Cleanup & Remediation
Wrap Up: DOE probes SRS accident; Officials laud Idaho milestone; Hawley demands school cleanup; magistrate judge appointed in WIPP case; small biz to build K-25 tower
An investigative office within the Department of Energy is looking into a December 2022 accident at the Savannah River Site in South Carolina that resulted in an employee of the prime contractor having a finger amputated. The enforcement unit within DOE’s Office of Enterprise Assessments told Savannah River Nuclear Solutions president and CEO Stuart MacVean […]
-
Transuranic Waste
Magistrate judge appointed in discrimination case against ex-WIPP contractor
A federal magistrate judge was assigned to handle pre-trial matters in a racial discrimination lawsuit brought by an employee at the Department of Energy’s Waste Isolation Pilot Plant in New Mexico who claims he was unfairly bypassed for promotion by the former site management contractor. U.S. District Judge James Browning issued an order earlier this […]
-
Transuranic Waste
Hanford rattled by New Mexico statements on out-of-state waste
New Mexico’s public misgivings about nuclear waste is worrisome in Washington state where the Department of Energy’s Hanford Site is expected to become a big shipper to the Waste Isolation Pilot Plant in a few years and finish around 2050, a Hanford community representative said this week. “There is one item that is hitting our […]
-
Transuranic Waste
Hanford rattled by New Mexico statements on out-of-state waste
New Mexico’s public misgivings about nuclear waste is worrisome in Washington state where the Department of Energy’s Hanford Site is expected to become a big shipper to the Waste Isolation Pilot Plant in a few years and finish around 2050, a Hanford community representative said Tuesday. “There is one item that is hitting our screen […]
-
Transuranic Waste
WIPP shaft sinking reaches midway point
Workers at the Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., are roughly halfway through sinking a new underground utility shaft, site managers said Thursday. Shaft-sinking crews recently surpassed the midway point at 1,076-feet deep, the DOE and its new prime contractor, Bechtel affiliate Salado Isolation Mining Contractors, said in a March 9 […]
-
Cleanup & Remediation
Wrap Up: RFP lull, see you in September; Ex-WIPP boss joins UCOR; Talks continue on ORNL vax case; Oak Ridge panel gets new members; Oscars ad touts Oppenheimer flick
A small business solicitation for nuclear cleanup, expected out within the next month, could be the only new one to hit the street by August, the Department of Energy Environmental Management Consolidated Business Center said this week. The DOE previously said the request for proposals (RFP) Small Business Nationwide Deactivation, Decommissioning and Removal contract could […]
-
Transuranic Waste
WIPP receives 32 TRU shipments in February; pace still below DOE goals
The Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., received 32 shipments of transuranic waste during February, according to the facility’s public website. The latest monthly figure shows progress over the prior year shipment period, but suggests DOE still must increase its rate over a sustained period to reach the annual levels the […]
-
Transuranic Waste
WIPP receives 32 TRU shipments in February; pace still below DOE goals
The Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., received 32 shipments of transuranic waste during February, according to the facility’s public website. The latest monthly figure shows progress over the prior year shipment period, but suggests DOE still must increase its rate over a sustained period to reach the annual levels the […]
-
Transuranic Waste
Ex-WIPP boss takes position at UCOR
The top boss from the Department of Energy’s former prime contractor at the Waste Isolation Pilot Plant in New Mexico is now a project manager with the Amentum-led environmental remediation contractor at the Oak Ridge Site in Tennessee, according to his LinkedIn profile. Sean Dunagan was president and project manager of Amentum-led Nuclear Waste Partnership […]
-
Transuranic Waste
WIPP utility shaft halfway sunk
Workers at the Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., are roughly halfway through sinking a new underground utility shaft, site managers said Thursday. Shaft-sinking crews recently surpassed the midway point at 1,076-feet deep, the DOE and its new prime contractor, Bechtel affiliate Salado Isolation Mining Contractors, said in a March 9 […]
-
Transuranic Waste
DOE targeting return to pre-2014 WIPP shipment levels
PHOENIX – The Department of Energy’s Waste Isolation Pilot Plant in New Mexico has since 2017 received only half as many transuranic waste shipments annually as it did prior to a February 2014 underground radiation leak that halted operations for three years – but that could soon change, officials said Wednesday. Encouraged by the startup […]
-
Transuranic Waste
New WIPP ventilation system to switch on by 2026
PHOENIX — The top manager for the Bechtel affiliate now in charge of the Department of Energy’s Waste Isolation Pilot Plant in New Mexico expects a new underground ventilation system to be operating by late 2025 or early 2026. Ken Harrawood, president and program manager of Salado Isolation Mining, which took over as prime contract […]
-
Transuranic Waste
DOE targeting return to pre-2014 WIPP shipment levels
PHOENIX – The Department of Energy’s Waste Isolation Pilot Plant in New Mexico has since 2017 received only half as many transuranic waste shipments annually as it did prior to a February 2014 underground radiation leak that halted operations for three years – but that could soon change, officials said Wednesday. Encouraged by the startup […]
-
Transuranic Waste
New WIPP ventilation system could be operating in 25-26 timeframe
PHOENIX — The top manager for the Bechtel affiliate now in charge of the Department of Energy’s Waste Isolation Pilot Plant in New Mexico expects a new underground ventilation system to be operating by late 2025 or early 2026. Ken Harrawood, president and program manager of Salado Isolation Mining, which took over as prime contract […]
-
Transuranic Waste
WIPP still studying fire safety hazards of lithium-battery electric vehicles, DNFSB says
The Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., continues to study fire safety and other potential hazards that might arise from use of electric vehicles powered by big lithium-ion batteries, a federal safety panel said this month. “These hazards include fire, smoke, and combustion products, including hydrogen fluoride associated with the large […]
-
Transuranic Waste
WIPP still studying fire safety hazards of lithium-battery electric vehicles, DNFSB says
The Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., continues to study fire safety and other potential hazards that might arise from use of electric vehicles powered by big lithium-ion batteries, a federal safety panel said this month. “These hazards include fire, smoke, and combustion products, including hydrogen fluoride associated with the large […]
-
Transuranic Waste
New Mexico agrees to extend WIPP permit comment period into April
Following requests from citizen groups last month, the New Mexico Environment Department agreed to extend the comment period by 60 days for a 10-year permit renewal for the Department of Energy’s Waste Isolation Pilot Plant. Interested parties now have until 5 p.m. Mountain Time on April 19 to weigh in on the permit renewal for […]
-
Transuranic Waste
WIPP starts 2023 with a busy January, 31 shipments
The Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M., received 31 shipments of transuranic waste during January, according to figures posted recently on the agency’s public website. Most of the shipments, 23, came from the Idaho National Laboratory. Six originated from the Los Alamos National Laboratory in New Mexico and there was one […]
-
Transuranic Waste
New Mexico agrees to extend WIPP permit comment period into April
Following requests from citizen groups last month, the New Mexico Environment Department agreed to extend the comment period by 60 days for a 10-year permit renewal for the Department of Energy’s Waste Isolation Pilot Plant. Interested parties now have until 5 p.m. Mountain Time on April 19 to weigh in on the permit renewal for […]
-
Transuranic Waste
Bechtel’s Salado formally takes control of WIPP
Effective Saturday Feb. 4, Bechtel’s Salado Isolation Mining Contractors took over operation of the Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M. Salado Isolation Mining Contractors (SIMCO), which also includes New Mexico-based subcontractor Los Alamos Technical Associates, said in a Friday evening press release it was about to officially take over as prime […]
-
Transuranic Waste
Bechtel’s Salado formally takes control of WIPP
Effective Saturday Feb. 4, Bechtel’s Salado Isolation Mining Contractors took over operation of the Department of Energy’s Waste Isolation Pilot Plant near Carlsbad, N.M. Salado Isolation Mining Contractors (SIMCO), which also includes New Mexico-based subcontractor Los Alamos Technical Associates, said in a Friday evening press release it was about to officially take over as prime […]
-
Transuranic Waste
Contractor adds new lawyer as WIPP discrimination trial now expected in May
The prime contractor for the Department of Energy’s Waste Isolation Pilot Plant in New Mexico has added a new attorney to its defense team in a racial discrimination case brought by an employee who claims he was unfairly passed over for promotion. With a new trial date and new federal magistrate judge in place, the […]
-
Transuranic Waste
DOE works with Carlsbad, N.M., on electric vehicle charging stations
The Department of Energy’s Carlsbad Field Office in New Mexico is working with Carlsbad city officials to secure federal money for electric vehicle charging stations in the community, a spokesperson said in a Tuesday email. The local Carlsbad Current Argus newspaper reported last week the city and DOE’s Carlsbad field office management have agreed to […]
-
Transuranic Waste
DOE works with Carlsbad, N.M., on electric vehicle charging stations
The Department of Energy’s Carlsbad Field Office in New Mexico is working with Carlsbad city officials to secure federal money for electric vehicle charging stations in the community, a spokesperson said in a Tuesday email. The local Carlsbad Current Argus newspaper reported last week the city and DOE’s Carlsbad field office management have agreed to […]
-
Transuranic Waste
New acting DOE boss now in place at Carlsbad field office
Mark Bollinger is now the acting manager for the Department of Energy’s Carlsbad Field Office in New Mexico, which oversees the Waste Isolation Pilot Plant. The DOE Office of Environmental Management announced earlier in January that Carlsbad manager Reinhard Knerr is moving to the Portsmouth-Paducah Project Office to become the deputy manager helping to oversee […]
-
Transuranic Waste
Contractor adds new lawyer as WIPP discrimination trial now expected in May
The prime contractor for the Department of Energy’s Waste Isolation Pilot Plant in New Mexico has added a new attorney to its defense team in a racial discrimination case brought by an employee who claims he was unfairly passed over for promotion. With a new trial date and new federal magistrate judge in place, the […]
-
Transuranic Waste
Groups seek WIPP comment period extension until April
As expected, citizen groups in New Mexico have asked the state Environment Department to extend the comment period by 60 days on a 10-year permit renewal for the Department of Energy’s Waste Isolation Pilot Plant. The draft permit is more than 1,200 pages long so granting the extension until April 19 is justified, according to […]
-
Transuranic Waste
Wrap Up: WIPP outage set, SRS has new deputy, Oak Ridge manager retiring, West Valley demo continues, consultant joins Veolia board
The Department of Energy’s Waste Isolation Pilot plant near Carlsbad, N.M., will carry out a three week maintenance outage from Feb. 27 through March 19, a spokesperson for the transuranic waste disposal site said in a Thursday email. Plans include upkeep and calibration of ventilation fans as well as testing and balancing underground ventilation, the […]
-
Transuranic Waste
WIPP, Los Alamos bosses brief state legislature on TRU waste, LANL cleanup
Roughly a quarter of the way through fiscal 2023 the Department of Energy’s Waste Isolation Pilot Plant has received 107 shipments of transuranic waste, about on pace for meeting its 400-shipment target for the fiscal year ending in September, DOE and its contractor told New Mexico lawmakers Tuesday. There have been 107 shipments to the […]
-
Transuranic Waste
Groups seek WIPP comment period extension until April
As expected, citizen groups in New Mexico have asked the state Environment Department to extend the comment period by 60 days on a 10-year permit renewal for the Department of Energy’s Waste Isolation Pilot Plant. The draft permit is more than 1,200 pages long so granting the extension until April 19 is justified, according to […]