Uranium Enrichment & Fuel Cycle
News on domestic uranium enrichment capacity — including HALEU supply and policy — fuel fabrication, and the broader nuclear fuel supply chain serving both existing and advanced reactors.
-
Uranium Enrichment & Fuel Cycle
At Portsmouth
NS&D Monitor 09/11/2015 Centrus Announces Possible Upcoming American Centrifuge Layoffs Centrus Energy has notified about 380 American Centrifuge workers that layoffs could be coming in a couple months. The company, which heads the uranium enrichment project, emphasized that the notices don’t necessarily mean layoffs are sure to happen but are necessary to comply with the Worker Adjustment […]
-
Uranium Enrichment & Fuel Cycle
DOE Releases Final RFP for Portsmouth/Paducah DUF6 Conversion Plants
The Department of Energy on Tuesday announced the release of the final request for proposals for companies interested in taking over operation of depleted uranium hexafluoride (DUF6) conversion plants in Paducah, Ky., and Portsmouth, Ohio. The department will select the operating contractor from the submitted proposals. It projects the value of the cost-plus award fee […]
-
Cleanup & Remediation
DOE Issues Request for Information for Paducah Site Cleanup
The Department of Energy on Wednesday issued a request for information from companies interested in taking on the decontamination and decommissioning contract for the former Paducah Gaseous Diffusion Plant in Kentucky. "DOE is seeking feedback from contractors and other interested parties regarding options for innovative approaches for the performance of the attached [draft performance work […]
-
Uranium Enrichment & Fuel Cycle
DUF6 Conversion Facilities RFP Coming Within Two Weeks, DOE Says
Jeremy L. Dillon WC Monitor 8/28/2015 The Department of Energy said last week it plans to issue the final request for proposals (RFP) for the operation of its depleted uranium hexafluoride (DUF6) conversion facilities within the next two weeks. According to the announcement, the department anticipates issuing the RFP in the next 15 to 20 […]
-
Uranium Enrichment & Fuel Cycle
Centrus Sees Opportunities in Japanese Reactor Restarts
Brian Bradley WC Monitor 8/28/2015 Although Centrus lost $30.5 million during the first six months of 2015, including $15.1 million in the second quarter, the reopening of nuclear power plants in Japan in the wake of the 2011 Fukushima disaster provides hope for future profits. “To be sure, there’s still a long road ahead, but […]
-
Non-Proliferation
Kazakhstan and IAEA Sign LEU Fuel Bank Agreement
Alissa Tabirian NS&D Monitor 8/28/2015 The government of Kazakhstan and the International Atomic Energy Agency (IAEA) yesterday signed a formal agreement establishing a facility in the country’s northeast that will provide a reliable supply of low-enriched reactor fuel to IAEA member states. The fuel bank, set to open in two years at the Ulba Metallurgical […]
-
Uranium Enrichment & Fuel Cycle
Centrus Sees Opportunities in Japanese Reactor Restarts
Brian Bradley RW Monitor 8/28/2015 Although Centrus lost $30.5 million during the first six months of 2015, including $15.1 million in the second quarter, the reopening of nuclear power plants in Japan in the wake of the 2011 Fukushima disaster provides hope for future profits. “To be sure, there’s still a long road ahead, but […]
-
Uranium Enrichment & Fuel Cycle
Honeywell Metropolis Works Facility Back On-Line
The Honeywell Metropolis Works facility returned to full operations yesterday following the investigation into a uranium hexafluoride leak that occurred earlier this month. The investigation revealed that 12.04 pounds of UF6 were released as a result of the leak, which was caused by the over pressurization of a system that was undergoing maintenance at the […]
-
Uranium Enrichment & Fuel Cycle
Japanese Reactor Restarts Provide Hope for Struggling Centrus
Although Centrus lost $30.5 million during the first six months of 2015, including $15.1 million in the second quarter, the reopening of nuclear power plants in Japan in the wake of the 2011 Fukushima disaster is providing hope for future profits. “To be sure, there’s still a long road ahead, but if nuclear generation continues […]
-
Uranium Enrichment & Fuel Cycle
Centrus Adds Two New VPs
Centrus Energy announced yesterday the appointment of two new senior vice presidents. Kevin Alldred and Elmer Dyke will join the company as senior vice president of business strategy and senior vice president of business operations, respectively. Alldred will focus on strategic business planning and the development of new business through project development, contractual arrangements, and […]
-
Uranium Enrichment & Fuel Cycle
DOE Anticipates Issuing Final DUF6 Conversion Facilities RFP Within Two Weeks
The Department of Energy plans to issue the final Request for Proposal (RFP) for the Operation of the Depleted Uranium Hexafluoride (DUF6) Conversion Facilities within the next two weeks, DOE announced last week. According to the announcement, the Department anticipates issuing the RFP in the next 15 to 20 days as of Aug. 17. DOE […]
-
Uranium Enrichment & Fuel Cycle
Centrus Reports Net Loss in Second Quarter
Centrus Energy Corp. late last week reported a net loss of $15.1 million for the second quarter of 2015, an improvement from the $28 million net loss the company suffered during the same period in 2014. Gross profit increased by $800,000 year over year during the second quarter and by $28.6 million in the first […]
-
Uranium Enrichment & Fuel Cycle
At Portsmouth
WC Monitor 8/7/2015 DOE Extending BWXT Uranium Conversion Contract The Department of Energy on Wednesday said it would extend by nine months BWXT Conversion Services’ contract to operate depleted uranium hexafluoride conversion plants in Paducah, Ky., and Portsmouth, Ohio. “The Department of Energy (DOE) Office of Portsmouth/Portsmouth Project Office (PPPO), intends to issue a noncompetitive […]
-
Uranium Enrichment & Fuel Cycle
NRC Inspecting Honeywell Plant After Uranium Hexafluoride Leak
Lance Moore WC Monitor 8/07/2015 A senior fuel facility inspector from the Nuclear Regulatory Commission (NRC) is expected this weekend to complete a weeklong assessment of the uranium hexafluoride (UF6) leak that occurred during maintenance activities at the Honeywell Metropolis Works facility in Illinois last Saturday. The amount of UF6 that leaked from a valve […]
-
Uranium Enrichment & Fuel Cycle
NRC Investigating Uranium Hexafluoride Leak at Honeywell Plant
The Nuclear Regulatory Commission (NRC) on Monday said it has initiated a special inspection of a uranium hexafluoride leak reported Saturday at the Honeywell Metropolis Works in Illinois. “This special inspection will analyze all details of this incident,” said Victor McCree, the NRC’s Region II administrator, in a press release. “While no workers were affected […]
-
Contracts & Procurement
DOE Extends Portsmouth Support Services Contract
Jeremy L. Dillon WC Monitor 7/24/2015 The Department of Energy late last week announced a six-month extension of the infrastructure support services contract at the Portsmouth Gaseous Diffusion Plant in Ohio. Current contractor Wastren-EnergX Mission Support will continue to work the contact that had originally been set to expire on July 25. The extension is […]
-
Uranium Enrichment & Fuel Cycle
DOE Looking Into Portsmouth DUF6 Chemical Spill
Jeremy L. Dillon WC Monitor 7/24/2015 The Energy Department’s Office of Enterprise Assessments’ Office of Enforcement announced this week that it would launch an investigation into an incident in which two workers were exposed to a potassium hydroxide spill at the Portsmouth DUF6 Conversion Plant earlier this year. According to a letter to operating contractor […]
-
Contracts & Procurement
DOE Extends Portsmouth Infrastructure Support Services Contract
The Department of Energy late last week announced the extension of the infrastructure support services contract at the Portsmouth Gaseous Diffusion Plant site for a period of six months. Current contractor Wastren-EnergX Mission Support will continue to work the contact that had originally set to expire on July 25. The extension is valued at approximately […]
-
Uranium Enrichment & Fuel Cycle
Centrus Names New CFO
Brian Bradley NS&D Monitor 7/17/2015 Centrus announced on July 10 that it has promoted Stephen Greene, Treasurer and Vice President of Finance, to CFO, Senior Vice President and Treasurer, effective July 24, according to a press release. Greene has served in his current posts since 2007. “Since joining the company, I have been impressed with […]
-
Uranium Enrichment & Fuel Cycle
Centrus Names New CFO
Centrus announced on Friday that it has promoted Stephen Greene, Treasurer and Vice President of Finance, to CFO, Senior Vice President and Treasurer, effective July 24, according to a July 10 press release. Greene has served in his current posts since 2007. “Since joining the company, I have been impressed with Steve’s financial acumen and […]
-
International
Would Renewal of 123 Agreement with China Open Bilateral Supply Partnerships?
Brian Bradley NS&D Monitor 7/10/2015 Renewing the 30-year-old U.S.-China civil nuclear agreement would allow bilateral nuclear supply partnerships if China becomes a larger nuclear supplier, Tom Countryman, State Department Assistant Secretary of International Security and Nonproliferation, stated in Congressional testimony submitted on Wednesday. “These export opportunities could support tens of thousands of high-paying American jobs,” […]
-
Cleanup & Remediation
At Paducah
WC Monitor 7/10/2015 DOE Announces Paducah Cleanup Milestone The Department of Energy’s Office of Environmental Management (EM) successfully completed further demolition of at least 32 inactive uranium enrichment sites associated with the Feed Plant and buildings complex of the Paducah Gaseous Diffusion Plant (GDP). Demolition included removal of 2,600 panels of cement asbestos siding and […]
-
Cleanup & Remediation
IG: DOE Should Use External Reviews in Dispute Resolution With Paducah Regulators
Kenneth Fletcher WC Monitor 6/12/2015 The Department of Energy should implement external reviews to help resolve disputes with regulators at the Paducah site to avoid delays and cost increases for cleanup work, according to a DOE Office of Inspector General report released this week. Numerous issues have delayed completion of the C-400 groundwater cleanup project, […]
-
Uranium Enrichment & Fuel Cycle
Concern Over Fee Provision in New DUF6 Contract ‘Out of Context,’ DOE Official Says
Kenneth Fletcher WC Monitor 6/12/2015 A fee-related provision that has raised industry concern in the draft Request for Proposals for the new contract to operate the Department of Energy’s two depleted uranium hexafluoride (DUF6) conversion plants has been taken “out of context,” a DOE procurement official said this week. At issue is a clause in […]
-
Uranium Enrichment & Fuel Cycle
Fee Language in Draft RFP for New DUF6 Contract Prompts Industry Concern
DOE Releases Updated Draft RFP Sections for Industry Comment Mike Nartker WC Monitor 6/5/2015 A provision in the draft Request for Proposals for the new contract to operate the Department of Energy’s two depleted uranium hexafluoride (DUF6) conversion plants that would give DOE wide discretion in how fee can be provided is prompting concern among […]
-
Uranium Enrichment & Fuel Cycle
DOE Says It Will Issue Final RFP for New DUF6 Operating Contract in 15-45 Days
A final Request for Proposals for the new contract to manage the Department of Energy’s two depleted uranium hexafluoride (DUF6) conversion plants is expected to be released within the next 15 to 45 days, DOE said in a notice issued yesterday. DOE also said that it expects to award the new contract “in or about” […]
-
Cleanup & Remediation
IG: DOE Should Use External Reviews in Dispute Resolution With Paducah Regulators
The Department of Energy should implement external reviews to help resolve disputes with regulators at the Paducah site to avoid delays and cost increases for cleanup work, according to a DOE Office of Inspector General report released yesterday. Numerous issues have delayed completion of the C-400 groundwater cleanup project, as well as held back finalizing […]
-
Uranium Enrichment & Fuel Cycle
Rep. Fleischmann: Poneman’s Centrus Appointment Shouldn’t Impact American Centrifuge Funding
Kenneth Fletcher NS&D Monitor 6/5/2015 Former Deputy Energy Secretary Dan Poneman’s appointment to lead Centrus Energy should not impact funding support from Congress for the American Centrifuge technology, Rep. Chuck Fleischmann (R-Tenn.) said late this week. Poneman, who left DOE last fall, was appointed as CEO of Centrus Energy in March in a move that […]
-
Decommissioning
Fluor-B&W Pushes Back Completion of Portsmouth’s X-326 Deactivation to June 2017
Kenneth Fletcher WC Monitor 6/5/2015 Portsmouth D&D contractor Fluor B&W Portsmouth, LLC, is placing a renewed focus on deactivation of the X-326 facility after pushing the project’s completion date from March 2016 to June 2017. The contractor this week instituted an organizational change for X-326 work, including a dedicated project team to focus on accelerated […]
-
Uranium Enrichment & Fuel Cycle
ConverDyn Still Pushing Court to Mandate Limits on DOE Uranium Transfers
Kenneth Fletcher WC Monitor 6/5/2015 Uranium conversion services company ConverDyn is still pushing a federal court to restrict the Department of Energy’s ability to transfer excess uranium to help pay for other work after DOE recently cut the level of those transfers, according to a court filing this week. ConverDyn sued DOE last year alleging […]