt […]

  • Advanced Manufacturing center nearly ready to go, SRS boss says

    SAVANNAH, GA. — The Department of Energy’s Savannah River National Laboratory in South Carolina should receive a certificate of completion for the offsite Advanced Manufacturing Collaborative this summer, Edwin Deshong said Wednesday. During the Radwaste Summit, Deshong gave a brief update on the status of the new research and meeting facility being built a few […]

  • DOE cleanup office removes ‘acting’ from Olds, Deshong field manager titles

    The acting heads of two major Department of Energy nuclear cleanup offices, one in Tennessee and the other in South Carolina, are “acting” managers no longer.  After acting as the DOE’s top remediation boss at the Savannah River Site since February, longtime DOE hand Edwin Deshong, III was promoted June 1 to head of the […]

  • DOE cleanup office removes ‘acting’ from Deshong’ SRS title

    After acting as the Department of Energy’s top remediation boss at the Savannah River Site since February, longtime DOE hand Edwin Deshong, III was promoted June 1 to head of the Environmental Management field office. DOE’s Office of Environmental Management (EM) announced Tuesday Deshong is getting the Savannah River field office job permanently. Deshong, who […]

  • Executive order halts surplus plutonium disposal; exempts South Carolina

    One of President Donald Trump’s May 23 executive orders instructs the secretary of energy to replace the surplus plutonium dilute and dispose program with one to process excess plutonium for fuel for advanced nuclear technologies. Trump’s executive order entitled “Reinvigorating the Nuclear Industrial Base,” one of four nuclear-themed executive orders released last week, said the […]

  • Changing of the guard set for Savannah River cleanup contractor

    The BWX Technologies-led joint venture doing liquid waste cleanup at the Department of Energy’s Savannah River Site in South Carolina said Wednesday its president is retiring and will be succeeded by the vice president. Savannah River Mission Completion (SRMC) President and Program Manager Dave Olson, who has held the top job since SRMC won the […]

  • Savannah River Site MOX settlement money pays for local waste station

    North Augusta, S.C., a city near the Savannah River Site, recently opened its $2 million waste transfer station, a facility paid for with money from a $600 million settlement in South Carolina’s case against the Department of Energy.  The settlement stemmed from DOE cancelling of the SRS Mixed Oxide Fuel Fabrication (MOX) Facility, one that […]

  • Savannah River winds down legacy TRU waste shipments to WIPP

    The Department of Energy’s Savannah River Site near Aiken, S.C., has only 400-odd containers of legacy transuranic (TRU) waste left for shipment to DOE’s underground disposal site in New Mexico. The Savannah River Site has loaded and shipped more than 35,000 containers of the legacy waste to the Waste Isolation Pilot Plant (WIPP) near Carlsbad, […]

  • Savannah River winds down legacy TRU waste shipments to WIPP

    The Department of Energy’s Savannah River Site near Aiken, S.C., has only 400-odd containers of legacy transuranic (TRU) waste left for shipment to DOE’s underground disposal site in New Mexico. The Savannah River Site has loaded and shipped more than 35,000 containers of the legacy waste to the Waste Isolation Pilot Plant (WIPP) near Carlsbad, […]

  • Savannah River Site MOX settlement money pays for local waste station

    North Augusta, S.C., a city near the Savannah River Site, recently opened its $2 million waste transfer station, a facility paid for with money from a $600 million settlement in South Carolina’s case against the Department of Energy.  The settlement stemmed from DOE cancelling of the SRS Mixed Oxide Fuel Fabrication (MOX) Facility, one that […]

  • Changing of the guard set for Savannah River cleanup contractor

    The BWX Technologies-led joint venture doing liquid waste cleanup at the Department of Energy’s Savannah River Site in South Carolina said Wednesday its president is retiring and will be succeeded by the vice president. Savannah River Mission Completion (SRMC) President and Program Manager Dave Olson, who has held the top job since SRMC won the […]

  • Garamendi says if Los Alamos makes 100 pits under Trump, ‘what’s Savannah River for?’

    Rep. John Garamendi (D-Calif.), a vocal nuclear critic and member of the House Armed Services Strategic Forces subcommittee, told the Exchange Monitor Los Alamos National Laboratory “ought to be able to produce” 100 pits in four years. Garamendi spoke to the Monitor last week in the halls of the Capitol about Secretary of Energy Chris […]

  • Spring outage underway for SRS liquid waste operations

    The Department of Energy’s Savannah River Site is putting liquid waste operations on hold due to a planned maintenance outage that started April 28. The annual break in operations is expected to last until July and should help increase liquid waste processing at the 310-square-mile site in South Carolina, a Savannah River Site (SRS) spokesperson […]

  • Spring outage underway for SRS liquid waste operations

    The Department of Energy’s Savannah River Site is putting liquid waste operations on hold due to a planned maintenance outage that started April 28. The annual break in operations is expected to last until July and should help increase liquid waste processing at the 310-square-mile site in South Carolina, a Savannah River Site (SRS) spokesperson […]

  • Fluor earnings fall, revenue rises during first quarter

    Earnings fell at Fluor, Irving, Texas, in the first quarter, which the engineering and construction company that serves the Department of Energy and other federal clients attributed mostly to its non-government work. Net earnings for the first quarter ended March 31 reflected a loss of $241 million, or $1.42 a share, down from earnings of […]

  • Savannah River execs outline fiscal 2025 plutonium downblend goals

    The Department of Energy’s Savannah River Site has completed nearly half of the plutonium downblends it scheduled for fiscal year 2025, the site’s interim manager reported earlier this week.  Managers at the DOE site, located near Aiken, S.C., updated South Carolina’s Nuclear Advisory Council on several production and remediation goals on tap for the fiscal […]