Y-12 RED TEAM RECOMMENDS MAJOR MGMT. CHANGE ON UPF, MAJOR NNSA PROJECTS

The Red Team that analyzed alternatives to the Uranium Processing Facility planned for the Y-12 National Security Complex also weighed in on management of the multi-billion-dollar facility, and NS&D Monitor has learned that the team recommended a major management change for the project. The recommendations of the team, led by Oak Ridge National Laboratory Director Thom Mason, have not been released, but officials with knowledge of the team’s report said the team recommended stripping the National Nuclear Security Administration’s Office of Acquisition and Project Management of its management responsibility for the project and moving it back under the agency’s weapons program. Such a move would be similar to the way projects are run in the Department of Energy’s Office of Science, and would address accountability issues that the team suggested have plagued UPF. The estimated price tag for the project ballooned in recent months to possibly more than $10 billion, forcing the NNSA to reconsider scaling back the facility.

As expected, the Red Team supported a move to a smaller facility that would allow the NNSA to move enriched uranium operations out of Y-12’s aging Building 9212, according to officials, but its criticism of the management of the project appear to be among the team’s most significant recommendations. The NNSA’s Office of Acquisition and Project Management was created in 2011 to help the agency get a handle on rising costs and delays to major construction projects, but officials have said the Red Team suggested APM has had an opposite effect, at least on UPF, separating management of the project from the program that is ultimately responsible for paying for the facility and running it. That has created a disconnect between the facility’s requirements and the rising cost of the project, officials with knowledge of the report said. The report is believed to suggest that APM could still play a significant role as a major advisor to the NNSA’s weapons program on major construction projects, but the final say on decision-making should rest with the weapons program.

More on This Topic


NNSA eyes 2027 RFQ for TEST 4 technical support contract

KNOXVILLE, Tenn. – The National Nuclear Security Administration expects to release a draft request for quotations (RFQ) for its Technical and Engineering Program Support 4 contract, or TEST 4, in January 2027, with the agency targeting contract performance beginning later that year.

B.J. Quigley, NNSA’s senior procurement executive, said at the Energy Technology and Environmental Business Association’s (ETEBA) annual conference Wednesday the agency is conducting market research through December as it develops the acquisition strategy for recompeting a TEST 4 contract. Quigley did not give any details on the contract.

NNSA is targeting an RFQ release between June and September 2027, with performance expected to begin Nov. 1, 2027, Quigley said during an industry panel.

The agency is seeking a more efficient and competitive approach to acquiring technical and engineering capabilities and views the contract as an opportunity to implement recent acquisition reforms, according to Quigley. NNSA is still considering how best to structure the procurement and is open to alternatives from industry, Quigley said in response to a question about whether the TEST 4 contract will proceed.

The TEST 4 procurement comes as NNSA seeks to accelerate its acquisition processes and make greater use of commercial approaches. Quigley said speed is increasingly viewed by the agency as a national-security issue, rather than simply an efficiency measure.

The agency is also examining alternative contracting mechanisms, including other transaction authorities and additional acquisition vehicles, as it seeks to give contracting officers more flexibility to select the approach best suited to individual requirements.

In This Issue






More on This Topic