Archive

Publications: Weapons Cleanup Monitor

  • At Idaho

    IWTU Enters Planned Outage Period WC Monitor 4/25/2014 The Idaho Integrated Waste Treatment Unit has entered into a planned outage period as the Department of Energy and contractor CH2M-WG Idaho get ready for the next stage of getting the facility ready to begin actual waste treatment. The outage period is expected to last approximately a […]

  • At Paducah

    DUF6 Plant Manager Leaves WC Monitor 4/25/2014 Tom Robinson has stepped down as B&W Conversion Services, LLC’s plant manager of the Paducah depleted uranium hexafluoride conversion plant. Robinson had served as manager of the Paducah plant since BWCS took over as managing contractor for the Department of Energy’s two DUF6 conversion plants (located at the […]

  • At Portsmouth

    Judge Blocks FBP from Hiring Pro2Serve Workers WC Monitor 4/25/2014 A federal judge late last week blocked Fluor-B&W Portsmouth, LLC, from hiring employees of Professional Project Services (Pro2Serve) at the Portsmouth D&D project. The judge partially granted a request from Pro2Serve for a temporary restraining order as it moves forward in its recently filed lawsuit […]

  • Wrap Up: In DOE, In The Industry

    WC Monitor 4/25/2014 IN DOE The Department of Energy is gearing up for an inquiry into an allegation of a hostile work environment within the DOE Office of Acquisition and Project Management. DOE issued a solicitation this week seeking a contractor to provide “fact finder services” to look into a “recent allegation” of a hostile […]

  • At West Valley

    DOE Conducts Market Research for Performance Assessments WC Monitor 4/25/2014 The Department of Energy is looking to see if small businesses are available that could perform probabilistic performance assessments and apply decision analysis tools to D&D work at the West Valley Demonstration Project, according to a sources sought notice released this week. DOE has begun […]

  • At Savannah River

    Readiness Assessment Delay for New H-Canyon Mission WC Monitor 4/25/2014 After delays last year due to conduct of operations issues, the Department of Energy has now pushed to May a planned readiness assessment for a new mission at Savannah River’s HB-Line to produce plutonium oxide for feedstock for the Mixed Oxide Fuel Fabrication Facility, WC […]

  • Wash. State Rejects DOE Proposal to Modify Hanford Consent Decree

    Mike Nartker WC Monitor 4/18/2014      Washington state late this week rejected a proposal put forward by the Department of Energy to modify the 2010 consent decree that governs the cleanup of Hanford’s tank waste. DOE had proposed employing a phased approach to getting the Hanford Waste Treatment Plant in operation that would entail […]

  • Two Months after WIPP Release, Still No ID of Contamination Source

    DOE Appoints Senderling, Teynor to Head Federal Recovery Team Kenneth Fletcher WC Monitor 4/18/2014 While this week marked two months since the Feb. 14 radiation release at the Waste Isolation Pilot Plant, teams entering the mine still have not identified the source of the incident. In the past week, the two recovery teams entered the […]

  • As SWPF Startup Talks Drag On, DOE Looking at Alternatives

    Kenneth Fletcher WC Monitor 4/18/2014 The Department of Energy is reportedly examining alternatives to commissioning the Savannah River Site’s Salt Waste Processing Facility as startup talks for the project with facility contractor Parsons have gone on for more than six months without resolution. Parsons submitted a “best and final offer” in late March for commissioning […]

  • K-25 Contamination in City Sludge Being Shipped to Perma-Fix Facility

    Kenneth Fletcher WC Monitor 4/18/2014 After technetium from the K-25 demolition ended up in an Oak Ridge city wastewater treatment plant, the Department of Energy is making progress in shipping contaminated sewer sludge to the Perma-Fix Northwest Richland facility for processing. Cleanup contractor URS-CH2M Oak Ridge, LLC, wrapped up recently the high-profile effort at the […]

  • DOE Seeks Comment on Benefits Test for Hanford 222-S Lab RFP

    Mike Nartker WC Monitor 4/18/2014 The Department of Energy is seeking industry comment as to whether an employee benefits test should be added to the planned Request for Proposals for the new contract to perform analysis and testing services at Hanford’s 222-S Laboratory. According to a notice issued this week, DOE is considering adding a […]

  • Senator Seeks Funding for DOE Program on Uranium/Thorium Sites

    Kenneth Fletcher WC Monitor 4/18/2014      While the Department of Energy is not seeking any funding next year for a program to reimburse the costs of cleaning up a set of sites that produced uranium and thorium, Sen. Richard Durbin (D-Ill.) has requested $54 million in Fiscal Year 2015 for the effort from Senate […]

  • UK Cleanup Focus

    Kenneth Fletcher WC Monitor 4/18/2014 NDA Launches Magnox Transition, No Challenges So Far  The Nuclear Decommissioning Authority has launched a five-month transition period for Cavendish Fluor Partnership to take over management of 10 Magnox power plants and two research reactor sites after no legal challenges to the contract award were filed during a recent 10-day […]

  • At River Protection

    Is State Too Focused on Tank Cleanup? The state of Washington’s focus on Hanford tank issues could come at a big price to work at the rest of the site, according to the Tri-City Development Council. TRIDEC warned Gov. Jay Inslee and Attorney General Bob Ferguson in a letter this week that some of those […]

  • Wrap Up: In Congress, In DOE

    IN CONGRESS The House Cleanup Caucus this week announced the schedule for this year’s set of briefings on specific Department of Energy cleanup sites. The schedule includes: — Idaho National Laboratory on April 30 at 4 p.m. in Room 1334 of the Longworth House Office Building; — Hanford’s Richland Operations Office on May 1 at […]

  • At Oak Ridge

    Questions Persist over Subcontractor Raid Three months after federal law enforcement agents raided the office of a subcontractor to URS-CH2M Oak Ridge, LLC (UCOR), the purpose of the raid remains unclear. On Jan. 16, agents with the FBI and the Department of Energy Inspector General’s Office removed records from the office of Transportation, Operations and […]

  • At Savannah River

    After Injury at DWPF, DOE Seeks Improvements The Department of Energy’s Office of Health, Safety and Security this week noted several issues as a result of an investigation into a shoulder injury last year suffered by a Savannah River Remediation worker. The injury occurred in March 2013 at the Defense Waste Processing Facility during replacement […]

  • Interim WTP Pretreatment System Could Cost $300M, DOE Official Says

    DOE, Washington State Looking to Start WTP LAW Facility Ahead of Other Portions of Plant Mike Nartker WC Monitor 4/11/2014 An interim pretreatment system to allow the Department of Energy to move forward with a proposal to begin operation of the Hanford Waste Treatment Plant’s Low Activity Waste Facility ahead of other portions of the […]

  • DNFSB Considering Establishing An Ombudsman Capability

    Board Working To Address Staff Morale Concerns Mike Nartker WC Monitor 4/11/2014 The Defense Nuclear Facilities Safety Board is considering establishing some sort of ombudsman capability as part of its efforts to address staff morale concerns, DNFSB Chairman Peter Winokur told WC Monitor this week. A new ombudsman was one of several recommendations developed by […]

  • DOE Taking More Time to ID Source of WIPP Rad. Release

    Kenneth Fletcher WC Monitor 4/11/2014 The push to identify the cause of the Feb. 14 radiation release at the Waste Isolation Pilot Plant continued this week, as workers moved to establish a third base underground. Last week, workers set up two bases of operations underground in areas free of contamination. While the Department of Energy […]

  • ITG in Talks with DOE on How it Can Earn Fee with WIPP Shutdown

      Mike Nartker WC Monitor 4/11/2014 With operations at the Waste Isolation Pilot Plant currently on hold, and the timetable for their resumption unclear, Idaho Treatment Group, LLC, is in discussions with the Department of Energy on modifying how it will be able to earn fee for operating the Advanced Mixed Waste Treatment Project. ITG […]

  • UK Cleanup Focus

    Dounreay Costs May Go up £200 Million Kenneth Fletcher WC Monitor 4/11/2014 The last eight double-shell waste tanks built at Hanford had only minor construction issues, according to the final construction review report released by the Department of Energy this week.  The review concluded that double-shell tanks in the AP Tank Farm were in better […]

  • FY15 Budget for Hanford Could Lead to Missed Milestones, Sen. Warns

      Mike Nartker  WC Monitor 4/11/2014 Sen. Patty Murray (D-Wash.) warned this week that the Department of Energy’s proposed Fiscal Year 2015 budget for Hanford could put milestones at risk of being missed. Hanford came in for one of the largest cuts in the DOE Office of Environmental Management’s  FY 2015 budget request—for work overseen […]

  • Ports. D&D Contractor Defends Plan To Descope Work from Pro2Serve

    Fluor-B&W Portsmouth Says It Can Save Money Mike Nartker WC Monitor 4/11/2014 Fluor-B&W Portsmouth, LLC, sought to defend its plan to self-perform some work at the Portsmouth D&D project currently being handled by Professional Project Services (Pro2Serve) in a court filing late last week. Pro2Serve is suing FBP in federal court, accusing it of seeking […]

  • DOE Cleanup Chief Defends Cut to FY15 Oak Ridge D&D

    Says Department Hopes to Begin U-233 Shipments to Nevada ‘Later This Year’ Mike Nartker WC Monitor 4/11/2014              Department of Energy cleanup chief David Huizenga this week defended DOE’s decision to seek a funding reduction for D&D activities at Oak Ridge in its Fiscal Year 2015 budget request. DOE is proposing to […]

  • ATL to Purchase DeNuke Services

    Sale to be Completed Within the Month Mike Nartker WC Monitor 4/11/2014 Advanced Technologies and Laboratories (ATL) has entered into an agreement to purchase DeNuke Services—a sale DeNuke Services President Fred Gardner said this week that he expects to complete within a month. “We’ve entered in a letter of intent and we’re selling all the […]

  • At River Protection

    Work Underway on Vit Plant Test Facility In about three weeks the control tower outside the Full Scale Vessel Test Facility at Washington State University Tri-Cities will grow to 90 feet tall, as part of an effort to geometrically mimic conditions at the Hanford Waste Treatment Plant’s Pretreatment Facility. The test facility, also called the […]

  • At Oak Ridge

    Will WAI Have Unfair Advantage for Sludge Contract? Some potential bidders on the new contract to provide architect and engineering services for design of the Sludge Processing Facility Buildouts Project at the Oak Ridge Transuranic Waste Processing Center appear to be concerned that Wastren Advantage may have an unfair advantage, according to a set of […]

  • At Savannah River

    SWPF, Tank Closure Teams Earn DOE Awards The Department of Energy this week doled out two Honor Awards related to tank waste cleanup at the Savannah River Site, one to the Salt Waste Processing Renegotiation Team and one to the tank closure team. The SWPF team negotiated a new agreement for the construction of the […]

  • Wrap Up: In DOE, In Congress, In the Industry

    IN DOE The current tension between the United States and Russia over Ukraine appears to have scuttled a planned Russian visit later this month to Hanford. A group of technical representatives from Russia’s mining and chemical combine, the Rosatom state nuclear energy corporation and the Russian embassy in the United States were scheduled to visit […]