More Workers Join SRNS Vaccine Lawsuit; Cite Fear of Death
More COVID-19 vaccine refusers have joined a lawsuit against Savannah River Nuclear Solutions, the management and operations contractor at the Savannah River Site, and have amended their lawsuit to list fear of death from vaccines as a reason a federal judge should block the contractor’s vaccine mandate. The amended complaint filed this week fine-tuned the […]
-
Contracts & Procurement
IWTU Could Run for Several Years
SUMMERLIN, NEV. The Department of Energy expects the integrated Waste Treatment Unit to take up to seven years to treat roughly 850,000 gallons of highly radioactive sodium-bearing liquid tank waste at the Idaho National Laboratory, an agency official said Friday. Following the heatup that started Oct. 24, DOE and Fluor Idaho is about to commence […]
-
Budget & Policy
GAO Report Urges More Deliberative Approach to Nuclear Cleanup R&D
The Government Accountability Office says in a recent report the Department of Energy should better evaluate and prioritize research and development needs across the weapons complex, rather than relying so much on individual field offices and national labs. The Government Accountability Office (GAO) also said in the report released Thursday that DOE’s assistant secretary for […]
-
National Laboratories
Federal Judge Won’t Block Oak Ridge’s Vaccine Mandate
A federal district judge in Tennessee has refused to issue a preliminary injunction against the Department of Energy’s management contractor for the Oak Ridge National Laboratory in a case brought by a small group of plaintiffs refusing to comply with a vaccine mandate. While contractor UT-Battelle’s treatment of employees seeking vaccine exemptions could have been […]
-
National Laboratories
Magistrate Judge Could Take Over Suit by ORNL Resisters
Although a federal judge in Tennessee turned down a preliminary injunction for vaccine holdouts at the Department of Energy’s Oak Ridge National Laboratory, and contractor UT-Battelle has asked that the lawsuit be tossed, a federal magistrate could take over the case. On Tuesday, District Judge Charles Atchley, Jr. said he wants a federal magistrate judge […]
-
Contracts & Procurement
There Could be Single Hanford DOE Office Within 4 Years
Between now and 2025, the Department of Energy envisions having a single operations office at the Hanford Site in Washington state rather than the current two, according to a procurement-related document. Although they have separate budgets approved by Congress, the Richland Operations Office and the Office of River Protection have reported to the same boss, […]
-
Cleanup & Remediation
Holistic Talks Continue, Details Scant in Latest Report
Talks between Washington state and the Department of Energy over the future of Hanford Site cleanup continued this fall at a very granular level, according to the latest court-mandated status update about these so-called “holistic” negotiations.. “Since filing the last update on July 30, 2021, the Parties have continued to participate in mediation sessions, including […]
-
Cleanup & Remediation
USW Local at Portsmouth Approves New 2-Year Extension With Fluor-BWXT
Members of United Steelworkers Local Union 1-689, working in deactivation and demolition at the Department of Energy’s former gaseous diffusion plant complex in Ohio,this week approved a two-year contract extension Monday with Fluor-BWXT Portsmouth. The local union’s president, Herman Potter, declined to provide a vote count. Turnout was light but those who did vote went […]
-
Contracts & Procurement
Active COVID Cases at EM Under 100 for Week; 11 Positives at Hanford
There were 99 confirmed active cases of COVID-19 in the Department of Energy nuclear cleanup complex during the past week, a spokesperson with the office of Environmental Management said via Thursday email. That is 16 less than the prior week. It is also much less than late September when the Environmental Management (EM) weekly case […]
-
Transuranic Waste
More WIPP Shipments in Near Future, Permit Decision Expected in Early ’23
SUMMERLIN, NEV. — The Department of Energy should have a new 10-year authorization to continue operating the Waste Isolation Pilot Plant in New Mexico in place before 2024, the manager of the agency’s Carlsbad Field Office said Wednesday. The Waste Isolation Pilot Plant’s (WIPP) current 10-year state license expired months ago and DOE will operate […]
-
Contracts & Procurement
DOE Cleanup Office Faces ‘Critical Challenge’ as Current Generation Retires
SUMMERLIN, NEV. Like other branches of the federal government, the Department of Energy’s Office of Environmental Management has a graying workforce and a pressing need to attract new blood in the coming years, speakers said here Thursday at the Radwaste Summit. The crowd at the summit “looks fabulous, I must say, but none of us […]
-
High-Level & Tank Waste
Wrap Up: Earnings Trio; SDU-7
Though it has posted a loss for the year so far overall, Fluor, Irving, Texas, ratcheted up its earnings guidance for continuing operations in 2021 after boosting the bottom line and booking a big contract extension from DOE, the company reported this week. Also, in an earnings presentation Friday, Fluor — whose team at the […]
-
Contracts & Procurement
Might be ‘Months’ Before Pantex, Y-12 Award, Fluor Says in Earnings Call
Though it has posted a loss for the year so far overall, Fluor, Irving, Texas, ratcheted up its earnings guidance for continuing operations in 2021 after boosting the bottom line and booking a big contract extension from DOE, the company reported this week. Also, in an earnings presentation Friday, Fluor — whose team at the […]
-
Transuranic Waste
Feds Making Progress on Filling Staffing Holes at WIPP
SUMMERLIN, NEV. The Department of Energy expects to fill most of its vacancies at the Waste Isolation Pilot Plant near Carlsbad, N.M., by May 2022, representatives of the Government Accountability Office, said here Thursday. The Government Accountability Office (GAO) reported last November the DOE Carlsbad Field Office that oversees the Waste Isolation Pilot Plant (WIPP) […]
-
Contracts & Procurement
UCOR Wins Kudos From Labor Union Leader Over COVID Vax Issue
SUMMERLIN, NEV. — A labor union official representing workers at the Department of Energy’s Oak Ridge Site in Tennessee had kind words Thursday for the manner in which the site’s remediation contractor, an Amentum-Jacobs partnership, handled its COVID-19 vaccine mandate. “They confronted their unvaccinated,” by setting an early, Oct. 1 deadline, Jimmy Hart, president of […]
-
Cleanup & Remediation
SRNS Plaintiffs Given Until Nov. 17 to Revise Complaint
Dozens of Savannah River Nuclear Solutions employees suing the Department of Energy contractor over a vaccine mandate got a two-week extension, to Nov. 17, to revise their complaint and respond to the company’s motion to dismiss the suit. The plaintiffs’ response to the motion to dismiss by Savannah River Nuclear Solutions (SRNS), the Fluor-led operations […]
-
Transuranic Waste
More WIPP Shipments in Near Future, Permit Decision Expected in Early ’23
SUMMERLIN, NEV. — The Department of Energy should have a new 10-year authorization to continue operating the Waste Isolation Pilot Plant in New Mexico in place before 2024, the manager of the agency’s Carlsbad Field Office said Wednesday. The Waste Isolation Pilot Plant’s (WIPP) current 10-year state license expired months ago and DOE will operate […]
-
National Laboratories
Magistrate Judge Could Take Over Suit by ORNL Resisters
Magistrate Judge Could Take Over Suit by ORNL Resisters Although a federal judge in Tennessee turned down a preliminary injunction for vaccine holdouts at the Department of Energy’s Oak Ridge National Laboratory, and contractor UT-Battelle has asked that the lawsuit be tossed, a federal magistrate could take over the case. On Tuesday, District Judge Charles […]
-
Cleanup & Remediation
Eleven Test Positive at Hanford Site
Eleven employees at the Department of Energy’s Hanford Site in Washington state on Monday informed their bosses they have tested positive for COVID-19, according to an online advisory. The Leidos-led contractor, Hanford Mission Integration Solutions, which acts as a landlord or city manager for the former plutonium production complex, posted the development Monday evening on […]
-
Cleanup & Remediation
Rate Settlement is Latest Financial Hit for FirstEnergy
FirstEnergy Corp. reached an agreement to refund $306 million to overcharged Ohio customers over the next four years, the Public Utilities Commission of Ohio announced Monday. The commission, which regulates electricity, water, gas and other utilities, supports the agreement but must still formally approve it, according to a press release. The agreement is between FirstEnergy […]
-
Cleanup & Remediation
USW Local at Portsmouth Approves New 2-Year Extension With Fluor-BWXT
Members of United Steelworkers Local Union 1-689, working in deactivation and demolition at the Department of Energy’s former gaseous diffusion plant complex in Ohio, approved a two-year contract extension Monday with Fluor-BWXT Portsmouth. The local union’s president, Herman Potter, declined to provide a vote count. Turnout was light but those who did vote went “overwhelmingly […]
-
High-Level & Tank Waste
Feds Unfazed by Industry Advocacy; Governors Must Step Up, Yankee Exec Says
SUMMERLIN, NEV — When it comes to getting spent nuclear fuel away from former power plant sites, the industry is “doing the wrong thing” to pressure the federal government to take action, a utility executive said here Tuesday. “[W]e really need to engage our governors and host communities more effectively to urge the federal government […]
-
Cleanup & Remediation
Holistic Hanford Talks Continue, Details Scant in Latest Report
Talks between Washington state and the Department of Energy over the future of Hanford Site cleanup continued this fall at a very granular level, according to the latest court-mandated status update about these so-called “holistic” negotiations.. “Since filing the last update on July 30, 2021, the Parties have continued to participate in mediation sessions, including […]
-
Contracts & Procurement
There Could be Single Hanford DOE Office Within 4 Years
Between now and 2025, the Department of Energy envisions having a single operations office at the Hanford Site in Washington state rather than the current two, according to a procurement-related document. Although they have separate budgets approved by Congress, the Richland Operations Office and the Office of River Protection have reported to the same boss, […]
-
Cleanup & Remediation
BWXT’s 3Q Income, Revenue Trickle Down on COVID Comps for Power Biz
Fresh off a big win at the Department of Energy’s Savannah River Site last week, BWX Technologies, Lynchburg, Va., reported Friday that profits dipped a little in the third quarter as revenue took a bit of a tumble. BWXT Technologies (BWXT) posted net income of about $60 million, or 63 cents a share in the […]
-
Contracts & Procurement
GAO Report Urges More Deliberative Approach to Nuclear Cleanup R&D
The Government Accountability Office says in a recent report the Department of Energy should better evaluate and prioritize research and development needs across the weapons complex, rather than relying so much on individual field offices and national labs. The Government Accountability Office (GAO) also said in the report released Thursday that DOE’s assistant secretary for […]
-
Cleanup & Remediation
This Week
Here are some events related to defense and civilian matters that the ExchangeMonitor staff is tracking this week: November 01-02: Exchange Monitor’s Decommissioning Strategies Forum. JW Marriott Las Vegas Resort and Spa, Summerlin, Nev. IN PERSON. 03-05: Exchange Monitor’s RadWaste Summit. JW Marriott Las Vegas Resort and Spa, Summerlin, Nev. IN PERSON. 02: Leidos plans to […]
-
Contracts & Procurement
South Carolina AG Joins Legal Fight Against Vax Orders for Federal Contractors
With a major suit filed against a Department of Energy contractor in his backyard, South Carolina Attorney General Alan Wilson (R) said in a Friday press release he is joining a lawsuit brought by the Georgia governor contending the federal government lacks authority to require government contractors to be vaccinated against COVID-19. The lawsuit was […]
-
Contracts & Procurement
A Newish UCOR Wins $8.3B Oak Ridge Cleanup Contract to Replace Incumbent UCOR
The Department of Energy said in an online notice Tuesday it is awarding the new remediation contract at the Oak Ridge Site in Tennessee to an Amentum-Jacobs team called United Cleanup Oak Ridge LLC in a deal potentially worth $8.3 billion over a 10-year ordering period. United Cleanup Oak Ridge (UCOR), won the Oak Ridge […]
-
Defense & Military
Amentum Buying PAE in Deal Valued at $1.9B, Barring Last-Minute Suitors
Maryland-based Amentum, a major player in the Department of Energy’s weapons complex, announced this week it will buy another federal contractor, Virginia-based PAE in a cash transaction valued at $1.9-billion. The acquisition, which includes Amentum’s assumption of some debt, was approved by PAE’s board of directors, according to the release. As a publicly-traded company, PAE […]