LANL Preparing Safety Basis Changes to Resume TRU Waste Operations

Alissa Tabirian
WC Monitor
9/18/2015

The Los Alamos National Laboratory (LANL) is taking steps to address materials-at-risk (MAR) concerns to resume transuranic (TRU) waste receipts at its Area G nuclear waste disposal site, according to a Defense Nuclear Facilities Safety Board (DNFSB) site representative report released last week. Department of Energy (DOE) Office of Environmental Management officials and the National Nuclear Security Administration (NNSA) Field Office worked with LANL to explore "necessary safety basis changes to allow limited [TRU] waste receipts and a return to OPERATIONS mode in Area G," the Aug. 21 report says. Waste receipts were paused "due to exceedance of composite source term (CST) [MAR] limits," it adds.

The report notes that LANL drafted an Evaluation of the Safety of the Situation/Justification for Continued Operations (ESS/JCO) "that will lower overall facility MAR limits and replace the CST limit with new limits on combustible waste," and conducted an accident analysis "for the 17 design basis accidents affected by the CST issues." It also says personnel placed the facility in operations mode to conduct sampling activities on waste drums as part of their effort "to improve the safety posture of Area G while the facility is in WARM STANDBY mode."

LANL spokesman Peter Hyde said by email that the “analysis and development” of the ESS/JCO for Area G “is on-going” and that “the final document has not been submitted to Los Alamos Field Office for review and approval.”

“Upon approval of the ESS/JCO, LANL will be authorized to safely return to operations mode following an independent verification review that all controls are properly implemented,” Hyde said. “It is not possible at this time to project a date as to when this would be completed but it is expected to occur within the next several weeks.”

 

 

In This Issue

More on This Topic


WIPP representatives outline plans for nearly six-month outage in 2027

The Department of Energy’s Waste Isolation Pilot Plant plans (WIPP) currently plans to begin a nearly six-month outage for waste hoist upgrades in July 2027, with work expected to finish in early January 2028, officials said during a Nov. 4 community forum.

The work will include upgrades to the waste hoist control and electrical systems, repairs to the shaft sump and refurbishment of related hoisting equipment. The project is part of WIPP’s longer-term infrastructure improvements outlined in DOE 2021-2031 strategic plan. 

DOE’s Carlsbad Field Office in New Mexico and WIPP’s Bechtel-led prime have been discussing the 2027 outage for some time. WIPP is the nation’s only deep underground disposal site for defense-related transuranic waste. 

The usual January maintenance period has been shifted and extended to accommodate the work. Salado Isolation Mining Contractors Deputy Program Manager Ryan Flynn said the schedule was developed in coordination with generator sites over the past year, taking their shipping preferences and contractor availability into account.

DOE and WIPP are coordinating with various DOE generator sites to reduce waste inventories at their facilities before the outage. Officials said waste generated during the work would be stored at the origin locations. Under current WIPP permit requirements, the repository can also store limited quantities of contact-handled transuranic mixed waste in its waste handling building for up to 60 days.

During fiscal 2026, ended Sept. 30, WIPP received 306 shipments, exceeding its annual  target by six, according to its online slide presentation. The number of transuranic waste shipments coming from Los Alamos National Laboratory amounted to 116 during the past fiscal year. 

DOE and the New Mexico Environment Department are continuing to negotiate a WIPP permit modification that could prioritize more shipments from Los Alamos.

Video of the meeting is available online. 