July 30, 2014

DOE Nears Halfway Point in Moab Uranium Mill Tailings Cleanup

By ExchangeMonitor

The Moab uranium mill tailings remediation project in Utah is almost halfway complete, the Department of Energy said yesterday. To date, approximately 7 million tons of material have been shipped from the Moab site to a nearby disposal cell. “We’re nearly 45 percent complete in relocating the 16-million-ton uranium mill tailings pile away from the Colorado River,” Federal Project Director Donald Metzler said in a release. “I’m proud to say that this has been accomplished while keeping the focus on safety.”

Comments are closed.