Holtec International
A nuclear technology company specializing in used fuel storage and transport and decommissioning services, and the company restarting the Palisades Nuclear Plant.
-
Recommissioning & Restarts
Holtec announces power purchase agreement for Palisades; plant still needs DOE loan
Two electric cooperatives would purchase electricity generated by the Palisades Nuclear Generating Station in Michigan if the plant restarts, plant owner Holtec International said Tuesday in a statement. If Palisades restarts, something Holtec has said could happen in August 2025, if everything goes according to the company’s unprecedented plan, Wolverine Power Cooperative will purchase two […]
-
Recommissioning & Restarts
Holtec says Palisades could restart in August 2025; NRC pushback on environmental review
The shuttered Palisades Nuclear Power Plant in Michigan could restart in about two years, plant owner Holtec International told the Nuclear Regulatory Commission in a public meeting Tuesday. The date will depend among other things on whether Holtec, Jupiter, Fla., can get a billion-dollar loan from the Department of Energy, but it may also depend […]
-
Recommissioning & Restarts
Holtec says Palisades could restart in August 2025; NRC pushback on environmental review
The shuttered Palisades Nuclear Power Plant in Michigan could restart in about two years, plant owner Holtec International told the Nuclear Regulatory Commission in a public meeting Tuesday. The date will depend among other things on whether Holtec, Jupiter, Fla., can get a billion-dollar loan from the Department of Energy, but it may also depend […]
-
Commercial Decommissioning
New York effectively bans wastewater discharges from Indian Point
In a move with ramifications for Holtec International’s decommissioning of the Indian Point Energy Center, New York Gov. Kathy Hochul (D) on Friday signed into law a state ban on discharging radioactive wastewater into the Hudson River. Holtec would now face escalating fines for discharges into the Hudson. For a first time offense, Holtec would […]
-
Commercial Decommissioning
Holtec hits back at ex-CFO’s allegations of corporate overvaluing
In court documents filed Monday Holtec International, Jupiter, Fla., formally denied its ex-finance chief’s allegations that the company overvalued itself in an investor pitch. Holtec also said the former chief financial officer, Kevin O’Rourke, acted maliciously and breached a non-disclosure agreement by filing a lawsuit that detailed, among other things, Holtec’s attempts to woo Hyundai […]
-
Commercial Decommissioning
Holtec promotes two as part of leadership realignment
Looking toward a future as a developer of small nuclear reactors, Holtec International, Jupiter, Fla., added power generation to the responsibilities of its lead decommissioning executive, the company announced Monday. Kelly Trice is now president Nuclear Generation and Decommissioning for Holtec, the company wrote in a press release. In his new role, Kelly will now […]
-
Recommissioning & Restarts
Holtec headed to NRC headquarters for open meeting about proposed Palisades restart
Holtec International planned to meet with Nuclear Regulatory Commission staff Aug. 29 to discuss what the company says is the biggest regulatory hurdle to restarting the Palisades Nuclear Generating Station. The commission posted a notice of the meeting online Tuesday. Executives with Holtec International will join members of the NRC’s Office of Nuclear Reactor Regulation and Office […]
-
Recommissioning & Restarts
Holtec headed to NRC headquarters for open meeting about proposed Palisades restart
Holtec International planned to meet with Nuclear Regulatory Commission staff Aug. 29 to discuss what the company says is the biggest regulatory hurdle to restarting the Palisades Nuclear Generating Station. The commission posted a notice of the meeting online Tuesday. Executives with Holtec International will join members of the NRC’s Office of Nuclear Reactor Regulation […]
-
Commercial Decommissioning
After Healey administration blocks Pilgrim discharge, lawmakers pull wastewater commission from state budget
The Massachusetts legislature stripped a proposal to create a radioactive wastewater commission from the final version of the state budget sent to the governor this week. Lawmakers sent a compromise version of the state’s $56-billion budget proposal to Gov. Maura Healey (D) on Monday after a six-person conference committee of the state’s bicameral legislature hammered […]
-
Decommissioning
Michigan approves financial aid for Palisades restart
Michigan Gov. Gretchen Whitmer (D) on Monday signed into law a state budget that would conditionally provide $150 million to restart the Palisades Nuclear Generating Station in Covert county. The funding, about half of what plant owner Holtec International says it needs from the state, is contingent on the federal Department of Energy providing a […]
-
Commercial Decommissioning
More than a month after passage, NY state ban on irradiated wastewater discharges no closer to law
Locals and activists this week renewed calls for New York Gov. Kathy Hochul (D) to sign the legislature’s ban on radioactive wastewater discharges into the Hudson River, but the governor made no move. In a meeting this week of the Indian Point Decommissioning Oversight Board, state officials got an earful from locals and activists who […]
-
Recommissioning & Restarts
Michigan approves financial aid for Palisades restart
Michigan Gov. Gretchen Whitmer (D) on Monday signed into law a state budget that would conditionally provide $150 million to restart the Palisades Nuclear Generating Station in Covert county. The funding, about half of what plant owner Holtec International says it needs from the state, is contingent on the federal Department of Energy providing a […]
-
Commercial Decommissioning
After Healey administration blocks Pilgrim discharge, lawmakers pull wastewater commission from state budget
The Massachusetts legislature stripped a proposal to create a radioactive wastewater commission from the final version of the state budget sent to the governor on Monday. Lawmakers sent a compromise version of the state’s $56-billion budget proposal to Gov. Maura Healey (D) on Monday after a six-person conference committee of the state’s bicameral legislature hammered […]
-
Commercial Decommissioning
Massachusetts blocks wastewater discharges from Pilgrim
Massachusetts on Monday forbade Holtec International from discharging irradiated wastewater into Cape Cod Bay from the Pilgrim Nuclear Power Plant, but the company could still get a federal permit to do so. The state Department of Environmental Protection published the decision in a tentative determination to deny Holtec’s application to modify a discharge permit the […]
-
Commercial Decommissioning
Massachusetts blocks wastewater discharges from Pilgrim
Massachusetts on Monday forbade Holtec International from discharging irradiated wastewater into Cape Cod Bay from the Pilgrim Nuclear Power Plant, but the company could still get a federal permit to do so. The state Department of Environmental Protection published the decision in a tentative determination to deny Holtec’s application to modify a discharge permit the […]
-
Recommissioning & Restarts
DOE weighing ‘options’ for Palisades financial aid, official says
The Department of Energy is still considering how and whether it will help bail out a shuttered power plant in Michigan, a senior agency official testified this week in Congress. Plant owner Holtec International, Jupiter, Fla., seeks a roughly $1 billion loan for DOE and said this spring that the federal agency could conditionally approve […]
-
Interim Storage & Waste Disposal
Holtec overvalued itself in investor pitch; interim storage a money pit, ex-CFO says in lawsuit
To net an investment from Hyundai, Holtec International, Camden, N.J., wanted to lie about its value and about the prospects for its proposed interim spent-fuel storage business, a former Holtec executive alleged. Kevin O’Rourke, Holtec’s former chief financial officer, said he was fired in 2022 after about a year on the job for refusing to […]
-
Interim Storage & Waste Disposal
Holtec overvalued itself in investor pitch; interim storage a money pit, ex-CFO says in lawsuit
To net an investment from Hyundai, Holtec International, Camden, N.J., wanted to lie about its value and about the prospects for its proposed interim spent-fuel storage business, a former Holtec executive alleged. Kevin O’Rourke, Holtec’s former chief financial officer, said he was fired in 2022 after about a year on the job for refusing to […]
-
Recommissioning & Restarts
Michigan legislature approves $150M for Palisades restart
The Michigan legislature on Wednesday evening easily passed a bill that would provide a $150-million grant to help restart the Palisades Nuclear Generating Station in Covert County. If signed by Michigan Gov. Gretchen Whitmer, the bill would provide half the funding that Holtec International, the current Palisades owner, has said it needed from the state […]
-
Decommissioning
Antis tell Michigan lawmakers not to fund Palisades restart
Antinuclear activists on Wednesday sent a letter to the Michigan legislature urging state lawmakers not to approve a $300 million grant to help Holtec International restart the Palisades Nuclear Generating Station. In a letter dated Wednesday and mailed to all 148 michigan lawmakers — 110 representatives and 38 senators — 79 people and 43 organizations […]
-
Commercial Decommissioning
NY Gov undecided on bill banning Indian Point wastewater discharges
New York’s governor had yet to decide whether she would sign a bill, passed Monday by the state legislature, that would punish anyone who discharges irradiated water into the Hudson River. The bill, S06893, passed the General Assembly 101-44 on the first day of a special session of the bicameral legislature’s lower chamber, where Democrats […]
-
Decommissioning
NY Gov undecided on bill banning Indian Point wastewater discharges
New York’s governor had yet to decide whether she would sign a bill, passed Monday by the state legislature, that would punish anyone who discharges irradiated water into the Hudson River. The bill, S06893, passed the General Assembly 101-44 on the first day of a special session of the bicameral legislature’s lower chamber, where Democrats […]
-
Decommissioning
New York lawmakers return to Albany to weigh Indian Point wastewater ban
New York state lawmakers were set to convene for a special session on Tuesday that will include consideration of a bill prohibiting discharge of irradiated wastewater into the Hudson River. The bill, S06893, would make it “unlawful to discharge any radiological substance into the Hudson River in connection with the decommissioning of a nuclear power […]
-
Commercial Decommissioning
New York lawmakers could soon return to Albany to ban Indian Point wastewater discharges
The New York state legislature could return to Albany for a special session, during which the body’s state Assembly could take up a bill passed by the state Senate that would ban discharge of irradiated water into the Hudson River. The local Albany Times Union reported June 10 that lawmakers in the Assembly could return for a […]
-
Recommissioning & Restarts
Holtec having ‘conversations’ with potential Palisades operators
SUMMERLIN, NEV — Holtec International is considering several companies as possible operators of the Palisades Nuclear Generating Station in Michigan, which the Florida-based decommissioning company hopes to restart, a company representative said here Thursday. “We’ve been involved in conversations with a couple of different potential buyers for the power,” Patrick O’Brien, director of government affairs […]
-
Decommissioning
With hope for wastewater ban fading in New York, state lawmakers, antinukers pressure gov
Antinuclear activists and state lawmakers on Tuesday demonstrated outside the New York governor’s office, demanding that she sign a bill to outlaw dumping of irradiated waste water into the Hudson River from the shuttered Indian Point Nuclear Energy Center. Food & Water Watch, a Washington-based nonprofit founded by activist Wenonah Hauter of Virginia, publicized the […]
-
Interim Storage & Waste Disposal
Holtec says funding fight for Palisades restart could be won or lost by July
Holtec International will know by June or July whether it will get the funds it wants to restart the shuttered Palisades Nuclear Generating Station in Calvert, Mich., executives told Nuclear Regulatory Commission staff Wednesday. It was the most specific public timetable Holtec has set yet for the full-court fundraising press the company initiated to restart […]
-
Interim Storage & Waste Disposal
Holtec says funding fight for Palisades restart could be won or lost by July
Holtec International will know by June or July whether it will get the funds it wants to restart the shuttered Palisades Nuclear Generating Station in Calvert, Mich., executives told Nuclear Regulatory Commission staff Wednesday. It was the most specific public timetable Holtec has set yet for the full-court fundraising press the company initiated to restart […]
-
Decommissioning
NRC to hear details about Palisades restart, Diablo Canyon extension
Holtec International and Pacific Gas and Electric were scheduled to speak to Nuclear Regulatory Commission staff on Wednesday about novel regulatory efforts to extend the lives of two nuclear power plants. Holtec International, Jupiter, Fla., was scheduled to go first, with their 10:00 a.m. Eastern presentation to commission staff about the regulatory pathway to restart […]
-
Interim Storage & Waste Disposal
NRC licenses Holtec to store spent nuclear fuel in New Mexico; New Mexico pols oppose
The Nuclear Regulatory Commission this week licensed Holtec International to operate a consolidated interim storage facility for spent nuclear fuel in New Mexico, where politicians vowed to block the project. Holtec’s is one of two proposed consolidated interim storage facilities the NRC has licensed over the last two years to receive spent fuel. If built, […]