Senator Drops Hold on EM-1 Nominee, But Confirmation Schedule Still Uncertain
Mike Nartker WC Monitor 12/12/2014 Sen. John Barrasso (R-Wyo.) has dropped his hold on Monica Regalbuto’s nomination to serve as the next Assistant Secretary of Energy for Environmental Management, but it remains to be seen if she’ll be confirmed by the Senate before the current Congress goes out of session, expected next week. Barrasso chose […]
-
Transuranic Waste
As New Mexico Levies $54 Million Penalty, DOE Examining Path Forward
Kenneth Fletcher WC Monitor 12/12/2014 After New Mexico levied $54.3 million in fines for violations this year at Los Alamos and the Waste Isolation Pilot Plant and warned of potentially even larger fines down the road, the Department of Energy is examining its path forward. The New Mexico Environment Department levied a $17.7 million fine […]
-
Cleanup & Remediation
Idaho Waste Treatment Facility Takes Major Step Forward in Startup Process
Still Uncertain, Though, When Facility Will Begin Operation Mike Nartker WC Monitor 12/12/2014 The Idaho Integrated Waste Treatment Unit reached a significant milestone in its startup process last week, but it could be well into 2015 before the facility begins processing actual radioactive waste. On Dec. 2, a waste simulant was introduced into the IWTU […]
-
Contracts & Procurement
Lengthy Dispute Over Small DOE Support Contract May Now Be Over
Unsuccessful Bidder Has Challenged Winner’s Ability to Meet Size Standard Mike Nartker WC Monitor 12/12/2014 A lengthy dispute over a small Department of Energy support contract may now be over, with the Small Business Administration’s Office of Hearings and Appeals denying this week a second appeal filed by an unsuccessful bidder challenging the contract winner’s […]
-
Uranium Enrichment & Fuel Cycle
DOE Gearing Up For Procurement for New DUF6 Operations Contract
Mike Nartker WC Monitor 12/12/2014 The Department of Energy is gearing up for the procurement for a new contract to operate DOE’s two depleted uranium hexafluoride conversion plants, announcing Dec. 8 that a draft Request for Proposals for the contract is expected to be released within 45 days. DOE also released this week a draft […]
-
Contracts & Procurement
DOE Seeks Companies Interested in Scope Planning Work for Los Alamos Transition
Kenneth Fletcher WC Monitor 12/12/2014 The Department of Energy this week released a sources sought notice for 8(a) small businesses interested in performing scope planning work for upcoming transition contracts for legacy cleanup work at Los Alamos National Laboratory. DOE is looking to transition administration of the cleanup work from National Nuclear Security Administration management […]
-
Contracts & Procurement
DOE Issues Final RFP for Portsmouth Support Services
Kenneth Fletcher WC Monitor 12/12/2014 The Department of Energy this week released a final Request for Proposals for a small business contract for infrastructure support services at the Portsmouth Gaseous Diffusion Plant. “A firm-fixed-price, labor hour, cost reimbursement, and indefinite delivery/indefinite quantity contract will be awarded from this Final RFP. The total estimated value of […]
-
Uranium Enrichment & Fuel Cycle
New Determination on DOE Uranium Transfers In the Works, Department Seeks Input
Kenneth Fletcher WC Monitor 12/12/2014 The Department of Energy is planning to develop a new secretarial determination regarding its uranium transfers to cover cleanup work at Portsmouth and the downblending of highly-enriched uranium, releasing last week a request for information from the public about potential impacts on the uranium markets. The move comes after industry […]
-
Contracts & Procurement
After Challenge, DOE Suspends LANL Natural Resources Damage Assessment Procurement
Kenneth Fletcher WC Monitor 12/12/2012 The Department of Energy has suspended a small business procurement for a Natural Resources Damage Assessment and Restoration Plan for Los Alamos National Laboratory pending the outcome of a challenge to the size standard used. The firm Environment International Ltd. filed the appeal of the 500 person size standard to […]
-
Cleanup & Remediation
Washington State Proposal for Hanford Cleanup Would Cost $18B, Fed. Government Says
Criticism Goes Back and Forth on Proposals to Modify Consent Decree Staff Reports WC Monitor 12/12/2014 New Hanford milestones the state of Washington has asked a federal judge to approve would require an extra $18 billion by Fiscal Year 2029, jeopardizing other Department of Energy cleanup projects across the nation, according to the federal government. […]
-
Cleanup & Remediation
Rep. Fleischmann Takes Helm of Congressional Nuclear Cleanup Caucus
Kenneth Fletcher WC Monitor 12/12/2014 With Congressional Nuclear Cleanup Caucus Chairman Rep. Doc Hastings (R-Wash.) set to retire next month, Rep. Chuck Fleischmann (R-Tenn.) this week announced that he will be leading the group. The caucus is comprised of lawmakers with Department of Energy cleanup sites in their districts, and Fleischmann said he is looking […]
-
High-Level & Tank Waste
At River Protection
URS Changes Top Person at Hanford Waste Treatment Plant WC Monitor 12/12/2014 URS is changing out its top executive at the Hanford Waste Treatment Plant. Mark Lindholm has been named Chief Operating Officer for Hanford tank farms contractor Washington River Protection Solutions, effective Jan. 5, 2015, the contractor announced this week. He replaces Wyatt Clark, […]
-
Contracts & Procurement
At Idaho
AMWTP Contractor Earns $3.3 Million in Fee for FY 2014 WC Monitor 12/12/2014 Idaho Treatment Group, LLC, which is responsible for the Idaho Advanced Mixed Waste Treatment Project, earned $3.3 million out of an available $5.3 million in Fiscal Year 2014, according to information the Department of Energy released this week. ITG’s fee was based […]
-
Cleanup & Remediation
At Richland
CSC Ordered to Pay Back Wages to Two Former Hanford Workers WC Monitor 12/12/2014 Computer Sciences Corp. has been ordered to pay back wages to two former Hanford employees that the Occupational Safety and Health Administration found were laid off in violation of whistleblower laws. The former contractor at Hanford has been ordered to pay […]
-
Budget & Policy
Wrap Up
WC Monitor 12/12/2014 IN CONGRESS The Republican-led 114th Congress will retain the current chairs of the House Armed Services subcommittees on Strategic Forces, Seapower and Projection Forces, Tactical Air and Land Forces and Readiness. Reps. Mike Rogers (Ala.), J. Randy Forbes (Va.), Mike Turner (Ohio) and Rob Wittman (Va.) will head the respective groups, according […]
-
Cleanup & Remediation
U.K. Cleanup Focus
Dounreay Agrees to Improvements After Fire and Possible Release Kenneth Fletcher WC Monitor 12/5/2014 Site license company Dounreay Site Restoration Limited has agreed to take steps to improve operations after a fire and potential radiological release at the Scottish cleanup site’s tank farms, the company said last month. The incident occurred on Oct. 7 at […]
-
Contracts & Procurement
DOE Again Asks LM Support Services Contract Bidders to Extend Proposals
Incumbent to Receive Another Extension, To End of March Mike Nartker WC Monitor 12/5/2014 The long-running search for a new support services contractor for the Department of Energy’s Office of Legacy Management may now stretch into 2015, with DOE asking bidders this week to again extend their proposals’ expiration dates, this time by another six […]
-
Contracts & Procurement
CH2M Hill Dropping Bid For New Idaho Cleanup Contract
Company Part of Incumbent CH2M-WG Idaho Mike Nartker WC Monitor 12/5/2014 As industry officials await the release of a final request for proposals for the new Idaho Cleanup Project (ICP) Core contract, a major shakeup appears to be in the works among the teams that have reportedly formed to go after the job should the […]
-
Cleanup & Remediation
Survey: Approx. 60 Percent of EM Employees Satisfied With Jobs
Mike Nartker WC Monitor 12/5/2014 A survey of employees in the Department of Energy’s Office of Environmental Management has found that approximately 60 percent are satisfied with their jobs, but less are satisfied with the organization as a whole, according to information EM recently provided to WC Monitor. The results of the 2014 Federal Employee […]
-
- U.K. Cleanup Focus
- DOE Again Asks LM Support Services Contract Bidders to Extend Proposals
- CH2M Hill Dropping Bid For New Idaho Cleanup Contract
- Survey: Approx. 60 Percent of EM Employees Satisfied With Jobs
- New Mexico Set to Propose $35M Fine for LANL, Separate Major Fine for WIPP
- Senate Clears Some Pending DOE Nominees, But EM-1 Choice Still in Limbo
- DOE Officially Releases Details on Los Alamos Cleanup Transition to EM
- DOE Again Pushes Back Deadline for Bids on New Oak Ridge TWPC Contract
- Small Businesses Call For Improvements in DOE Contracting
- Former LANL Dep. Director Suspended from Gov’t Work
- Final FY15 Defense Bill Would Lower DNFSB Employee Cap
- Oak Ridge Mercury Strategy Complete, DOE Advancing Treatment Plant Design
- INTERA Drops Challenges to Navarro’s Win of New NNSS Contract
- Savannah River’s 235-F Risk Reduction Plan Delayed 29 Months
- After Acquisition and New Name, Security Firm Centerra Planning Expansion
- Final FY15 Defense Bill Would Establish Manhattan Project Park
- On WIPP
- At River Protection
- At Richland
- At Los Alamos
- At Oak Ridge
- Wrap Up
-
Cleanup & Remediation
New Mexico Set to Propose $35M Fine for LANL, Separate Major Fine for WIPP
Fines Connected to Both WIPP Incident and Los Alamos Cleanup Kenneth Fletcher WC Monitor 12/5/2014 The New Mexico Environment Department is planning in the next 10 days to take enforcement actions against the Department of Energy that could include about $35 million in fines related to cleanup issues at Los Alamos National Laboratory, with a […]
-
Budget & Policy
Senate Clears Some Pending DOE Nominees, But EM-1 Choice Still in Limbo
Mike Nartker WC Monitor 12/5/2014 The Senate moved forward late this week with approving a handful of pending Department of Energy nominations, but the White House’s choice to serve as the next head of the Office of Environmental Management still appears to remain in confirmation limbo. Franklin Orr was confirmed to serve as the new […]
-
Cleanup & Remediation
DOE Officially Releases Details on Los Alamos Cleanup Transition to EM
Kenneth Fletcher WC Monitor 12/5/2014 The Department of Energy this week officially released the details of plans for the 18-to-24-month period for the transition of management of legacy cleanup work at Los Alamos National Laboratory to the Office of Environmental Management from the National Nuclear Security Administration. As previously reported by WC Monitor, DOE plans […]
-
Transuranic Waste
DOE Again Pushes Back Deadline for Bids on New Oak Ridge TWPC Contract
Mike Nartker WC Monitor 12/5/2014 In apparent response to requests from potential bidders, the Department of Energy late this week pushed back the deadline for bids for the new contract to operate the Oak Ridge Transuranic Waste Processing Center, for a second time, to Dec. 23, from Dec. 11. The new extension was contained in […]
-
Contracts & Procurement
Small Businesses Call For Improvements in DOE Contracting
Kenneth Fletcher WC Monitor 12/5/2014 Industry officials called on the Department of Energy late last month to take a number of steps to improve small business contracting, including promoting more meaningful prime and subcontract opportunities that encourage business growth. A contracting task force formed by the Energy, Technology and Environmental Business Association discussed its recommendations […]
-
National Laboratories
Former LANL Dep. Director Suspended from Gov’t Work
Todd Jacobson WC Monitor 12/5/2014 Former Los Alamos National Laboratory Deputy Director Beth Sellers and her husband, Bill, have been suspended from doing work with the government and have been proposed for debarment, government records indicate. Sellers resigned as Los Alamos’ deputy director in March after an investigation by the Department of Energy’s Inspector General […]
-
Budget & Policy
Final FY15 Defense Bill Would Lower DNFSB Employee Cap
Mike Nartker and Kenneth Fletcher WC Monitor 12/5/2014 The Defense Nuclear Facilities Safety Board would see a cut of approximately 15 percent in the maximum number of employees it can have under the final version of the Fiscal Year 2015 defense authorization bill unveiled this week. The bill would limit the DNFSB to 130 employees, […]
-
Cleanup & Remediation
Oak Ridge Mercury Strategy Complete, DOE Advancing Treatment Plant Design
Kenneth Fletcher WC Monitor 12/5/2014 A strategy plan for dealing with mercury contamination at Oak Ridge has been completed by the Department of Energy and regulators, and DOE is moving forward with design work for a new treatment plant in hope of stating of construction in 2017, according to acting DOE Oak Ridge EM Manager […]
-
Contracts & Procurement
INTERA Drops Challenges to Navarro’s Win of New NNSS Contract
Portage Protest Still Pending Mike Nartker WC Monitor 12/5/2014 INTERA has dropped its pending challenges against Navarro Research and Engineering’s win of the new Nevada National Security Site environmental programs services contract. INTERA had filed a protest over Navarro’s win with the Government Accountability Office, and was in the midst of appealing a determination by […]
-
Cleanup & Remediation
Savannah River’s 235-F Risk Reduction Plan Delayed 29 Months
Kenneth Fletcher WC Monitor 12/5/2014 The completion of a risk reduction plan for Building 235-F at the Savannah River Site will be delayed 29 months due to budget setbacks, the Department of Energy told the Defense Nuclear Facilities Safety Board last week. The DNFSB formally urged action to reduce risk at the former plutonium processing […]