REVIEW EXAMINES READINESS TO RESUME WORK ON WTP HLW FACILITY
-
Contracts & Procurement
AFTER ACQUISITION, HII WILL OPERATE STOLLER AS SUBSIDIARY
Mike Nartker WC Monitor 1/10/2014 Huntington Ingalls Industries late last week wrapped up its acquisition of S.M. Stoller in a move intended to help HII expand its role in the Department of Energy marketplace. Going forward, Stoller will operate as a wholly owned subsidiary under HII’s Newport News Shipbuilding Division, which also includes Newport News […]
-
Budget & Policy
SHORT TERM CR COULD BE NEEDED AS APPROPRIATORS FINISH OMNIBUS
Todd Jacobson WC Monitor 1/10/2014 Congressional appropriators have largely wrapped up work on the Energy and Water portion of a planned omnibus spending bill for the remainder of the fiscal year, but there is growing sentiment among Capitol Hill aides that a short-term Continuing Resolution will be necessary to give lawmakers time to iron out […]
-
Contracts & Procurement
SRNS EARNS 84 PERCENT OF FY’13 AWARD FEE
Kenneth Fletcher WC Monitor 1/10/2014 Savannah River Nuclear Solutions, the managing contractor for the Savannah River Site, earned 84 percent of its total available award fee in Fiscal Year 2013, earning about $47 million out of $56 million, according to information the Department of Energy released this week. The contractor did best in DOE Office […]
-
Budget & Policy
ADMIN. RENOMINATES DOZENS, INCLUDING KEY DOE/NNSA PICKS
Committees Expected to Move Quickly on Already Cleared Noms, but Senate Floor Action Unclear Todd Jacobson WC Monitor 1/10/2014 The Obama Administration this week returned dozens of nominations to the Senate, including a handful of Department of Energy selections, and Senate committees began acting quickly to report out the nominations, with the Senate Armed Services Committee […]
-
Contracts & Procurement
SRR EARNS 95 PERCENT OF FY’13 AWARD FEE
Kenneth Fletcher WC Monitor 1/10/2014 Savannah River Remediation, LLC, the liquid waste cleanup contractor for the Savannah River Site, earned 95 percent of its total available award fee in Fiscal Year 2013, or about $29.7 million out of $31.4 million, according to information the Department of Energy released this week. “SRR has provided safe, timely, […]
-
Contracts & Procurement
DOE RELEASES RFP FOR BUILDING 55 PROCUREMENT
Kenneth Fletcher WC Monitor 1/10/2014 The Department of Energy this week released a final Request for Proposals for technical and administrative support services for Building 55 at the Denver Federal Center in Colorado. The fixed-price contract is being set aside for 8(a) small businesses, has an estimated value of $5-$10 million, and has an indefinite […]
-
Contracts & Procurement
CHBWV EARNS 60 PERCENT OF AWARD FEE IN SECOND HALF OF FY ‘13
Kenneth Fletcher WC Monitor 1/10/2014 West Valley Demonstration Project cleanup contractor CH2M Hill B&W West Valley, LLC, earned about 60 percent of the total award fee available for the evaluation period that ran from March 1, 2013, through the end of August, according to an award fee determination scorecard recently posted by the Department of […]
-
Cleanup & Remediation
ENERGYSOLUTIONS MAKES NEW SENIOR MANAGEMENT CHANGES
Mike Nartker WC Monitor 1/10/2014 EnergySolutions is starting off the new year with a set of senior management changes. As part of a new “consolidation” of the company’s management team, Mark Morant and Alan Parker have been named to oversee Projects; and Products, Projects and Technology, according to EnergySolutions spokesman Mark Walker. “Mark Morant is […]
-
Contracts & Procurement
DOE RELEASES FINAL RTP FOR NEW ETEC CONTRACT
Kenneth Fletcher WC Monitor 1/10/2014 The Department of Energy late last week released a final Request for Task Proposals for environmental monitoring and D&D work at the Energy Technology Engineering Center site in California. The procurement, which is being conducted under DOE’s nationwide small business set-aside indefinite quantity/indefinite delivery contracts, is open to contract holders […]
-
Cleanup & Remediation
DOE MAKING PROGRESS ON CLOSING OPEN DNFSB RECOMMENDATIONS
Kenneth Fletcher WC Monitor 1/10/2014 The Department of Energy appears to be making progress on closing still-pending recommendations from the Defense Nuclear Facilities Safety Board, with the DNFSB recently agreeing to close one recommendation and the Department seeking to have another one also closed. Last month, the DNFSB closed a recommendation from 2000 called “Prioritization […]
-
Cleanup & Remediation
WRAP UP: IN THE DNFSB, IN MEMORIAM
WC Monitor 1/10/2014 IN THE DNFSB Kenneth Mossman, the newest member of the Defense Nuclear Facilities Safety Board, passed away this week. In November, he was confirmed by the Senate to join the Board. Mossman previously served as a professor of health physics at Arizona State University and an Administrative Judge for the Nuclear Regulatory […]
-
Cleanup & Remediation
AT OAK RIDGE
UCOR EARNS 90 PERCENT OF AWARD FEE WC Monitor 1/10/2014 Oak Ridge cleanup contractor URS-CH2M Oak Ridge, LLC, earned about 90 percent of its available award fee in the period from April 1 through September 30, 2013, according to information recently released by the Department of Energy. UCOR received about $3.11 million out of a […]
-
Cleanup & Remediation
AT RICHLAND
TRIDEC LOOKING AT BRINGING SMR TO HANFORD WC Monitor 1/10/2014 The Tri-City Development Council has issued a request for proposals to analyze the pros and cons of a small modular nuclear reactor system at Hanford to provide power for Department of Energy projects. Proposals are due Jan. 17. State Sen. Sharon Brown ( R-Kennewick) made […]
-
International
UK CONSORTIUM LAUNCHES WASTE TREATMENT RESEARCH EFFORT
Kenneth Fletcher WC Monitor 1/10/2014 The U.K.’s Nuclear Decommissioning Authority is set to launch next month a four-year research effort on waste treatment technologies with Sellafield Limited, the National Nuclear Laboratory, numerous U.K. universities and other partners, the NDA announced this week. The program is expected to cost £8-£9 million ($13.2 million to $14.8 million) […]