Cleanup & Remediation
Coverage of DOE-EM’s multi-billion-dollar effort to address Cold War and Manhattan Project nuclear legacy waste, including tank waste treatment, site remediation, and decommissioning at Hanford, Savannah River, Oak Ridge, and other major sites.
-
Cleanup & Remediation
Senators Want DOE IG to Assess Hanford Safety Environment
The U.S. senators from Washington state are calling on the Department of Energy’s inspector general to assess the safety environment at the Hanford, including investigating its third-party administrator for workers’ compensation claims. The request comes after DOE notified the administrator, Penser North America, that it would end its contract without exercising all options for extensions. […]
-
Cleanup & Remediation
Hanford Starts Limited Use of Air Purifying Respirators in Tank Farms
Hanford Site workers next week will switch to some highly limited use of air purifying respirators in place of supplied air respirators at the Department of Energy facility’s waste storage tank farms. A joint statement Thursday informed workers that starting March 14 some entries into the AP Tank Farm would involve use of air-purified […]
-
Cleanup & Remediation
Two Executives Exiting Fluor
Fluor’s chief operating officer is retiring at the end of this month, followed by the company’s chief financial officer before the year is over, the Texas-based Department of Energy contractor announced Wednesday. COO Peter Oosterveer has been with Fluor for 28 years in a number of positions, including as head of the company’s energy and chemicals […]
-
Cleanup & Remediation
Hanford Workers’ Compensation Bill Advances in Wash. Legislature
The Washington state House of Representatives last week voted 69-29 in favor of legislation that would make Hanford Site personnel more likely to be awarded workers’ compensation, but not before making a significant change to the bill. The state Senate now has its turn to consider Substitute House Bill 1723. The bill, modeled after a […]
-
Cleanup & Remediation
Tight Window Between Building LAWPS and Starting Liquid Waste Treatment at Hanford
PHOENIX — A facility needed to treat low-activity liquid waste at the Energy Department’s Hanford Site in Washington state will not be built until 2021 — the year before contractor Bechtel National must either prove its Waste Treatment Plant (WTP) is ready to treat low-activity waste, or forfeit more than $150 million in fees, according to […]
-
Cleanup & Remediation
Senators Ping Perry About Postponed Whistleblower Protections
Three Democratic Senators on Monday asked newly minted Energy Secretary Rick Perry to instate new whistleblower protections at the agency that the Trump administration delayed as part of a government-wide regulatory freeze. The whistleblower protection was part of a rule published in the waning days of Barack Obama’s administration that clarified DOE may assess civil penalties against contractors that […]
-
Cleanup & Remediation
CH2M Nuclear Segment Profitable in a Tough 2016
Yearly operating profit at CH2M’s Environment and Nuclear business rose 7 percent year over year to $83 million in an otherwise-tough 2016, the Englewood, Colo.-based engineering company reported this week. Gross revenue in the segment, which includes the company’s Cold War cleanup work with the Energy Department’s Office of Environmental Management, was just over $2 billion: up […]
-
Cleanup & Remediation
Legacy Nuclear Cleanup in the Trump Administration: Day 50 of 100
Editor’s note: This is the third in a series of quarterly news summaries and analyses about President Donald Trump’s first 100 days in office. We’ll check in with one long, big-picture update every 25 days, with a regular flow of updates in between to keep you up on news affecting U.S. nuclear cleanup during the […]
-
Plutonium Pit Production
NRC Lauds MOX Contractor’s 2016 Construction, Safety Performance
The Nuclear Regulatory Commission lauded CB&I AREVA MOX Services, which is building the embattled Mixed Oxide Fuel Fabrication Facility in South Carolina, for its construction program and oversight in an assessment of the contractor’s construction activities and safety performance during 2016. The regulatory body said in a March 2 letter to CB&I AREVA MOX Services that the […]
-
Cleanup & Remediation
Senators Want DOE IG to Assess Hanford Safety Environment
The U.S. senators from Washington state are calling on the Department of Energy’s inspector general to assess the safety environment at the Hanford Site, including investigating its third-party administrator for workers’ compensation claims. The request comes after DOE notified the administrator, Penser North America, that it would end its contract without exercising all options for […]
-
Cleanup & Remediation
Dearholt Lands Job Interview to Head Environmental Management Office
PHOENIX — John “Rick” Dearholt, a former Jacobs Engineering hand who has worked on uranium enrichment complex demolition at the Oak Ridge Site, could soon become the Energy Department’s assistant secretary for environmental management. Reached by phone late Wednesday, Dearholt confirmed one of the biggest rumors circulating at the annual Waste Management Symposium here: that […]
-
Cleanup & Remediation
Two Executives Exiting Fluor
Fluor’s chief operating officer is retiring at the end of this month, followed by the company’s chief financial officer before the year is over, the Texas-based Department of Energy contractor announced Wednesday. COO Peter Oosterveer has been with Fluor for 28 years in a number of positions, including as head of the company’s energy and chemicals […]
-
Cleanup & Remediation
Tight Window Between Building LAWPS and Starting Liquid Waste Treatment at Hanford
PHOENIX — A facility needed to treat low-activity liquid waste at the Energy Department’s Hanford Site in Washington state will not be built until 2021 — the year before contractor Bechtel National must either prove its Waste Treatment Plant (WTP) is ready to treat low-activity waste, or forfeit more than $150 million in fees, according to […]
-
National Laboratories
WCS Negotiating TRU Waste Storage Contract Extension
PHOENIX — Waste Control Specialists and the Department of Energy are negotiating an extension of the contract for the company’s continued storage of transuranic waste from the Los Alamos National Laboratory in New Mexico, a WCS executive said Tuesday. The current contract expires on March 31. WCS’ Andrews County, Texas, waste storage facility has held more […]
-
Cleanup & Remediation
Vapor Data Chokes Hanford’s Wireless Internet
PHOENIX — With a wireless networking infrastructure one contractor called “young,” dealing with the torrents of data generated by monitoring the Hanford Site’s millions of gallons of liquid nuclear waste can be challenging. “For those of you that have just tried to put a router in your house and make it work with your multiple […]
-
Cleanup & Remediation
Savannah River Gets Extra TRU Waste Temp Storage Time Ahead of Shipping
The Savannah River Site received additional time Monday for storage of transuranic (TRU) waste containers outside of regulated areas so the facility can better prepare to resume shipments of the material to the newly reopened Waste Isolation Pilot Plant (WIPP) near Carlsbad, N.M. The Department of Energy site requested, from the South Carolina Department of Health and Environmental Control […]
-
National Laboratories
LANL Prepares to Treat Nitrate Salts Drums
PHOENIX — The Los Alamos National Laboratory expects next month to begin treating 60 drums that contain a combustible mix of nitrate salts and kitty litter like that one that blew open and released a small amount of radiation into the Waste Isolation Pilot Plant in 2014, officials said here Monday. The incident closed the […]
-
Plutonium Pit Production
NRC Lauds MOX Contractor’s 2016 Construction, Safety Performance
The Nuclear Regulatory Commission lauded CB&I AREVA MOX Services, which is building the embattled Mixed Oxide Fuel Fabrication Facility in South Carolina, for its construction program and oversight in an assessment of the contractor’s construction activities and safety performance during 2016. The regulatory body said in a March 2 letter to CB&I AREVA MOX Services that the […]
-
National Laboratories
WIPP Shipping Queue Gelling; Oak Ridge, LANL at Back of Line This Year
PHOENIX — The first three sites to ship transuranic waste to the Waste Isolation Pilot Plant (WIPP) in New Mexico will be privately operated Waste Control Specialists of Andrews, Texas; the Idaho National Laboratory, and the Savannah River National Laboratory, a senior DOE official said here Monday. DOE has not yet decided which of those […]
-
Cleanup & Remediation
DOE Cleanup Officials Hope for Infrastructure Dollars, Gird for Funding Cuts
PHOENIX — Top officials in the Energy Department’s cleanup program of its Cold War nuclear complex are angling for a piece of the infrastructure spending spree promised by President Donald Trump, but the agency’s acting Environmental Management boss has yet to receive any formal direction from the new administration about which DOE programs, if any, qualify for such […]
-
Cleanup & Remediation
Hanford Workers’ Compensation Bill Advances in Wash. Legislature
The Washington state House of Representatives last week voted 69-29 in favor of legislation that would make Hanford Site personnel more likely to be awarded workers’ compensation, but not before making a significant change to the bill. The state Senate now has its turn with Substitute House Bill 1723. The bill, modeled after a state […]
-
Cleanup & Remediation
CH2M Schedules Quarterly Investor Call
Department of Energy cleanup contractor CH2M is scheduled to discuss its fourth-quarter 2016 results with investors at 10 a.m. EST Tuesday. The company also signaled the upcoming filings of its 10-K and 8-K forms with the U.S. Securities and Exchange Commission. The company is in the midst of a restructuring that is expected to involve moving […]
-
Plutonium Pit Production
MOX Contractor Draws NNSA Criticism, Small Award Fee in Stinging FY16 Evaluation
The contractor building the Mixed Oxide Fuel Fabrication Facility received less than 9 percent of its possible award fee in its latest performance evaluation, along with a stinging rebuke from the Energy Department’s National Nuclear Security Administration. The NNSA on Feb. 21 released to Savannah River Site Watch its fiscal 2016 performance evaluation report and […]
-
Nuclear Weapons & Stockpile
DOE Contractors Wait for Policy Guidance as Trump Administration Slowly Forms
The absence of senior leadership at the Trump administration’s Cabinet agencies threatens to leave contractors without clear policy direction on matters including the Department of Energy’s nuclear weapons and cleanup complexes, executives said Tuesday. There is no imminent end in sight to this dilemma, they acknowledged. Panelists at the ExchangeMonitor’s Nuclear Deterrence Summit spoke two […]
-
Cleanup & Remediation
COMMENTARY: Portsmouth Gaseous Diffusion Plant Needs Third-Party Assessment
By Billy Spencer, Mayor, Piketon, Ohio. Scioto County Commissioner Mike Crabtree is misinformed with respect to the Village of Piketon’s long-held position on the cleanup and redevelopment plan for the Portsmouth Gaseous Diffusion Plant (PORTS) and the need for a third-party independent assessment. He should also know that the Village of Piketon is not alone […]
-
Plutonium Pit Production
One Pleads Guilty, Another Maintains Innocence in SRS MOX Fraud Case
One of two men accused of stealing more than $4 million from the federal government while working for the Savannah River Site’s MOX program could face up to five years in prison after entering into a plea agreement on Friday. Meanwhile, the other suspect has waived his right to a speedy trial and wants the […]
-
Cleanup & Remediation
DOE Wavers on PFP Demolition Deadline
Demolition of the Hanford Site’s Plutonium Finishing Plant might stretch beyond a Sept. 30 regulatory deadline, the manager of the Energy Department’s Richland Operations Office told a citizens group Wednesday. While there is a “high probability we can get it done by the end of this year,” the project might only be “near-done by the […]
-
Cleanup & Remediation
BWXT CEO Seeks to Bolster Profits at Nuclear Cleanup Segment
Revenue at the BWX Technologies business focused on the Energy Department’s Cold War cleanup program rose more than 15 percent last year as part of a generally strong 2016, the company reported Monday. The Lynchburg, Va., company derives the preponderance of its revenue from its sole-source nuclear propulsion work for the U.S. Navy and reports […]
-
Cleanup & Remediation
Uranium Sequestration Expands at Hanford
Uranium sequestration operations near the Columbia River in the Hanford Site’s 300 Area are expanding after a successful test project. Soil had earlier been excavated in places down to a depth of 15 feet in the 300 Area to remove most of the uranium that has put the groundwater at risk of contamination. The hope […]
-
Budget & Policy
SRS on Pace to Double-Stack 200 Canisters of Waste in FY17
The Savannah River Site is on pace to meet its fiscal 2017 goal to double-stack and safely store 200 canisters of treated radioactive waste, according to a site official. In October, liquid waste contractor Savannah River Remediation (SRR) began stacking canisters of vitrified waste on top of each other in Glass Waste Storage Building 1 […]