Contamination Event, Blockage, Delay Idaho RH-Waste Processing

Schedule Recovery Expected
Kenneth Fletcher
WC Monitor
5/1/2015
While remote-handled transuranic waste processing at the Department of Energy’s Idaho site ran into  delays late last year, including a worker contamination incident and a system blockage,…

In This Issue









More on This Topic


A tunnel boring machine operating inside an underground rock-salt mine tunnel.

SRS resumes shipping remote-handled TRU waste to WIPP

The Department of Energy has sent its first shipment of remote-handled transuranic waste since 2009 from the Savannah River Site in South Carolina to the Waste Isolation Pilot Plant (WIPP) using a new shipping container. Remote-handled waste is more radioactive… SUBSCRIBER ACCESS Thank you for visitingWeapons Complex Monitor! You must be logged in as a […]