NNSA sets $23.5 billion baseline for SRPPF main building

The National Nuclear Security Administration (NNSA) has set a $23.5 billion performance baseline for the Savannah River Plutonium Processing Facility’s (SRPPF) main processing building, with completion now estimated for December 2038, the agency told Exchange…