RadWaste Monitor Vol. 11 No. 4
Visit Archives | Return to Issue
PDF
RadWaste & Materials Monitor
Article 6 of 7
January 25, 2019

La Crosse Nuclear Plant Deals With Tritium in Groundwater

By ExchangeMonitor

Elevated levels of radioactive tritium were found in groundwater samples taken early last year from the La Crosse Boiling Water Reactor in Wisconsin, produced during demolition of the reactor building, according to a site investigation report submitted to the state in November.

However, subsequent sampling through much of 2018 showed tritium infiltration of groundwater had stopped, the environmental consulting firm Haley & Aldrich said in a report to decommissioning contractor LaCrosseSolutions that was forwarded to the Wisconsin Department of Natural Resources.

“No remedial activities are warranted. No further action is necessary,” the consultant said.

Built in 1967, the power reactor near Genoa, Wis., operated for 19 years before the Dairyland Power Cooperative shut it down in 1987. In subsequent years it was partly decommissioned, with EnergySolutions subsidiary LaCrosseSolutions in 2016 assuming its operations license to complete the job. Decommissioning was largely complete by October 2018, with only two support structures remaining, Dairyland spokeswoman Katie Thomson said last week by email.

Groundwater samples taken in December 2017 from a monitoring well at the site showed a tritium concentration of 13,000 picocuries per liter. While that did not reach the U.S. Environmental Protection Agency’s maximum contaminant level of 20,000 picocuries per liter, it was high enough for further evaluation. Samples were taken from three wells in February 2018, with one showing tritium concentration of 24,200 picocuries per liter. Further sampling from April to September showed tritium was not entering the groundwater.

The contamination originated with exhaust from the air-filtration system for the reactor building demolition that contained a gas form of tritium and merged with water and ice melt runoff. LaCrosseSolutions fixed the source problem and has been monitoring for further contamination, Thomson said.

The Department of Natural Resources’ review of the report should wrap up in a matter of days, according to hydrogeologist Tim Zeichert. Groundwater monitoring will continue until that occurs, he said. The possible outcomes would be either continued monitoring of groundwater or closure of the case by the state.

As of last fall, decommissioning operations at La Crosse were scheduled to end by the second quarter of this year. “The remaining work includes: Completing the reactor building foundation survey, final status surveys, shipping out a small amount of remaining waste, backfilling and seeding the site, finalizing the license termination plan and transferring the license back to Dairyland,” Thomson wrote. “We do not have an updated schedule at this time. The current government shutdown has paused some proceedings.”

Dairyland referred questions regarding the shutdown to EnergySolutions, which did not respond by deadline.

The Nuclear Regulatory Commission is reviewing the companies’ application to transfer the reactor license back to Dairyland for termination. A decision is expected in the second quarter of this year. The transfer would take effect once LaCrosseSolutions finishes all decommissioning and license termination operations.

Comments are closed.

Partner Content
Social Feed

NEW: Via public records request, I’ve been able to confirm reporting today that a warrant has been issued for DOE deputy asst. secretary of spent fuel and waste disposition Sam Brinton for another luggage theft, this time at Las Vegas’s Harry Reid airport. (cc: @EMPublications)

DOE spent fuel lead Brinton accused of second luggage theft.



by @BenjaminSWeiss, confirming today's reports with warrant from Las Vegas Metro PD.

Waste has been Emplaced! 🚮

We have finally begun emplacing defense-related transuranic (TRU) waste in Panel 8 of #WIPP.

Read more about the waste emplacement here: https://wipp.energy.gov/wipp_news_20221123-2.asp

Load More