DOE report says Hanford cleanup costs $72 billion above 2022 estimate for lower range

In a Lifecycle report released every three years, the Department of Energy said costs to fully complete the nation’s biggest and most expensive nuclear cleanup in Washington State will be between $364 billion and $589.4 billion.
The Hanford Lifecycle Scope, Schedule,…