IWTU Test Run to Resume Monday

By ExchangeMonitor

With the promise of a reliable nitrogen supply apparently in hand, the Department of Energy is preparing to resume a final test run to demonstrate operations of a long-awaited plant to treat sodium-bearing radioactive waste at the Idaho National Laboratory, according to a state official.

“Warm up” of the Integrated Waste Treatment Unit (IWTU) was scheduled to begin Monday, Feb. 7, Kim Custer, senior hazardous waste permit writer with the Idaho Department of Environmental Quality, said via email late Friday. The heat-up will probably take about 10 days, the state agency has said previously.

The nitrogen supplier “has committed to having a dedicated driver to deliver to the IWTU starting on the 7th,” Custer added.

A 50-day demonstration run with simulant started in December for the long-delayed plant, which is designed to convert roughly 900,000 gallons of liquid sodium-bearing waste into a granular, solid form for disposal. After a rough start related to the unit’s plumbing, the demo run was suspended Jan. 6. DOE cited an inconsistent supply of nitrogen.

Nitrogen is central to numerous facets of operations at the plant and its steam-reforming technology, the agency has said.

The Idaho Environmental Coalition, a joint venture of Jacobs and North Wind along with several small businesses, is now the third environmental contractor to assume responsibility for the IWTU.

CH2M-WG Idaho built the plant but during initial startup in June 2012, IWTU experienced a “system pressure event” leading to a shutdown, the DOE Office of Inspector General said in a May 2020 report

The DOE did not always ensure adequate quality assurance practices by CH2M-WG Idaho and its predecessor, Fluor Idaho, as various changes were made to IWTU over the years to ensure proper operation. The Idaho Environmental Coalition took over from Fluor Idaho in January.  

Citing delays associated with the COVID-19 pandemic, the state in 2021 gave DOE until September of this year to produce the first canisters of granular waste at IWTU. The prior deadline was June 2021.

Comments are closed.

Partner Content
Social Feed

NEW: Via public records request, I’ve been able to confirm reporting today that a warrant has been issued for DOE deputy asst. secretary of spent fuel and waste disposition Sam Brinton for another luggage theft, this time at Las Vegas’s Harry Reid airport. (cc: @EMPublications)

DOE spent fuel lead Brinton accused of second luggage theft.



by @BenjaminSWeiss, confirming today's reports with warrant from Las Vegas Metro PD.

Waste has been Emplaced! 🚮

We have finally begun emplacing defense-related transuranic (TRU) waste in Panel 8 of #WIPP.

Read more about the waste emplacement here: https://wipp.energy.gov/wipp_news_20221123-2.asp

Load More